Using IP Geolocation, an organization can always direct a client request from France to a datacenter in Dublin.

  1. True
  2. False

Answer(s): A



Which three of these software modules can you layer on top of LTM on a BIG-IP device? (Choose three.)

  1. Web Accelerator
  2. APM
  3. ARX
  4. GTM
  5. Firepass
  6. Enterprise Manager

Answer(s): A,B,D

Explanation:

These software modules can you layer on top of LTM on a BIG-IP device are AAM, APM and GTM.



Customers can purchase LTM as a stand-alone product, or layer it with additional software modules to increase the functionality of the BIG-IP device.

  1. True
  2. False

Answer(s): A



Which two of the following options can LTM use when all of the pool members are not available or if the pool is overloaded?

  1. Floating IPs
  2. Fallback host
  3. Auto last hop
  4. SNAT automap
  5. Pool offload
  6. Priority group activation

Answer(s): D

Explanation:

http://support.f5.com/kb/enus/
products/bigip_ltm/manuals/product/ltm_configuration_guide_10_0_0/ltm_pools.html



The least connections load balancing method functions best when all pool members share similar characteristics.

  1. True
  2. False

Answer(s): A



Viewing Page 5 of 93



Share your comments for F5 101 exam with other users:

nITA KALE 8/22/2023 1:57:00 AM

i need dumps
Anonymous


Karan 5/17/2023 4:26:00 AM

need this dump
Anonymous