A Gantt chart:
Answer(s): D
The major advantage of a Gantt chart is its simplicity: It requires no special tools or mathematics. However, it depicts only the interrelationships between tasks in a limited way. Thus, trying to identify a project's critical path from a Gantt chart may not be feasible.
In the Gantt chart below, shaded bars represent completed portions of activities, bars depicted with broken lines represent uncompleted portions, and blank bars represent activities notyet begun.As of week 8, the Gantt chart shows that the project is:
Answer(s): C
Activities B and C are the only activities that should be underway during week 8. Since both are underway and on schedule, the project is on schedule.
When using PERT (Program Evaluation Review Technique), the expected time for an activity when given an optimistic time (a), a pessimistic time (b),andamostlikelytime(m) is calculated by which one of the following formulas?
PERT was developed to aid managers in controlling large, complex projects. PERT analysis includes probabilistic estimates of activity completion times. Three time estimates are made:optimistic, most likely, and pessimistic. The time estimates for an activity are assumed to approximate a beta probability distribution. PERT approximates the mean of the beta distribution by dividing the sum of the optimistic time, the pessimistic time, and four times the most likely time by six.
The process of adding resources to shorten selected activity times on the critical path in project scheduling is called:
Answer(s): A
Crashing is the process of adding resources to shorten activity times on the critical path in project scheduling.
The network diagram and the corresponding activity cost chart for a manufacturing project at Networks, Inc., are presented below. The numbers in the diagram are the expected times (in days) to perform each activity in the project.The expected time of the critical path is:
Answer(s): B
The critical path is the longest path. The longest path in the diagram is A-D-E, which requires 13 days (5.5 + 7.5) based on expected times.
Share your comments for IIA IIA-CIA-PART3-3P exam with other users:
nice document
thank you for making the questions and answers intractive and selectable.
answers are correct?
can i belive this dump
great site to practice for sitecore exam
good for students
nice practice dumps
nokia 4a0-114 dumps
great content and wonderful to have the answers with explanation
for question #118, the answer is option c. the screen shot is showing the drop down, but the answer is marked incorrectly please update . thanks for sharing such nice questions.
the correct answer for the question 29 is d.
question no 22: correct answers: bc, 1 per session 1 per page 1 per component always
these are pretty useful
awesome
yes please upload
great job whoever put this together, for the greater good! thanks!
just started to view all questions for the exam
helpful material
hope for the best
will post exam has finished
really correct and good analyze!
excellent thanks a lot
will post once pass the cka exam
good content
q:32 answer has to be option c
nice questions
i really like the support team in this website. they are fast in communication and very helpful.
a good contemporary exam review
q23, its an array, isnt it? starts with [ and end with ]. its an array of objects, not object.
cool very helpfull
i just passed. this exam dumps is the same one from prepaway and examcollection. it has all the real test questions.
is this a valid prince2 practitioner dumps?
all are relatable questions
might help me to prepare for the exam