Which of the following BEST describes how an organization should coordinate management of multiple related projects?

  1. Apply the SDLC process.
  2. Establish a program.
  3. Consult the CCB.
  4. Use different frameworks

Answer(s): B



A project team gathers weekly to review its progress.
Which of the following is the project manager MOST likely to have prepared to ensure team members who are absent remain informed about assignments?

  1. Status report
  2. Project plan
  3. Change log
  4. Meeting minutes

Answer(s): D



A project manager prefers to have immediate contact with team members because it allows for faster response times and more interactive discussions.
Which of the following communication methods should the project manager use?

  1. Synchronous
  2. Informal
  3. Asynchronous
  4. Formal

Answer(s): A



As part of the planning phase, a PM has defined tasks, durations, resources, and costs.
Which of the following is the NEXT step in the process?

  1. Update the work breakdown structure.
  2. Review the backlog.
  3. Seek baseline approval.
  4. Establish the resource pool.

Answer(s): C



A project manager realizes that a project will not be completed on time due to resource constraints.
Which of the following actions should the project manager take NEXT?

  1. Trigger the contingency plan and communicate with the stakeholders.
  2. Work with the functional managers to create a work-around.
  3. Submit a change request to the change control board.
  4. Transfer the risk by hiring a new vendor who was successful on a previous project.
  5. Set up an escalation meeting with the sponsor.

Answer(s): C



Viewing Page 2 of 74



Share your comments for CompTIA PK0-005 exam with other users:

Amitabha Roy 10/5/2023 3:16:00 AM

planning to attempt for the exam.
Anonymous


Prem Yadav 7/29/2023 6:20:00 AM

pleaseee upload
INDIA


Ahmed Hashi 7/6/2023 5:40:00 PM

thanks ly so i have information cia
EUROPEAN UNION


mansi 5/31/2023 7:58:00 AM

hello team, i need sap qm dumps for practice
INDIA


Jamil aljamil 12/4/2023 4:47:00 AM

it’s good but not senatios based
UNITED KINGDOM


Cath 10/10/2023 10:19:00 AM

q.119 - the correct answer is b - they are not captured in an update set as theyre data.
VIET NAM


P 1/6/2024 11:22:00 AM

good matter
Anonymous


surya 7/30/2023 2:02:00 PM

please upload c_sacp_2308
CANADA


Sasuke 7/11/2023 10:30:00 PM

please upload the dump. thanks very much !!
Anonymous


V 7/4/2023 8:57:00 AM

good questions
UNITED STATES


TTB 8/22/2023 5:30:00 AM

hi, could you please update the latest dump version
Anonymous


T 7/28/2023 9:06:00 PM

this question is keep repeat : you are developing a sales application that will contain several azure cloud services and handle different components of a transaction. different cloud services will process customer orders, billing, payment, inventory, and shipping. you need to recommend a solution to enable the cloud services to asynchronously communicate transaction information by using xml messages. what should you include in the recommendation?
NEW ZEALAND


Gurgaon 9/28/2023 4:35:00 AM

great questions
UNITED STATES


wasif 10/11/2023 2:22:00 AM

its realy good
UNITED ARAB EMIRATES


Shubhra Rathi 8/26/2023 1:12:00 PM

oracle 1z0-1059-22 dumps
Anonymous


Leo 7/29/2023 8:48:00 AM

please share me the pdf..
INDIA


AbedRabbou Alaqabna 12/18/2023 3:10:00 AM

q50: which two functions can be used by an end user when pivoting an interactive report? the correct answer is a, c because we do not have rank in the function pivoting you can check in the apex app
GREECE


Rohan Limaye 12/30/2023 8:52:00 AM

best to practice
Anonymous


Aparajeeta 10/13/2023 2:42:00 PM

so far it is good
Anonymous


Vgf 7/20/2023 3:59:00 PM

please provide me the dump
Anonymous


Deno 10/25/2023 1:14:00 AM

i failed the cisa exam today. but i have found all the questions that were on the exam to be on this site.
Anonymous


CiscoStudent 11/15/2023 5:29:00 AM

in question 272 the right answer states that an autonomous acces point is "configured and managed by the wlc" but this is not what i have learned in my ccna course. is this a mistake? i understand that lightweight aps are managed by wlc while autonomous work as standalones on the wlan.
Anonymous


pankaj 9/28/2023 4:36:00 AM

it was helpful
Anonymous


User123 10/8/2023 9:59:00 AM

good question
UNITED STATES


vinay 9/4/2023 10:23:00 AM

really nice
Anonymous


Usman 8/28/2023 10:07:00 AM

please i need dumps for isc2 cybersecuity
Anonymous


Q44 7/30/2023 11:50:00 AM

ans is coldline i think
UNITED STATES


Anuj 12/21/2023 1:30:00 PM

very helpful
Anonymous


Giri 9/13/2023 10:31:00 PM

can you please provide dumps so that it helps me more
UNITED STATES


Aaron 2/8/2023 12:10:00 AM

thank you for providing me with the updated question and answers. this version has all the questions from the exam. i just saw them in my exam this morning. i passed my exam today.
SOUTH AFRICA


Sarwar 12/21/2023 4:54:00 PM

how i can see exam questions?
CANADA


Chengchaone 9/11/2023 10:22:00 AM

can you please upload please?
Anonymous


Mouli 9/2/2023 7:02:00 AM

question 75: option c is correct answer
Anonymous


JugHead 9/27/2023 2:40:00 PM

please add this exam
Anonymous