A team member finds a malfunctioning procedure in the system that will take a considerable amount of time to fix. Which of the following should be done FIRST?

  1. Update the risk register
  2. Document the finding in the change log.
  3. Create a record in the issue log
  4. Detail a proposed solution.

Answer(s): C



A project team has identified a bug during user acceptance testing. Which of the following is the BEST method for communicating that bug to the development team?

  1. Call the development lead to discuss the fixes for the bug.
  2. Include the bug issue as part of the status update for stakeholders.
  3. Issue a change request.
  4. Add the bug issue to the project's risk register.

Answer(s): C



Internal project team members and a subject matter expert had a heated discussion about the client's needs. The deliverable is now at risk of being delayed. Which of the following should be notified LAST?

  1. Program manager
  2. End user
  3. Steering committee
  4. Project sponsor

Answer(s): B



Which of the following methodologies/frameworks should be used when incremental value is expected in a timeboxed period?

  1. PRINCE2
  2. Waterfall
  3. Scrum
  4. SLDC

Answer(s): C



A project manager has just finished overseeing the implementation of a new, self-service benefits enrollment system. Many employees, however, are calling the human resources team for assistance instead of using the self-service system. Which of the following should the project manager have done as part of the execution plan?

  1. Establish a minimally viable product.
  2. Prepare new knowledge base documentation.
  3. Update the project baseline and schedule.
  4. Periodically review vendor performance.

Answer(s): B



Which of the following methods frequently delivers new code in an automatic way for development projects?

  1. Automated testing
  2. CI/CD process
  3. Validation checks
  4. Deploy sprint

Answer(s): B



When trying to calculate the expected monetary value for using a particular vendor, which of the following charts would be BEST to use?

  1. Decision tree
  2. Fishbone
  3. Histogram
  4. Pareto

Answer(s): A



Two projects share resources. The mobile application project cannot start if the database renewal project has not started. Which of the following relationships describes this situation?

  1. Start-to-finish
  2. Start-to-start
  3. Finish-to-start
  4. Finish-to-finish

Answer(s): B



Share your comments for CompTIA PK0-005 exam with other users:

V
vel
8/28/2023 9:17:09 AM

good one with explanation

G
Gurdeep
1/18/2024 4:00:15 PM

This is one of the most useful study guides I have ever used.

AI Tutor 👋 I’m here to help!