The seller tells you that your activities have resulted in an increase in their costs. You should:

  1. Recommend a change to the project costs.
  2. Have a meeting with management to find out what to do.
  3. Ask the seller for supporting information.
  4. Deny any wrongdoing.

Answer(s): C



Which of the following is CORRECT?

  1. The critical path helps prove how long the project will take.
  2. There can be only one critical path.
  3. The network diagram will change every time the end date changes.
  4. A project can never have negative float.

Answer(s): A



Which of the following is CORRECT about quality improvements?

  1. They are a tool of Perform Quality Assurance and an output of Verify Scope.
  2. They require the preparation of change requests or the recommendation of corrective actions.
  3. They occur only through experience of the project manager, team, and sponsor.
  4. They are a product of cooperation between the customer and the project manager.

Answer(s): B



A problem occurs on an activity with free float and the project manager has extended its duration.
What is MOST likely to be affected?

  1. Project duration
  2. Resource schedules
  3. Project scope management plan
  4. The latest start for the successor activity

Answer(s): B



Which of the following is NOT a reason to measure variances from the baseline?

  1. To catch deviations early
  2. To allow early corrective action
  3. To determine if there are any wild fluctuations
  4. To create a project control system

Answer(s): D



Viewing Page 17 of 131



Share your comments for GAQM PPM-001 exam with other users:

Miguel 10/16/2023 11:18:00 AM

question 5, it seems a instead of d, because: - care plan = case - patient = person account - product = product2;
SPAIN


Byset 9/25/2023 12:49:00 AM

it look like real one
Anonymous


Debabrata Das 8/28/2023 8:42:00 AM

i am taking oracle fcc certification test next two days, pls share question dumps
Anonymous


nITA KALE 8/22/2023 1:57:00 AM

i need dumps
Anonymous


CV 9/9/2023 1:54:00 PM

its time to comptia sec+
GREECE


SkepticReader 8/1/2023 8:51:00 AM

question 35 has an answer for a different question. i believe the answer is "a" because it shut off the firewall. "0" in registry data means that its false (aka off).
UNITED STATES


Nabin 10/16/2023 4:58:00 AM

helpful content
MALAYSIA


Blessious Phiri 8/15/2023 3:19:00 PM

oracle 19c is complex db
Anonymous


Sreenivas 10/24/2023 12:59:00 AM

helpful for practice
Anonymous


Liz 9/11/2022 11:27:00 PM

support team is fast and deeply knowledgeable. i appreciate that a lot.
UNITED STATES


Namrata 7/15/2023 2:22:00 AM

helpful questions
Anonymous


lipsa 11/8/2023 12:54:00 PM

thanks for question
Anonymous


Eli 6/18/2023 11:27:00 PM

the software is provided for free so this is a big change. all other sites are charging for that. also that fucking examtopic site that says free is not free at all. you are hit with a pay-wall.
EUROPEAN UNION


open2exam 10/29/2023 1:14:00 PM

i need exam questions nca 6.5 any help please ?
Anonymous


Gerald 9/11/2023 12:22:00 PM

just took the comptia cybersecurity analyst (cysa+) - wished id seeing this before my exam
UNITED STATES


ryo 9/10/2023 2:27:00 PM

very helpful
MEXICO


Jamshed 6/20/2023 4:32:00 AM

i need this exam
PAKISTAN


Roberto Capra 6/14/2023 12:04:00 PM

nice questions... are these questions the same of the exam?
Anonymous


Synt 5/23/2023 9:33:00 PM

need to view
UNITED STATES


Vey 5/27/2023 12:06:00 AM

highly appreciate for your sharing.
CAMBODIA


Tshepang 8/18/2023 4:41:00 AM

kindly share this dump. thank you
Anonymous


Jay 9/26/2023 8:00:00 AM

link plz for download
UNITED STATES


Leo 10/30/2023 1:11:00 PM

data quality oecd
Anonymous


Blessious Phiri 8/13/2023 9:35:00 AM

rman is one good recovery technology
Anonymous


DiligentSam 9/30/2023 10:26:00 AM

need it thx
Anonymous


Vani 8/10/2023 8:11:00 PM

good questions
NEW ZEALAND


Fares 9/11/2023 5:00:00 AM

good one nice revision
Anonymous


Lingaraj 10/26/2023 1:27:00 AM

i love this thank you i need
Anonymous


Muhammad Rawish Siddiqui 12/5/2023 12:38:00 PM

question # 142: data governance is not one of the deliverables in the document and content management context diagram.
SAUDI ARABIA


al 6/7/2023 10:25:00 AM

most answers not correct here
Anonymous


Bano 1/19/2024 2:29:00 AM

what % of questions do we get in the real exam?
UNITED STATES


Oliviajames 10/25/2023 5:31:00 AM

i just want to tell you. i took my microsoft az-104 exam and passed it. your program was awesome. i especially liked your detailed questions and answers and practice tests that made me well-prepared for the exam. thanks to this website!!!
UNITED STATES


Divya 8/27/2023 12:31:00 PM

all the best
UNITED STATES


KY 1/1/2024 11:01:00 PM

very usefull document
Anonymous