A Gantt chart:
Answer(s): D
The major advantage of a Gantt chart is its simplicity: It requires no special tools or mathematics. However, it depicts only the interrelationships between tasks in a limited way. Thus, trying to identify a project's critical path from a Gantt chart may not be feasible.
In the Gantt chart below, shaded bars represent completed portions of activities, bars depicted with broken lines represent uncompleted portions, and blank bars represent activities notyet begun.As of week 8, the Gantt chart shows that the project is:
Answer(s): C
Activities B and C are the only activities that should be underway during week 8. Since both are underway and on schedule, the project is on schedule.
When using PERT (Program Evaluation Review Technique), the expected time for an activity when given an optimistic time (a), a pessimistic time (b),andamostlikelytime(m) is calculated by which one of the following formulas?
PERT was developed to aid managers in controlling large, complex projects. PERT analysis includes probabilistic estimates of activity completion times. Three time estimates are made:optimistic, most likely, and pessimistic. The time estimates for an activity are assumed to approximate a beta probability distribution. PERT approximates the mean of the beta distribution by dividing the sum of the optimistic time, the pessimistic time, and four times the most likely time by six.
The process of adding resources to shorten selected activity times on the critical path in project scheduling is called:
Answer(s): A
Crashing is the process of adding resources to shorten activity times on the critical path in project scheduling.
The network diagram and the corresponding activity cost chart for a manufacturing project at Networks, Inc., are presented below. The numbers in the diagram are the expected times (in days) to perform each activity in the project.The expected time of the critical path is:
Answer(s): B
The critical path is the longest path. The longest path in the diagram is A-D-E, which requires 13 days (5.5 + 7.5) based on expected times.
Share your comments for Financial CIA-III exam with other users:
are these valid chfi questions
question: 162 should be dlp (b)
good exam questions
I have to say this is really close to real exam. Passed my exam with this.
good analytics question
this looks accurate
question 46, the answer should be data "virtualization" (not visualization).
its useful.
Pass this exam 3 days ago. The PDF version and the Xengine App is quite useful.
informative for me.
question 134s answer shoule be "dlp"
in 72 the answer must be [sys_user_has_role] table.
i appreciated the mix of multiple-choice and short answer questions. i passed my exam this morning.
great to find this website, thanks
examination questions seem to be relevant.
planning to take psm test
please allow to download
please provide dumps
is the answer to question 15 correct ? i feel like the answer should be b
its getting more technical
i think these questions are what i need.
helpful assessment
i am confused about the answers to the questions. do you know if the answers are correct?
hi, please make the dumps available for my upcoming examination.
good practice
so far it is really informative
hi i want it please please upload it
am preparing for exam ,just nice questions
please upload c_tadm_23 exam
can we get tdvan4 vantage data engineering pdf?
want to clear the exam.
could you please upload the dumps of sap c_sac_2302
asm management configuration is about storage
kool thumb up