The following information and diagram apply to a project:


The earliest completion time for the project is:

  1. 11 days.
  2. 14 days.
  3. 15 days.
  4. 20 days.

Answer(s): C

Explanation:

The two paths through the network are A-C-E (5+4 + 6= 15days) and B-D-E (3 + 2 + 6 = 11 days). The critical or longest path is thus A-C-E. Hence, the earliest completion time is 15 days.



Which of the following terms is not used in project management?

  1. Dummy activity.
  2. Latest finish.
  3. Optimistic time.
  4. Lumpy demand.

Answer(s): D

Explanation:

Project management concerns managing teams assigned to special projects. Lumpy demand refers to periodic demand for a product or service that increases in large, lumpy increments.



Activity scheduling information for the installation of a new computer system is given below.


For this project, the critical path is:

  1. A-C
  2. B-E
  3. A-D-E
  4. B-D-C

Answer(s): C

Explanation:

The critical path is the longest path because it defines the minimum duration of the project. A-D-E (4 + 6 + 5 = 15 days) is the critical path.



In a critical path analysis, if slack time in an activity exists, the activity:

  1. Is not essential to the overall project.
  2. Is a backup activity to replace a main activity should it fail.
  3. Could be delayed without delaying the overall project.
  4. Involves essentially no time to complete.

Answer(s): C

Explanation:

Slack is the free time associated with activities not on the critical path. Slack represents unused resources that can be diverted to the critical path.



Various tools are employed to control large scale projects. They include all of the following except:

  1. PERT.
  2. CPM.
  3. Statistical process control.
  4. Gantt charts.

Answer(s): C

Explanation:

Statistical process (quality) control is not used to control large scale projects. Statistical quality control is a method of determining whether the shipment or production run of units lies within acceptable limits. It is also used to determine whether production processes are out of control.



Share your comments for IIA IIA-CIA-PART3-3P exam with other users:

A
Az
9/16/2023 2:43:00 PM

q75. azure files is pass

K
ketty
11/9/2023 8:10:00 AM

very helpful

S
Sonail
5/2/2022 1:36:00 PM

thank you for these questions. it helped a lot.

S
Shariq
7/28/2023 8:00:00 AM

how do i get the h12-724 dumps

A
adi
10/30/2023 11:51:00 PM

nice data dumps

E
EDITH NCUBE
7/25/2023 7:28:00 AM

answers are correct

R
Raja
6/20/2023 4:38:00 AM

good explanation

B
BigMouthDog
1/22/2022 8:17:00 PM

hi team just want to know if there is any update version of the exam 350-401

F
francesco
10/30/2023 11:08:00 AM

helpful on 2017 scrum guide

A
Amitabha Roy
10/5/2023 3:16:00 AM

planning to attempt for the exam.

P
Prem Yadav
7/29/2023 6:20:00 AM

pleaseee upload

A
Ahmed Hashi
7/6/2023 5:40:00 PM

thanks ly so i have information cia

M
mansi
5/31/2023 7:58:00 AM

hello team, i need sap qm dumps for practice

J
Jamil aljamil
12/4/2023 4:47:00 AM

it’s good but not senatios based

C
Cath
10/10/2023 10:19:00 AM

q.119 - the correct answer is b - they are not captured in an update set as theyre data.

P
P
1/6/2024 11:22:00 AM

good matter

S
surya
7/30/2023 2:02:00 PM

please upload c_sacp_2308

S
Sasuke
7/11/2023 10:30:00 PM

please upload the dump. thanks very much !!

V
V
7/4/2023 8:57:00 AM

good questions

T
TTB
8/22/2023 5:30:00 AM

hi, could you please update the latest dump version

T
T
7/28/2023 9:06:00 PM

this question is keep repeat : you are developing a sales application that will contain several azure cloud services and handle different components of a transaction. different cloud services will process customer orders, billing, payment, inventory, and shipping. you need to recommend a solution to enable the cloud services to asynchronously communicate transaction information by using xml messages. what should you include in the recommendation?

G
Gurgaon
9/28/2023 4:35:00 AM

great questions

W
wasif
10/11/2023 2:22:00 AM

its realy good

S
Shubhra Rathi
8/26/2023 1:12:00 PM

oracle 1z0-1059-22 dumps

L
Leo
7/29/2023 8:48:00 AM

please share me the pdf..

A
AbedRabbou Alaqabna
12/18/2023 3:10:00 AM

q50: which two functions can be used by an end user when pivoting an interactive report? the correct answer is a, c because we do not have rank in the function pivoting you can check in the apex app

R
Rohan Limaye
12/30/2023 8:52:00 AM

best to practice

A
Aparajeeta
10/13/2023 2:42:00 PM

so far it is good

V
Vgf
7/20/2023 3:59:00 PM

please provide me the dump

D
Deno
10/25/2023 1:14:00 AM

i failed the cisa exam today. but i have found all the questions that were on the exam to be on this site.

C
CiscoStudent
11/15/2023 5:29:00 AM

in question 272 the right answer states that an autonomous acces point is "configured and managed by the wlc" but this is not what i have learned in my ccna course. is this a mistake? i understand that lightweight aps are managed by wlc while autonomous work as standalones on the wlan.

P
pankaj
9/28/2023 4:36:00 AM

it was helpful

U
User123
10/8/2023 9:59:00 AM

good question

V
vinay
9/4/2023 10:23:00 AM

really nice

AI Tutor 👋 I’m here to help!