A Gantt chart:
Answer(s): D
The major advantage of a Gantt chart is its simplicity: It requires no special tools or mathematics. However, it depicts only the interrelationships between tasks in a limited way. Thus, trying to identify a project's critical path from a Gantt chart may not be feasible.
In the Gantt chart below, shaded bars represent completed portions of activities, bars depicted with broken lines represent uncompleted portions, and blank bars represent activities notyet begun.As of week 8, the Gantt chart shows that the project is:
Answer(s): C
Activities B and C are the only activities that should be underway during week 8. Since both are underway and on schedule, the project is on schedule.
When using PERT (Program Evaluation Review Technique), the expected time for an activity when given an optimistic time (a), a pessimistic time (b),andamostlikelytime(m) is calculated by which one of the following formulas?
PERT was developed to aid managers in controlling large, complex projects. PERT analysis includes probabilistic estimates of activity completion times. Three time estimates are made:optimistic, most likely, and pessimistic. The time estimates for an activity are assumed to approximate a beta probability distribution. PERT approximates the mean of the beta distribution by dividing the sum of the optimistic time, the pessimistic time, and four times the most likely time by six.
The process of adding resources to shorten selected activity times on the critical path in project scheduling is called:
Answer(s): A
Crashing is the process of adding resources to shorten activity times on the critical path in project scheduling.
The network diagram and the corresponding activity cost chart for a manufacturing project at Networks, Inc., are presented below. The numbers in the diagram are the expected times (in days) to perform each activity in the project.The expected time of the critical path is:
Answer(s): B
The critical path is the longest path. The longest path in the diagram is A-D-E, which requires 13 days (5.5 + 7.5) based on expected times.
Share your comments for Financial CIA-III-2012 exam with other users:
wish you would allow more free questions
great simulation
very g inood
q35 should be a
sap c_ts450_2021
nice questions
ecellent materil for unserstanding
good so far
this is way too informative
very helpfull
q.189 - answers are incorrect.
awesome job in getting these questions
i cant find aws certified practitioner clf-c01 exam in aws website but i found aws certified practitioner clf-c02 exam. can everyone please verify the difference between the two clf-c01 and clf-c02? thank you
grazie mille. i got a satisfactory mark in my exam test today because of this exam dumps. sorry for my english.
some of the answers are incorrect. need to be reviewed.
so far so good
i am really liking it
thanks good stuff
need dump c_tadm_23
next time i will write a full review
first time using this site
please sent me oracle 1z0-1105-22 pdf
very helpful
good info about oml
very useful to practice
this website is very helpful.
good content
so challenging
17 should be d ,for morequery its scale out
nice question
yes.
good mateial
good practice exam
impressivre qustion