A team member finds a malfunctioning procedure in the system that will take a considerable amount of time to fix. Which of the following should be done FIRST?

  1. Update the risk register
  2. Document the finding in the change log.
  3. Create a record in the issue log
  4. Detail a proposed solution.

Answer(s): C



A project team has identified a bug during user acceptance testing. Which of the following is the BEST method for communicating that bug to the development team?

  1. Call the development lead to discuss the fixes for the bug.
  2. Include the bug issue as part of the status update for stakeholders.
  3. Issue a change request.
  4. Add the bug issue to the project's risk register.

Answer(s): C



Internal project team members and a subject matter expert had a heated discussion about the client's needs. The deliverable is now at risk of being delayed. Which of the following should be notified LAST?

  1. Program manager
  2. End user
  3. Steering committee
  4. Project sponsor

Answer(s): B



Which of the following methodologies/frameworks should be used when incremental value is expected in a timeboxed period?

  1. PRINCE2
  2. Waterfall
  3. Scrum
  4. SLDC

Answer(s): C



A project manager has just finished overseeing the implementation of a new, self-service benefits enrollment system. Many employees, however, are calling the human resources team for assistance instead of using the self-service system. Which of the following should the project manager have done as part of the execution plan?

  1. Establish a minimally viable product.
  2. Prepare new knowledge base documentation.
  3. Update the project baseline and schedule.
  4. Periodically review vendor performance.

Answer(s): B



Which of the following methods frequently delivers new code in an automatic way for development projects?

  1. Automated testing
  2. CI/CD process
  3. Validation checks
  4. Deploy sprint

Answer(s): B



When trying to calculate the expected monetary value for using a particular vendor, which of the following charts would be BEST to use?

  1. Decision tree
  2. Fishbone
  3. Histogram
  4. Pareto

Answer(s): A



Two projects share resources. The mobile application project cannot start if the database renewal project has not started. Which of the following relationships describes this situation?

  1. Start-to-finish
  2. Start-to-start
  3. Finish-to-start
  4. Finish-to-finish

Answer(s): B



Share your comments for CompTIA PK0-005 exam with other users:

J
Jay
9/26/2023 8:00:00 AM

link plz for download

L
Leo
10/30/2023 1:11:00 PM

data quality oecd

B
Blessious Phiri
8/13/2023 9:35:00 AM

rman is one good recovery technology

D
DiligentSam
9/30/2023 10:26:00 AM

need it thx

V
Vani
8/10/2023 8:11:00 PM

good questions

F
Fares
9/11/2023 5:00:00 AM

good one nice revision

L
Lingaraj
10/26/2023 1:27:00 AM

i love this thank you i need

M
Muhammad Rawish Siddiqui
12/5/2023 12:38:00 PM

question # 142: data governance is not one of the deliverables in the document and content management context diagram.

A
al
6/7/2023 10:25:00 AM

most answers not correct here

B
Bano
1/19/2024 2:29:00 AM

what % of questions do we get in the real exam?

O
Oliviajames
10/25/2023 5:31:00 AM

i just want to tell you. i took my microsoft az-104 exam and passed it. your program was awesome. i especially liked your detailed questions and answers and practice tests that made me well-prepared for the exam. thanks to this website!!!

D
Divya
8/27/2023 12:31:00 PM

all the best

K
KY
1/1/2024 11:01:00 PM

very usefull document

A
Arun
9/20/2023 4:52:00 PM

nice and helpful questions

J
Joseph J
7/11/2023 2:53:00 PM

i found the questions helpful

M
Meg
10/12/2023 8:02:00 AM

q 105 . ans is d

N
Navaneeth S
7/14/2023 7:57:00 AM

i have interest to get a sybase iq dba certification

A
Aish
10/11/2023 5:27:00 AM

want to pass exm.

A
Anonymous
6/12/2023 7:23:00 AM

are the answers correct?

K
Kris
7/7/2023 9:43:00 AM

good morning, could you please upload this exam again, i need it to test my knowledge in sd-wan with version 7.0.

M
Meghraj mali
10/7/2023 1:47:00 PM

very nice question

N
Noel
11/1/2022 9:14:00 PM

i have learning disability and this exam dumps allowed me to focus on the actual questions and not worry about notes and the those other study materials.

J
Jas
10/25/2023 6:01:00 PM

165 should be apt

N
Neetu
6/22/2023 8:41:00 AM

please upload the dumps, real need of them

M
Mark
10/24/2023 1:34:00 AM

any recent feeedback?

G
Gopinadh
8/9/2023 4:05:00 AM

question number 2 is indicating you are giving proper questions. observe and change properly.

S
Santhi
1/1/2024 8:23:00 AM

passed today.40% questions were new.litwere case study,lots of new questions on afd,ratelimit,tm,lb,app gatway.got 2 set series of questions which are not present here.questions on azure cyclecloud, no.of vnet/vms required for implimentation,blueprints assignment/management group etc

R
Raviraj Magadum
1/12/2024 11:39:00 AM

practice test

S
sivaramakrishnan
7/27/2023 8:12:00 AM

want the dumps for emc content management server programming(cmsp)

A
Aderonke
10/23/2023 1:52:00 PM

brilliant and helpful

A
Az
9/16/2023 2:43:00 PM

q75. azure files is pass

K
ketty
11/9/2023 8:10:00 AM

very helpful

S
Sonail
5/2/2022 1:36:00 PM

thank you for these questions. it helped a lot.

S
Shariq
7/28/2023 8:00:00 AM

how do i get the h12-724 dumps

AI Tutor 👋 I’m here to help!