A milestone task on the critical path has been completed. Which of the following should the project manager notify?

  1. Owner of predecessor task
  2. Project team
  3. Project sponsor
  4. Project steering committee

Answer(s): C



During a project assessment, a project manager determines the initial project cost estimates were incorrect, and there is not enough budget left, including reserves, to complete the project.
Which of the following actions should the project manager take?

  1. Alert the project sponsor of the situation.
  2. Contact the customer and request more funding.
  3. Announce the project will end early due to lack of funds.
  4. Attempt to save money in downstream activities.

Answer(s): A


Reference:

Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 233



Which of the following is the primary purpose of an MOA or an MOU?

  1. State expectations of all signatory parties to reduce potential misunderstandings.
  2. Facilitate potential legal action and resulting remediation if one of the signatory parties violates any terms.
  3. Enumerate a detailed code of conduct for all employees, contractors, and subcontractors participating in the program.
  4. Provide transparency to competitors regarding all signatory parties.

Answer(s): A


Reference:

Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 303



Two team members have concluded that documentation is not required due to the size of the current project. The project manager has encouraged them to align strictly within the process.
Which of the following conflict resolution techniques has the project manager utilized?

  1. Smoothing
  2. Forcing
  3. Compromising
  4. Avoiding

Answer(s): B


Reference:

Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 200



The client accepts the critical design review.
Which of the following meetings should be held to move to the NEXT step in the project?

  1. Execution
  2. Kickoff
  3. Closure
  4. Planning

Answer(s): B


Reference:

Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 112



Viewing Page 9 of 147



Share your comments for CompTIA PK0-004 exam with other users:

Biswa 11/20/2023 8:50:00 AM

refresh db knowledge
Anonymous


Shalini Sharma 10/17/2023 8:29:00 AM

interested for sap certification
JAPAN


ethan 9/24/2023 12:38:00 PM

could you please upload practice questions for scr exam ?
HONG KONG


vijay joshi 8/19/2023 3:15:00 AM

please upload free oracle cloud infrastructure 2023 foundations associate exam braindumps
Anonymous


Ayodele Talabi 8/25/2023 9:25:00 PM

sweating! they are tricky
CANADA


Romero 3/23/2022 4:20:00 PM

i never use these dumps sites but i had to do it for this exam as it is impossible to pass without using these question dumps.
UNITED STATES


John Kennedy 9/20/2023 3:33:00 AM

good practice and well sites.
Anonymous


Nenad 7/12/2022 11:05:00 PM

passed my first exam last week and pass the second exam this morning. thank you sir for all the help and these brian dumps.
INDIA


Lucky 10/31/2023 2:01:00 PM

does anyone who attended exam csa 8.8, can confirm these questions are really coming ? or these are just for practicing?
HONG KONG


Prateek 9/18/2023 11:13:00 AM

kindly share the dumps
UNITED STATES


Irfan 11/25/2023 1:26:00 AM

very nice content
Anonymous


php 6/16/2023 12:49:00 AM

passed today
Anonymous


Durga 6/23/2023 1:22:00 AM

hi can you please upload questions
Anonymous


JJ 5/28/2023 4:32:00 AM

please upload quetions
THAILAND


Norris 1/3/2023 8:06:00 PM

i passed my exam thanks to this braindumps questions. these questions are valid in us and i highly recommend it!
UNITED STATES


abuti 7/21/2023 6:10:00 PM

are they truely latest
Anonymous


Curtis Nakawaki 7/5/2023 8:46:00 PM

questions appear contemporary.
UNITED STATES


Vv 12/2/2023 6:31:00 AM

good to prepare in this site
UNITED STATES


praveenkumar 11/20/2023 11:57:00 AM

very helpful to crack first attempt
Anonymous


asad Raza 5/15/2023 5:38:00 AM

please upload this exam
CHINA


Reeta 7/17/2023 5:22:00 PM

please upload the c_activate22 dump questions with answer
SWEDEN


Wong 12/20/2023 11:34:00 AM

q10 - the answer should be a. if its c, the criteria will meet if either the prospect is not part of the suppression lists or if the job title contains vice president
MALAYSIA


david 12/12/2023 12:38:00 PM

this was on the exam as of 1211/2023
Anonymous


Tink 7/24/2023 9:23:00 AM

great for prep
GERMANY


Jaro 12/18/2023 3:12:00 PM

i think in question 7 the first answer should be power bi portal (not power bi)
Anonymous


9eagles 4/7/2023 10:04:00 AM

on question 10 and so far 2 wrong answers as evident in the included reference link.
Anonymous


Tai 8/28/2023 5:28:00 AM

wonderful material
SOUTH AFRICA


VoiceofMidnight 12/29/2023 4:48:00 PM

i passed!! ...but barely! got 728, but needed 720 to pass. the exam hit me with labs right out of the gate! then it went to multiple choice. protip: study the labs!
UNITED STATES


A K 8/3/2023 11:56:00 AM

correct answer for question 92 is c -aws shield
Anonymous


Nitin Mindhe 11/27/2023 6:12:00 AM

great !! it is really good
IRELAND


BailleyOne 11/22/2023 1:45:00 AM

explanations for the answers are to the point.
Anonymous


patel 10/25/2023 8:17:00 AM

how can rea next
INDIA


MortonG 10/19/2023 6:32:00 PM

question: 128 d is the wrong answer...should be c
EUROPEAN UNION


Jayant 11/2/2023 3:15:00 AM

thanks for az 700 dumps
Anonymous