While project work is being done, conflicts can arise between the procurement officer and the project manager because the procurement officer:

  1. Is the only one who can change the contract.
  2. Works for a different department.
  3. Needs to obtain the project manager's approval to make project changes.
  4. Has a different approach to creating a contract.

Answer(s): A



You are negotiating with a seller. Time is of the essence but you have a limited budget, and the seller knows this.
What is your BEST negotiating strategy under these circumstances?

  1. Focus the negotiation on seller's profit margin in order to decrease the project cost.
  2. Negotiate to get the work done even sooner than necessary in order to add a reserve.
  3. Negotiate identified risks.
  4. Arrange to reschedule the negotiation until you can acquire information of which the seller is not aware.

Answer(s): C



You receive 25 new computers from the seller, but were expecting only 20. In looking at the contract, you see that it says "seller to provide twenty (25) computers." What should you do FIRST?

  1. Issue a change order through the contract manager.
  2. Return the five extra computers.
  3. Make payment for the 25 computers.
  4. Call the seller and ask for clarification.

Answer(s): B



A project manager you are mentoring comes to you for help because he is about to face his first procurement audit. You might explain that he should NOT worry about such an audit because it:

  1. Identifies successes and failures that warrant transfer to other procurements.
  2. Makes sure the contract is being followed.
  3. Makes sure costs are in line with the project.
  4. Makes sure the seller is following the contract.

Answer(s): A



All of the following are typical concerns of matrixed team members EXCEPT:

  1. Wondering who will handle their evaluations.
  2. Serving multiple bosses.
  3. Developing commitment.
  4. Computing fringe benefits when working on multiple projects.

Answer(s): D



Viewing Page 16 of 131



Share your comments for GAQM PPM-001 exam with other users:

Mn8300 11/9/2023 8:53:00 AM

nice questions
Anonymous


Nico 4/23/2023 11:41:00 PM

my 3rd purcahse from this site. these exam dumps are helpful. very helpful.
ITALY


Chere 9/15/2023 4:21:00 AM

found it good
Anonymous


Thembelani 5/30/2023 2:47:00 AM

excellent material
Anonymous


vinesh phale 9/11/2023 2:51:00 AM

very helpfull
UNITED STATES


Bhagiii 11/4/2023 7:04:00 AM

well explained.
Anonymous


Rahul 8/8/2023 9:40:00 PM

i need the pdf, please.
CANADA


CW 7/11/2023 2:51:00 PM

a good source for exam preparation
UNITED STATES


Anchal 10/23/2023 4:01:00 PM

nice questions
INDIA


J Nunes 9/29/2023 8:19:00 AM

i need ielts general training audio guide questions
BRAZIL


Ananya 9/14/2023 5:16:00 AM

please make this content available
UNITED STATES


Swathi 6/4/2023 2:18:00 PM

content is good
Anonymous


Leo 7/29/2023 8:45:00 AM

latest dumps please
INDIA


Laolu 2/15/2023 11:04:00 PM

aside from pdf the test engine software is helpful. the interface is user-friendly and intuitive, making it easy to navigate and find the questions.
UNITED STATES


Zaynik 9/17/2023 5:36:00 AM

questions and options are correct, but the answers are wrong sometimes. so please check twice or refer some other platform for the right answer
Anonymous


Massam 6/11/2022 5:55:00 PM

90% of questions was there but i failed the exam, i marked the answers as per the guide but looks like they are not accurate , if not i would have passed the exam given that i saw about 45 of 50 questions from dump
Anonymous


Anonymous 12/27/2023 12:47:00 AM

answer to this question "what administrative safeguards should be implemented to protect the collected data while in use by manasa and her product management team? " it should be (c) for the following reasons: this administrative safeguard involves controlling access to collected data by ensuring that only individuals who need the data for their job responsibilities have access to it. this helps minimize the risk of unauthorized access and potential misuse of sensitive information. while other options such as (a) documenting data flows and (b) conducting a privacy impact assessment (pia) are important steps in data protection, implementing a "need to know" access policy directly addresses the issue of protecting data while in use by limiting access to those who require it for legitimate purposes. (d) is not directly related to safeguarding data during use; it focuses on data transfers and location.
INDIA


Japles 5/23/2023 9:46:00 PM

password lockout being the correct answer for question 37 does not make sense. it should be geofencing.
Anonymous


Faritha 8/10/2023 6:00:00 PM

for question 4, the righr answer is :recover automatically from failures
UNITED STATES


Anonymous 9/14/2023 4:27:00 AM

question number 4s answer is 3, option c. i
UNITED STATES


p das 12/7/2023 11:41:00 PM

very good questions
UNITED STATES


Anna 1/5/2024 1:12:00 AM

i am confused about the answers to the questions. are the answers correct?
KOREA REPUBLIC OF


Bhavya 9/13/2023 10:15:00 AM

very usefull
Anonymous


Rahul Kumar 8/31/2023 12:30:00 PM

need certification.
CANADA


Diran Ole 9/17/2023 5:15:00 PM

great exam prep
CANADA


Venkata Subbarao Bandaru 6/24/2023 8:45:00 AM

i require dump
Anonymous


D 7/15/2023 1:38:00 AM

good morning, could you please upload this exam again,
Anonymous


Ann 9/15/2023 5:39:00 PM

hi can you please upload the dumps for sap contingent module. thanks
AUSTRALIA


Sridhar 1/16/2024 9:19:00 PM

good questions
Anonymous


Summer 10/4/2023 9:57:00 PM

looking forward to the real exam
Anonymous


vv 12/2/2023 2:45:00 PM

good ones for exam preparation
UNITED STATES


Danny Zas 9/15/2023 4:45:00 AM

this is a good experience
UNITED STATES


SM 1211 10/12/2023 10:06:00 PM

hi everyone
UNITED STATES


A 10/2/2023 6:08:00 PM

waiting for the dump. please upload.
UNITED STATES