To keep costs at a minimum and decrease the completion time by 1-1/2 days, Networks, Inc.
should crash activity(ies):

  1. AD and AB
  2. DE
  3. AD
  4. AB and CE

Answer(s): A

Explanation:

The critical (longest) path is A-D-E, which has an expected time of 13 days (5.5 + 7.5). However, to decrease the project's completion time by 1.5 days, paths A-B-C-E (4.5 + 1.0 + 6.5 = 12 days) and A-B-D-E (4.5 + .5 + 7.5= 12.5 days) as well as A-D-E must also be shortened. Hence, A-D-E must be reduced by 1.5 days. A-B-C-E by .5 day, and A-B-D-E by 1.0 day. The only way to decrease A-D-E by 1.5 days is to crash activity AD (5.5 expected time - 4.0 crash time = 1.5 days). Crashing DE results in a 1.0-day saving (7.5-6.5) only. Crashing AB is the efficient way to reduce both A-B-C-E and A-B-D-E by the desired amount of time because it is part of both paths. The incremental cost of crashing AB is US $1,000 (US $4,000 crash cost - US $3,000 normal cost) to shorten the completion time by 1.0 day (4.5 - 3.5). The alternatives for decreasing both A-B-C-E and A-B-D-E are more costly.



When making a cost-time trade-off in CPM analysis, the first activity that should be crashed is the activity:

  1. With the largest amount of slack.
  2. With the lowest unit crash cost.
  3. On the critical path with the maximum possible time reduction.
  4. On the critical path with the lowest unit crash cost.

Answer(s): D

Explanation:

When making a cost-time trade-off, the first activity to be crashed (have its completion time accelerated) is one on the critical path. To select an activity on another path would not reduce the total time of completion. The initial activity chosen should be the one with the completion time that can be accelerated at the lowest possible cost per unit of time saved.



In PERT, slack is the:

  1. Uncertainty associated with time estimates.
  2. Difference between the latest starting time and earliest finishing time.
  3. Path that has the largest amount of time associated with it.
  4. Number of days an activity can be delayed without forcing a delay for the entire project.

Answer(s): D

Explanation:

Slack is the amount of time that commencement of an activity can be delayed without forcing a delay of the entire project.



The network below describes the interrelationships of several activities necessary to complete a project. The arrows represent the activities. The numbers between the arrows indicate the number of months to complete each activity.


The shortest time to complete the project is:

  1. 5 months.
  2. 6 months.
  3. 8 months.
  4. 14 months.

Answer(s): C

Explanation:

The critical (longest) path through the network from node (A) to node (F) is path A-C-D-F. All other paths are shorter than path A-C-D-F, so the activities along those paths can be completed before the activities along path A-C-D-F. Thus, the shortest time to complete the project is 8 months (3 + 3 + 2).



A shortest-route algorithm is used in network models to:

  1. Identify bottlenecks in a network and hence identify the longest path.
  2. Minimize total travel time from one site to each of the other sites in a transportation system.
  3. Maximize throughput in networks with distinct entry (source node) and exit (sink node) points.
  4. Identify the set of connecting branches having the shortest combined length.

Answer(s): B

Explanation:

Network models are used to solve managerial problems pertaining to project scheduling, information systems design, and transportation systems design. Networks consisting of nodes and arcs may be created to represent in graphic form problems related to transportation, assignment, and transshipment. The shortest-route, minimal spanning tree, and maximal flow problems are other applications of network models. A shortest-route algorithm minimizes total travel time from one site to each of the other sites in a transportation system.



Share your comments for Financial CIA-III exam with other users:

C
CW
7/10/2023 6:46:00 PM

these are the type of questions i need.

N
Nobody
8/30/2023 9:54:00 PM

does this actually work? are they the exam questions and answers word for word?

S
Salah
7/23/2023 9:46:00 AM

thanks for providing these questions

R
Ritu
9/15/2023 5:55:00 AM

interesting

R
Ron
5/30/2023 8:33:00 AM

these dumps are pretty good.

