A project manager has been very diligent in maintaining the version control for the documentation of requirements. Which of the following tools is the project manager using?

  1. Multiauthoring software
  2. Word processor
  3. Real-time polling
  4. Conferencing platforms

Answer(s): A



The project team determines that software installation can only begin after the desktops have been installed and can be powered on. Which of the following dependencies does this represent?

  1. External
  2. Internal
  3. Mandatory
  4. Discretionary

Answer(s): C



A hurricane delays the shipment of critical equipment for a project. Which of the following is BEST to use to document the effects of this delay?

  1. Issue log
  2. Gantt chart
  3. Milestone chart
  4. Change control log

Answer(s): A



Due to budgetary and time constraints, a PM scheduled a meeting with all stakeholders during the planning phase to review the requirements and come to an agreement on the minimum viable product that would be acceptable. Which of the following would be used to document this input?

  1. Project change management plan
  2. Project management plan
  3. Project transition plan
  4. Project communication plan

Answer(s): B



A project team was instructed to refurbish old desktops. The following provides the details of the issues observed:



Which of the following issues should be addressed FIRST?

  1. Replace missing peripherals because this process can be easy and less costly.
  2. An old operating system issue has the most amount of occurrences.
  3. Damage to the monitor has the highest percentage.
  4. Address each issue as discovered to avoid rework.

Answer(s): B



A project manager was not part of a contract negotiation. The project manager is concerned that stakeholders will expect the project to achieve deliverables requested in the RFP. Which of the following documents should the project manager produce FIRST to start communication about the boundaries of the project?

  1. Milestone chart
  2. Work breakdown structure
  3. Project charter
  4. Detailed scope statement

Answer(s): C



In a functional organization, a project has been completed successfully. Which of the following actions would the project manager MOST likely perform?

  1. Assemble a new project with existing resources.
  2. Obtain the final report from release management.
  3. Notify the functional manager that resources are released.
  4. Allocate resources in a different project.

Answer(s): C



A third party needs to perform a short-term task for which the duration cannot be accurately estimated and the cost cannot be calculated in advance. Which of the following should the project manager put in place before work begins?

  1. Time and materials contract
  2. Master service agreement
  3. Fixed-price contract
  4. Statement of work
  5. Cost-plus agreement

Answer(s): A



Share your comments for CompTIA PK0-005 exam with other users:

P
praveenkumar
11/20/2023 11:57:00 AM

very helpful to crack first attempt

A
asad Raza
5/15/2023 5:38:00 AM

please upload this exam

R
Reeta
7/17/2023 5:22:00 PM

please upload the c_activate22 dump questions with answer

W
Wong
12/20/2023 11:34:00 AM

q10 - the answer should be a. if its c, the criteria will meet if either the prospect is not part of the suppression lists or if the job title contains vice president

D
david
12/12/2023 12:38:00 PM

this was on the exam as of 1211/2023

T
Tink
7/24/2023 9:23:00 AM

great for prep

J
Jaro
12/18/2023 3:12:00 PM

i think in question 7 the first answer should be power bi portal (not power bi)

9
9eagles
4/7/2023 10:04:00 AM

on question 10 and so far 2 wrong answers as evident in the included reference link.

T
Tai
8/28/2023 5:28:00 AM

wonderful material

V
VoiceofMidnight
12/29/2023 4:48:00 PM

i passed!! ...but barely! got 728, but needed 720 to pass. the exam hit me with labs right out of the gate! then it went to multiple choice. protip: study the labs!

A
A K
8/3/2023 11:56:00 AM

correct answer for question 92 is c -aws shield

N
Nitin Mindhe
11/27/2023 6:12:00 AM

great !! it is really good

B
BailleyOne
11/22/2023 1:45:00 AM

explanations for the answers are to the point.

P
patel
10/25/2023 8:17:00 AM

how can rea next

M
MortonG
10/19/2023 6:32:00 PM

question: 128 d is the wrong answer...should be c

J
Jayant
11/2/2023 3:15:00 AM

thanks for az 700 dumps

B
Bipul Mishra
12/14/2023 7:12:00 AM

thank you for this tableau dumps . it will helpfull for tableau certification

H
hello
10/31/2023 12:07:00 PM

good content

M
Matheus
9/3/2023 2:14:00 PM

just testing if the comments are real

Y
yenvti2@gmail.com
8/12/2023 7:56:00 PM

very helpful for exam preparation

M
Miguel
10/5/2023 12:16:00 PM

question 11: https://help.salesforce.com/s/articleview?id=sf.admin_lead_to_patient_setup_overview.htm&type=5

N
Noushin
11/28/2023 4:52:00 PM

i think the answer to question 42 is b not c

S
susan sandivore
8/28/2023 1:00:00 AM

thanks for the dump

A
Aderonke
10/31/2023 12:51:00 AM

fantastic assessments

P
Priscila
7/22/2022 9:59:00 AM

i find the xengine test engine simulator to be more fun than reading from pdf.

S
suresh
12/16/2023 10:54:00 PM

nice document

W
Wali
6/4/2023 10:07:00 PM

thank you for making the questions and answers intractive and selectable.

N
Nawaz
7/18/2023 1:10:00 AM

answers are correct?

D
das
6/23/2023 7:57:00 AM

can i belive this dump

S
Sanjay
10/15/2023 1:34:00 PM

great site to practice for sitecore exam

J
jaya
12/17/2023 8:36:00 AM

good for students

B
Bsmaind
8/20/2023 9:23:00 AM

nice practice dumps

K
kumar
11/15/2023 11:24:00 AM

nokia 4a0-114 dumps

V
Vetri
10/3/2023 12:59:00 AM

great content and wonderful to have the answers with explanation

AI Tutor 👋 I’m here to help!