Financial The Certified Internal Auditor Part 3 CIA-III Dumps in PDF

Free Financial CIA-III Real Questions (page: 21)

A Gantt chart:

  1. Shows the critical path for a project.
  2. Is used for determining an optimal product mix.
  3. Shows only the activities along the critical path of a network.
  4. Does not necessarily show the critical path through a network.

Answer(s): D

Explanation:

The major advantage of a Gantt chart is its simplicity: It requires no special tools or mathematics. However, it depicts only the interrelationships between tasks in a limited way. Thus, trying to identify a project's critical path from a Gantt chart may not be feasible.



In the Gantt chart below, shaded bars represent completed portions of activities, bars depicted with broken lines represent uncompleted portions, and blank bars represent activities notyet begun.



As of week 8, the Gantt chart shows that the project is:

  1. Complete.
  2. Ahead of schedule.
  3. On schedule.
  4. Behind schedule.

Answer(s): C

Explanation:

Activities B and C are the only activities that should be underway during week 8. Since both are underway and on schedule, the project is on schedule.



When using PERT (Program Evaluation Review Technique), the expected time for an activity when given an optimistic time (a), a pessimistic time (b),andamostlikelytime(m) is calculated by which one of the following formulas?

  1. (b - a) + 2
  2. (a + b) + 2
  3. (a + 4m+b) + 6
  4. (4abm) + 6

Answer(s): C

Explanation:

PERT was developed to aid managers in controlling large, complex projects. PERT analysis includes probabilistic estimates of activity completion times. Three time estimates are made:
optimistic, most likely, and pessimistic. The time estimates for an activity are assumed to approximate a beta probability distribution. PERT approximates the mean of the beta distribution by dividing the sum of the optimistic time, the pessimistic time, and four times the most likely time by six.



The process of adding resources to shorten selected activity times on the critical path in project scheduling is called:

  1. Crashing.
  2. The Delphi technique.
  3. ABC analysis.
  4. A branch-and-bound solution.

Answer(s): A

Explanation:

Crashing is the process of adding resources to shorten activity times on the critical path in project scheduling.



The network diagram and the corresponding activity cost chart for a manufacturing project at Networks, Inc., are presented below. The numbers in the diagram are the expected times (in days) to perform each activity in the project.


The expected time of the critical path is:

  1. 12.0 days
  2. 13.0 days
  3. 11.5 days
  4. 11.0 days

Answer(s): B

Explanation:

The critical path is the longest path. The longest path in the diagram is A-D-E, which requires 13 days (5.5 + 7.5) based on expected times.



Share your comments for Financial CIA-III exam with other users:

E
Emmah
7/29/2023 9:59:00 AM

are these valid chfi questions

M
Mort
10/19/2023 7:09:00 PM

question: 162 should be dlp (b)

E
Eknath
10/4/2023 1:21:00 AM

good exam questions

N
Nizam
6/16/2023 7:29:00 AM

I have to say this is really close to real exam. Passed my exam with this.

P
poran
11/20/2023 4:43:00 AM

good analytics question

A
Antony
11/23/2023 11:36:00 AM

this looks accurate

E
Ethan
8/23/2023 12:52:00 AM

question 46, the answer should be data "virtualization" (not visualization).

N
nSiva
9/22/2023 5:58:00 AM

its useful.

R
Ranveer
7/26/2023 7:26:00 PM

Pass this exam 3 days ago. The PDF version and the Xengine App is quite useful.

S
Sanjay
8/15/2023 10:22:00 AM

informative for me.

T
Tom
12/12/2023 8:53:00 PM

question 134s answer shoule be "dlp"

A
Alex
11/7/2023 11:02:00 AM

in 72 the answer must be [sys_user_has_role] table.

F
Finn
5/4/2023 10:21:00 PM

i appreciated the mix of multiple-choice and short answer questions. i passed my exam this morning.

A
AJ
7/13/2023 8:33:00 AM

great to find this website, thanks

C
Curtis Nakawaki
6/29/2023 9:11:00 PM

examination questions seem to be relevant.

U
Umashankar Sharma
10/22/2023 9:39:00 AM

planning to take psm test

E
ED SHAW
7/31/2023 10:34:00 AM

please allow to download

A
AD
7/22/2023 11:29:00 AM

please provide dumps

A
Ayyjayy
11/6/2023 7:29:00 AM

is the answer to question 15 correct ? i feel like the answer should be b

B
Blessious Phiri
8/12/2023 11:56:00 AM

its getting more technical

J
Jeanine J
7/11/2023 3:04:00 PM

i think these questions are what i need.

A
Aderonke
10/23/2023 2:13:00 PM

helpful assessment

T
Tom
1/5/2024 2:32:00 AM

i am confused about the answers to the questions. do you know if the answers are correct?

V
Vinit N.
8/28/2023 2:33:00 AM

hi, please make the dumps available for my upcoming examination.

S
Sanyog Deshpande
9/14/2023 7:05:00 AM

good practice

T
Tyron
9/8/2023 12:12:00 AM

so far it is really informative

B
beast
7/30/2023 2:22:00 PM

hi i want it please please upload it

M
Mirex
5/26/2023 3:45:00 AM

am preparing for exam ,just nice questions

E
exampei
8/7/2023 8:05:00 AM

please upload c_tadm_23 exam

A
Anonymous
9/12/2023 12:50:00 PM

can we get tdvan4 vantage data engineering pdf?

A
Aish
10/11/2023 5:51:00 AM

want to clear the exam.

S
Smaranika
6/22/2023 8:42:00 AM

could you please upload the dumps of sap c_sac_2302

B
Blessious Phiri
8/15/2023 1:56:00 PM

asm management configuration is about storage

L
Lewis
7/6/2023 8:49:00 PM

kool thumb up

AI Tutor 👋 I’m here to help!