S
Sowl
8/10/2023 6:22:00 PM

good questions

B
Blessious Phiri
8/15/2023 2:02:00 PM

dbua is used for upgrading oracle database

R
Richard
10/24/2023 6:12:00 AM

i am thrilled to say that i passed my amazon web services mls-c01 exam, thanks to study materials. they were comprehensive and well-structured, making my preparation efficient.

J
Janjua
5/22/2023 3:31:00 PM

please upload latest ibm ace c1000-056 dumps

M
Matt
12/30/2023 11:18:00 AM

if only explanations were provided...

R
Rasha
6/29/2023 8:23:00 PM

yes .. i need the dump if you can help me

A
Anonymous
7/25/2023 8:05:00 AM

good morning, could you please upload this exam again?

A
AJ
9/24/2023 9:32:00 AM

hi please upload sre foundation and practitioner exam questions

P
peter parker
8/10/2023 10:59:00 AM

the exam is listed as 80 questions with a pass mark of 70%, how is your 50 questions related?

B
Berihun
7/13/2023 7:29:00 AM

all questions are so important and covers all ccna modules

N
nspk
1/19/2024 12:53:00 AM

q 44. ans:- b (goto setup > order settings > select enable optional price books for orders) reference link --> https://resources.docs.salesforce.com/latest/latest/en-us/sfdc/pdf/sfom_impl_b2b_b2b2c.pdf(decide whether you want to enable the optional price books feature. if so, select enable optional price books for orders. you can use orders in salesforce while managing price books in an external platform. if you’re using d2c commerce, you must select enable optional price books for orders.)

M
Muhammad Rawish Siddiqui
12/2/2023 5:28:00 AM

"cost of replacing data if it were lost" is also correct.

A
Anonymous
7/14/2023 3:17:00 AM

pls upload the questions

M
Mukesh
7/10/2023 4:14:00 PM

good questions

E
Elie Abou Chrouch
12/11/2023 3:38:00 AM

question 182 - correct answer is d. ethernet frame length is 64 - 1518b. length of user data containing is that frame: 46 - 1500b.

D
Damien
9/23/2023 8:37:00 AM

i need this exam pls

N
Nani
9/10/2023 12:02:00 PM

its required for me, please make it enable to access. thanks

E
ethiopia
8/2/2023 2:18:00 AM

seems good..

W
whoAreWeReally
12/19/2023 8:29:00 PM

took the test last week, i did have about 15 - 20 word for word from this site on the test. (only was able to cram 600 of the questions from this site so maybe more were there i didnt review) had 4 labs, bgp, lacp, vrf with tunnels and actually had to skip a lab due to time. lots of automation syntax questions.

V
vs
9/2/2023 12:19:00 PM

no comments

J
john adenu
11/14/2023 11:02:00 AM

nice questions bring out the best in you.

O
Osman
11/21/2023 2:27:00 PM

really helpful

E
Edward
9/13/2023 5:27:00 PM

question #50 and question #81 are exactly the same questions, azure site recovery provides________for virtual machines. the first says that it is fault tolerance is the answer and second says disater recovery. from my research, it says it should be disaster recovery. can anybody explain to me why? thank you

M
Monti
5/24/2023 11:14:00 PM

iam thankful for these exam dumps questions, i would not have passed without this exam dumps.

A
Anon
10/25/2023 10:48:00 PM

some of the answers seem to be inaccurate. q10 for example shouldnt it be an m custom column?

P
PeterPan
10/18/2023 10:22:00 AM

are the question real or fake?

C
CW
7/11/2023 3:19:00 PM

thank you for providing such assistance.

M
Mn8300
11/9/2023 8:53:00 AM

nice questions

N
Nico
4/23/2023 11:41:00 PM

my 3rd purcahse from this site. these exam dumps are helpful. very helpful.

AI Tutor 👋 I’m here to help!