After identifying all known tasks, the project manager has started to sequence and set durations.
Which of the following describes how the project manager should BEST determine the initial sequence and durations?

  1. Use milestones identified in the project charter.
  2. Use data based on past knowledge.
  3. Hold a full team workshop to review the complete WBS.
  4. Collaborate with other project managers.

Answer(s): A



A company has updated the method it uses to initiate projects. The company requires RFPs from three vendors, and low and high bids must be rejected to determine the selected vendor.
Which of the following terms describe this requirement?

  1. Outsourcing
  2. Business acquisition
  3. Business process change
  4. Internal reorganization

Answer(s): A


Reference:

Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 297



A project team is overseeing the installation of a new reptile habitat at the local zoo. During execution, zoo personnel decides to house a different type of reptile that will require a different temperature range than the capacity of the installed system. The modification has been approved.
Which of the following constraints are MOST likely to be affected? (Choose two.)

  1. Quality because the existing system is now outside the threshold.
  2. Requirements because this is a change to initial scope.
  3. Cost because replacing the system incurs additional expense.
  4. Schedule because this was an unscheduled task and will impact the timeline.
  5. Stakeholders because they will need to understand the modification and provide buy-in.

Answer(s): C,D


Reference:

Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 293



Assuming an iterative approach, which of the following will be conducted at the end of each iteration?

  1. SCRUM retrospective
  2. Kickoff meeting
  3. Budget baseline
  4. Risk review

Answer(s): A


Reference:

Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 306



The project manager has noticed a vendor is not performing in accordance with the SLA.
Which of the following items should the project manager use to highlight the vendor’s areas of poor performance?

  1. Balanced score card
  2. WBS
  3. Post-project evaluation
  4. PERT

Answer(s): A


Reference:

Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 332



Viewing Page 7 of 147



Share your comments for CompTIA PK0-004 exam with other users:

unanimous 12/15/2023 6:38:00 AM

very nice very nice
Anonymous


akminocha 9/28/2023 10:36:00 AM

please help us with 1z0-1107-2 dumps
INDIA


Jefi 9/4/2023 8:15:00 AM

please upload the practice questions
Anonymous


Thembelani 5/30/2023 2:45:00 AM

need this dumps
Anonymous


Abduraimov 4/19/2023 12:43:00 AM

preparing for this exam is overwhelming. you cannot pass without the help of these exam dumps.
UNITED KINGDOM


Puneeth 10/5/2023 2:06:00 AM

new to this site but i feel it is good
EUROPEAN UNION


Ashok Kumar 1/2/2024 6:53:00 AM

the correct answer to q8 is b. explanation since the mule app has a dependency, it is necessary to include project modules and dependencies to make sure the app will run successfully on the runtime on any other machine. source code of the component that the mule app is dependent of does not need to be included in the exported jar file, because the source code is not being used while executing an app. compiled code is being used instead.
Anonymous


Merry 7/30/2023 6:57:00 AM

good questions
Anonymous


VoiceofMidnight 12/17/2023 4:07:00 PM

Delayed the exam until December 29th.
UNITED STATES


Umar Ali 8/29/2023 2:59:00 PM

A and D are True
Anonymous


vel 8/28/2023 9:17:09 AM

good one with explanation
Anonymous


Gurdeep 1/18/2024 4:00:15 PM

This is one of the most useful study guides I have ever used.
CANADA