Two team members are arguing over two different approaches to complete a task. The project manager listens to both sides, determines neither approach will work, and directs the team members to use a third option.

This type of conflict resolution is known as:

  1. forcing.
  2. avoiding.
  3. smoothing.
  4. compromising.

Answer(s): A


Reference:

Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 200



Which of the following metrics demonstrates to a project manager if a project is overspending or underspending?

  1. EAC
  2. BAC
  3. CPI
  4. ETC

Answer(s): C


Reference:

Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 231



The project sponsor has cut the resources required for project completion. The project manager cannot complete the project without additional resources.
Which of the following should the project manager do to obtain the resources?

  1. The project manager should identify and document the reasons for the additional resources in a change request.
  2. The project manager should hire additional resources temporarily to complete the project.
  3. The project manager should terminate the project until additional resources are added to the project.
  4. The project manager should ask the project team members to take on more tasks to complete the project on time.

Answer(s): A



An organization has multiple projects that are taking place simultaneously.
Which of the following should be tasked with ensuring resources are appropriately allocated to projects?

  1. PMO
  2. Project sponsor
  3. Project coordinator
  4. HR

Answer(s): B


Reference:

Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 82



When a risk event occurs, which of the following documents is BEST suited for recording and tracking new items corresponding to the risk?

  1. Issue log
  2. Risk management plan
  3. Communications plan
  4. Risk register
  5. Status report

Answer(s): D



Viewing Page 8 of 147



Share your comments for CompTIA PK0-004 exam with other users:

Thembelani 5/30/2023 2:22:00 AM

anyone who wrote this exam recently
Anonymous


P 9/16/2023 1:27:00 AM

ok they re good
Anonymous


Jorn 7/13/2023 5:05:00 AM

relevant questions
UNITED KINGDOM


AM 6/20/2023 7:54:00 PM

please post
UNITED STATES


Nagendra Pedipina 7/13/2023 2:22:00 AM

q:42 there has to be a image in the question to choose what does it mean from the options
INDIA


BrainDumpee 11/18/2023 1:36:00 PM

looking for cphq dumps, where can i find these for free? please and thank you.
UNITED STATES


sheik 10/14/2023 11:37:00 AM

@aarun , thanks for the information. it would be great help if you share your email
Anonymous


Random user 12/11/2023 1:34:00 AM

1z0-1078-23 need this dumps
Anonymous


labuschanka 11/16/2023 6:06:00 PM

i gave the microsoft azure az-500 tests and prepared from this site as it has latest mock tests available which helped me evaluate my performance and score 919/1000
Anonymous


Marianne 10/22/2023 11:57:00 PM

i cannot see the button to go to the questions
Anonymous


sushant 6/28/2023 4:52:00 AM

good questions
EUROPEAN UNION


A\MAM 6/27/2023 5:17:00 PM

q-6 ans-b correct. https://docs.paloaltonetworks.com/pan-os/9-1/pan-os-cli-quick-start/use-the-cli/commit-configuration-changes
UNITED STATES


unanimous 12/15/2023 6:38:00 AM

very nice very nice
Anonymous


akminocha 9/28/2023 10:36:00 AM

please help us with 1z0-1107-2 dumps
INDIA


Jefi 9/4/2023 8:15:00 AM

please upload the practice questions
Anonymous


Thembelani 5/30/2023 2:45:00 AM

need this dumps
Anonymous


Abduraimov 4/19/2023 12:43:00 AM

preparing for this exam is overwhelming. you cannot pass without the help of these exam dumps.
UNITED KINGDOM


Puneeth 10/5/2023 2:06:00 AM

new to this site but i feel it is good
EUROPEAN UNION


Ashok Kumar 1/2/2024 6:53:00 AM

the correct answer to q8 is b. explanation since the mule app has a dependency, it is necessary to include project modules and dependencies to make sure the app will run successfully on the runtime on any other machine. source code of the component that the mule app is dependent of does not need to be included in the exported jar file, because the source code is not being used while executing an app. compiled code is being used instead.
Anonymous


Merry 7/30/2023 6:57:00 AM

good questions
Anonymous


VoiceofMidnight 12/17/2023 4:07:00 PM

Delayed the exam until December 29th.
UNITED STATES


Umar Ali 8/29/2023 2:59:00 PM

A and D are True
Anonymous


vel 8/28/2023 9:17:09 AM

good one with explanation
Anonymous


Gurdeep 1/18/2024 4:00:15 PM

This is one of the most useful study guides I have ever used.
CANADA