CIMA E2 Managing Performance CIMAPRA19-E02-1 Dumps in PDF

Free CIMA CIMAPRA19-E02-1 Real Questions (page: 5)

The difference between the latest event time and the earliest event time in a project network analysis is referred to as:

  1. Critical Activity
  2. Float
  3. Critical Path
  4. Node

Answer(s): B



The Board of organisation Y has authorised an upgrade to its computerised finance system.

The Finance Director, X, has been tasked with managing this project. X has been requested to consult with stakeholders, in order that a Project Initiation Document (PID) may be produced.

What are the TWO main uses of a PID?

  1. To ensure that the project is broken down into work packages and a Work Breakdown Structure be produced.
  2. To produce a risk assessment of both internal and external risks that are likely to effect the project, and alternative actions to reduce the risks.
  3. To ensure that the project has a complete sound basis before any major commitment to
    the project.
  4. To act as a base document against which the project can be managed for progress, change management issues, and ongoing viability issues.

Answer(s): C,D



A highly complex IT project is being tackled by a self-managing team of three technical specialists who had never met each other before.

At first they argued constantly for nearly two days over the best way to tackle the work and what technical software tools to use. Finally these issues were resolved, the team went out for dinner together and they agreed how best to share the workload between them.

After this point, the productivity improved dramatically and good work progress was made. All was going well until two days later when another IT specialist turned up unexpectedly. This person was far less experienced than the other three.

The new arrival explained that he would be taking over as project manager and immediately started to give explicit orders to the team.

In the context of Tuckman's team development theory, which interpretation fits the facts of the scenario.

  1. The team had reached the performing stage but the arrival of the new specialist may result in the team reverting to the storming stage.
  2. The team had reached the norming stage and instructions from the new arrival will quickly help the team reach the performing stage.
  3. The team had already formed and were moving into the storming stage when the new arrival turned up and reset development at the forming stage.
  4. The new arrival will mean that the team will move forward from norming through storming into the final performing stage.

Answer(s): A



Q has been appointed as the Commercial Director of a medium-sized publishing company that is facing strong competitive pressures in difficult trading conditions. Q is surprised to find that the firm is pursuing the formal/rational approach to strategy development.

Q is now preparing a presentation to the Board to change the basis of strategy development to an emergent approach.

Which THREE arguments could Q use in the presentation?

  1. The rational approach takes up significant organisational resources, can be very expensive, time consuming and complicated.
  2. The rational process can end up as a bureaucratic, top-down process focusing on plans, systems and targets, leading to a loss of entrepreneurial spirit.
  3. Given an uncertain business environment, it is impossible for rational strategy makers to make reliable assumptions about the future.
  4. An emergent approach encourages managers to take a longer term view of the development of the business, rather than being short-term and reactive.
  5. From a stakeholder perspective, the emergent approach could be viewed as demonstrating that the organisation has a very clear sense of where it is going.

Answer(s): A,B,C



James argues that performance appraisal has its roots in three substantiated psychological principles, meaning that people work / learn / achieve more when they are given the opportunities.

Which of the following does NOT apply?

  1. Information for human resource planning.
  2. Involvement in the setting of tasks and goals.
  3. Adequate feedback as to how they are performing, in other words knowledge of results.
  4. Clear attainable goals so they know what to strive for.

Answer(s): A



Share your comments for CIMA CIMAPRA19-E02-1 exam with other users:

V
vijay joshi
8/19/2023 3:15:00 AM

please upload free oracle cloud infrastructure 2023 foundations associate exam braindumps

A
Ayodele Talabi
8/25/2023 9:25:00 PM

sweating! they are tricky

R
Romero
3/23/2022 4:20:00 PM

i never use these dumps sites but i had to do it for this exam as it is impossible to pass without using these question dumps.

J
John Kennedy
9/20/2023 3:33:00 AM

good practice and well sites.

N
Nenad
7/12/2022 11:05:00 PM

passed my first exam last week and pass the second exam this morning. thank you sir for all the help and these brian dumps.

L
Lucky
10/31/2023 2:01:00 PM

does anyone who attended exam csa 8.8, can confirm these questions are really coming ? or these are just for practicing?

P
Prateek
9/18/2023 11:13:00 AM

kindly share the dumps

I
Irfan
11/25/2023 1:26:00 AM

very nice content

P
php
6/16/2023 12:49:00 AM

passed today

D
Durga
6/23/2023 1:22:00 AM

hi can you please upload questions

J
JJ
5/28/2023 4:32:00 AM

please upload quetions

N
Norris
1/3/2023 8:06:00 PM

i passed my exam thanks to this braindumps questions. these questions are valid in us and i highly recommend it!

A
abuti
7/21/2023 6:10:00 PM

are they truely latest

C
Curtis Nakawaki
7/5/2023 8:46:00 PM

questions appear contemporary.

V
Vv
12/2/2023 6:31:00 AM

good to prepare in this site

P
praveenkumar
11/20/2023 11:57:00 AM

very helpful to crack first attempt

A
asad Raza
5/15/2023 5:38:00 AM

please upload this exam

R
Reeta
7/17/2023 5:22:00 PM

please upload the c_activate22 dump questions with answer

W
Wong
12/20/2023 11:34:00 AM

q10 - the answer should be a. if its c, the criteria will meet if either the prospect is not part of the suppression lists or if the job title contains vice president

D
david
12/12/2023 12:38:00 PM

this was on the exam as of 1211/2023

T
Tink
7/24/2023 9:23:00 AM

great for prep

J
Jaro
12/18/2023 3:12:00 PM

i think in question 7 the first answer should be power bi portal (not power bi)

9
9eagles
4/7/2023 10:04:00 AM

on question 10 and so far 2 wrong answers as evident in the included reference link.

T
Tai
8/28/2023 5:28:00 AM

wonderful material

V
VoiceofMidnight
12/29/2023 4:48:00 PM

i passed!! ...but barely! got 728, but needed 720 to pass. the exam hit me with labs right out of the gate! then it went to multiple choice. protip: study the labs!

A
A K
8/3/2023 11:56:00 AM

correct answer for question 92 is c -aws shield

N
Nitin Mindhe
11/27/2023 6:12:00 AM

great !! it is really good

B
BailleyOne
11/22/2023 1:45:00 AM

explanations for the answers are to the point.

P
patel
10/25/2023 8:17:00 AM

how can rea next

M
MortonG
10/19/2023 6:32:00 PM

question: 128 d is the wrong answer...should be c

J
Jayant
11/2/2023 3:15:00 AM

thanks for az 700 dumps

B
Bipul Mishra
12/14/2023 7:12:00 AM

thank you for this tableau dumps . it will helpfull for tableau certification

H
hello
10/31/2023 12:07:00 PM

good content

M
Matheus
9/3/2023 2:14:00 PM

just testing if the comments are real

AI Tutor 👋 I’m here to help!