A Gantt chart:
Answer(s): D
The major advantage of a Gantt chart is its simplicity: It requires no special tools or mathematics. However, it depicts only the interrelationships between tasks in a limited way. Thus, trying to identify a project's critical path from a Gantt chart may not be feasible.
In the Gantt chart below, shaded bars represent completed portions of activities, bars depicted with broken lines represent uncompleted portions, and blank bars represent activities notyet begun.As of week 8, the Gantt chart shows that the project is:
Answer(s): C
Activities B and C are the only activities that should be underway during week 8. Since both are underway and on schedule, the project is on schedule.
When using PERT (Program Evaluation Review Technique), the expected time for an activity when given an optimistic time (a), a pessimistic time (b),andamostlikelytime(m) is calculated by which one of the following formulas?
PERT was developed to aid managers in controlling large, complex projects. PERT analysis includes probabilistic estimates of activity completion times. Three time estimates are made:optimistic, most likely, and pessimistic. The time estimates for an activity are assumed to approximate a beta probability distribution. PERT approximates the mean of the beta distribution by dividing the sum of the optimistic time, the pessimistic time, and four times the most likely time by six.
The process of adding resources to shorten selected activity times on the critical path in project scheduling is called:
Answer(s): A
Crashing is the process of adding resources to shorten activity times on the critical path in project scheduling.
The network diagram and the corresponding activity cost chart for a manufacturing project at Networks, Inc., are presented below. The numbers in the diagram are the expected times (in days) to perform each activity in the project.The expected time of the critical path is:
Answer(s): B
The critical path is the longest path. The longest path in the diagram is A-D-E, which requires 13 days (5.5 + 7.5) based on expected times.
Share your comments for IIA IIA-CIA-PART3-3P exam with other users:
good questions
hello are these questions valid for ms-102
some questions are wrongly answered but its good nonetheless
how to get system serial number using intune
is it really helpful to pass the exam
#229 in incorrect - all the customers require an annual review
kindy upload
fantastic assessment on psm 1
56 question correct answer a,b
thank you for providing the q bank
true quesstions
i can´t believe ms asks things like this, seems to be only marketing material.
hi, could you please add the last update of ns0-527
question #3 refers to vnet4 and vnet5. however, there is no vnet5 listed in the case study (testlet 2).
sometimes it may be good some times it may be
qs 4 answer seems wrong- please check
very detailed explanation !
the interactive nature of the test engine application makes the preparation process less boring.
very useful.
complete question dump should be made available for practice.
i just passed my first exam. i got 2 exam dumps as part of the 50% sale. my second exam is under work. once i write that exam i report my result. but so far i am confident.
nice create dewey stefen
i just wrote this exam and it is still valid. the questions are exactly the same but there are about 4 or 5 questions that are answered incorrectly. so watch out for those. best of luck with your exam.
passed my exam today. this is a good start to 2023.
great sharing
very helpful
thanks.. very helpful
i registered for 1z0-1047-23 but dumps qre available for 1z0-1047-22. help me with this...
please upload oracle 1z0-1110-22 exam pdf
becoming interesting on the logical part of the cdbs and pdbs
some of the answers are incorrect, i would be wary of using this until an admin goes back and reviews all the answers
question # 267: federated operating model is also correct.
its helpful alot.