A Gantt chart:
Answer(s): D
The major advantage of a Gantt chart is its simplicity: It requires no special tools or mathematics. However, it depicts only the interrelationships between tasks in a limited way. Thus, trying to identify a project's critical path from a Gantt chart may not be feasible.
In the Gantt chart below, shaded bars represent completed portions of activities, bars depicted with broken lines represent uncompleted portions, and blank bars represent activities notyet begun.As of week 8, the Gantt chart shows that the project is:
Answer(s): C
Activities B and C are the only activities that should be underway during week 8. Since both are underway and on schedule, the project is on schedule.
When using PERT (Program Evaluation Review Technique), the expected time for an activity when given an optimistic time (a), a pessimistic time (b),andamostlikelytime(m) is calculated by which one of the following formulas?
PERT was developed to aid managers in controlling large, complex projects. PERT analysis includes probabilistic estimates of activity completion times. Three time estimates are made:optimistic, most likely, and pessimistic. The time estimates for an activity are assumed to approximate a beta probability distribution. PERT approximates the mean of the beta distribution by dividing the sum of the optimistic time, the pessimistic time, and four times the most likely time by six.
The process of adding resources to shorten selected activity times on the critical path in project scheduling is called:
Answer(s): A
Crashing is the process of adding resources to shorten activity times on the critical path in project scheduling.
The network diagram and the corresponding activity cost chart for a manufacturing project at Networks, Inc., are presented below. The numbers in the diagram are the expected times (in days) to perform each activity in the project.The expected time of the critical path is:
Answer(s): B
The critical path is the longest path. The longest path in the diagram is A-D-E, which requires 13 days (5.5 + 7.5) based on expected times.
Share your comments for IIA IIA-CIA-PART3-3P exam with other users:
q6 = 1. download odt application 2. create a configuration file (xml) 3. setup.exe /download to download the installation files 4. setup.exe /configure to deploy the application
great material
could you please upload sap c_arsor_2302 questions? it will be very much helpful.
vraag 20c: rsa veilig voor symmtrische cryptografie? antwoord c is toch fout. rsa is voor asymmetrische cryptogafie??
so far good
question 31 has obviously wrong answers. tls and ssl are used to encrypt data at transit, not at rest.
pls provide dump for 1z0-1080-23 planning exams
could you please upload the exam?
please upload this
good material
lets see if this is good stuff...
useful information
intéressant
thank you for making the interactive questions
questions are accurate
i need questions/dumps for this exam.
i need this exam, when will it be uploaded
i need the dumps !
very helpful
good source
my 3rd test and passed on first try. hats off to this brain dumps site.
please upload it
does anybody know if are these real exam questions?
are these questions similar to actual questions in the exam? because they seem to be too easy
i have a lot of experience but what comes in the exam is totally different from the practical day to day tasks. so i thought i would rather rely on these brain dumps rather failing the exam.
good questions
valied exam dumps. they were very helpful and i got a pretty good score. i am very grateful for this service and exam questions
will it help?
very useful to verify knowledge before exam
good stuffs
question 17 : responses arent b and c ?
just passed the exam on my first try using these dumps.
these questions look good.