Each of the following accurately describes total float in a schedule EXCEPT:

  1. The amount of time an activity can be delayed without delaying the overall project completion time.
  2. Can be positive or negative.
  3. The amount of time an activity can be delayed without delaying the start or occurrence of any other activity or event in the network.
  4. Computed for an activity by subtracting its early finish from its late finish, or its early start from its late start.

Answer(s): C

Explanation:

Total float measures the flexibility in an activity’s timing within a schedule. It is defined as the amount of time an activity can be delayed without affecting the project’s overall completion date or the completion date of any of its successors.
Option A, B, and D accurately describe total float: it is calculated as the difference between early and late start/finish dates, can be positive or negative, and is associated with project completion.
Option C describes free float, not total float, and thus is incorrect.



The amount of time that an activity can be delayed from its early start date without delaying project completion is called:

  1. Negative float.
  2. Free float.
  3. Total float.
  4. Interfering float.

Answer(s): C

Explanation:

The time an activity can be delayed from its early start without impacting the overall project completion date is called total float.
Option A (negative float) refers to delays beyond permissible limits.
Option B (free float) refers to delays without affecting the early start of any successor.
Option D (interfering float) is a lesser-used term denoting the time available without delaying the project completion but affecting a successor’s float.



In its simplest form, what is the main drawback of critical path method scheduling?

  1. It requires a backward pass to calculate late dates.
  2. It assumes that resources are unlimited.
  3. It doesn't account for interdependent between activities.
  4. It allows for Precedence Diagramming Method to be used in place of Arrow Diagramming Method.

Answer(s): B

Explanation:

A fundamental limitation of Critical Path Method (CPM) scheduling is its assumption of unlimited resources, meaning it does not account for resource constraints when calculating schedules.
Option A (backward pass) is a standard part of the CPM process.
Option C is incorrect as CPM considers activity dependencies.
Option D refers to flexibility in diagramming methods, not a drawback.
The PSP Study Guide highlights resource constraints as a significant challenge in CPM application.



If after calculating a schedule an activity exhibits negative total float, which of the following is certain? The activity

  1. Is a milestone.
  2. It is on the critical path.
  3. Was completed in the past.
  4. Has yet to be completed.

Answer(s): D

Explanation:

Negative total float occurs when an activity’s scheduled completion date extends beyond the project deadline due to constraints. This condition indicates that the activity is still pending and needs immediate attention to avoid further delays.
Option A (milestone) is unrelated.
Option B (critical path) is not necessarily true, as activities with negative float can exist off the critical path under certain constraints.
Option C (completed in the past) is incorrect as negative float applies only to future or ongoing activities.



Which of the following will NOT affect the total float calculation of a non-resource leveled schedule?

  1. Multiple calendars.
  2. Start and finish constraints.
  3. Preferential logic.
  4. Front end loading.

Answer(s): D

Explanation:

Total float is influenced by factors like multiple calendars, start/finish constraints, and preferential logic because these directly affect the calculation of early and late dates.
Option D (front end loading), which involves distributing work to earlier project phases, does not inherently affect float calculations as it primarily pertains to resource or phase management strategies.



You are retained by a contractor who asks you to perform a simple as-planned versus as-built analysis (APAB) of a large hydro-electric dam project that took more than five years to complete. Your analysis will form the basis of a change order that requests a time extension. You suggest using a different methodology for quantifying the delay.
Which of the following reasons for recommending a different analysis does NOT apply to a simple APAB analysis?

  1. Not suitable for complicated projects with multiple planned critical paths.
  2. Accuracy is increased by inserting delaying events into the as-planned schedule.
  3. Not suitable for projects with long durations.
  4. Less accurate as the analysis advances through the project.

Answer(s): B

Explanation:

As-Planned vs. As-Built (APAB) Analysis:
A simple APAB compares the planned schedule to the actual schedule to identify deviations.
It does not involve inserting delaying events or re-forecasting the schedule, which makes it unsuitable for detailed analysis.
Limitations of APAB:
Unsuitable for complex projects (A).
Inserting delays is not part of APAB (B).
Accuracy diminishes for long projects (C) or those requiring granular mid-project analyses (D).
Conclusion: The correct answer is B, as inserting delays into the as-planned schedule is not a feature of simple APAB analysis.



Which statement is true?

  1. Where compensability cannot be established, excusability is assumed.
  2. Where compensability can be established, excusabltity cannot be assumed.
  3. Where compensability cannot be established, excusability is a given.
  4. Where compensability can be established, excusability is assumed.

Answer(s): D

Explanation:

Compensability and Excusability:
Excusable delays are those beyond the contractor’s control, while compensable delays are excusable delays for which the owner bears responsibility.
If a delay is compensable, it inherently qualifies as excusable.
PSP Study Guide Reference:
The relationship between excusability and compensability is clarified in delay analysis discussions.
Conclusion: The correct answer is D, as compensability implies excusability.



Which of the following phases does NOT describe the commonly accepted construction life cycle?

  1. Claims and disputes phase.
  2. Installation phase.
  3. Planning and design phase.
  4. Turnover and start-up phase.

Answer(s): A

Explanation:

Construction Life Cycle Phases:
Common phases: planning and design, installation (execution), and turnover/start-up.
Claims and disputes may arise during the project but are not a defined phase of the construction life cycle.
PSP Study Guide Reference:
The study guide outlines standard phases without including claims and disputes as a formal phase.
Conclusion: The correct answer is A, as claims and disputes are not an inherent phase of the construction life cycle.



Share your comments for AACE International AACE-PSP exam with other users:

T
tumz
1/16/2024 10:30:00 AM

very helpful

N
NRI
8/27/2023 10:05:00 AM

will post once the exam is finished

K
kent
11/3/2023 10:45:00 AM

relevant questions

Q
Qasim
6/11/2022 9:43:00 AM

just clear exam on 10/06/2202 dumps is valid all questions are came same in dumps only 2 new questions total 46 questions 1 case study with 5 question no lab/simulation in my exam please check the answers best of luck

C
Cath
10/10/2023 10:09:00 AM

q.112 - correct answer is c - the event registry is a module that provides event definitions. answer a - not correct as it is the definition of event log

S
Shiji
10/15/2023 1:31:00 PM

good and useful.

A
Ade
6/25/2023 1:14:00 PM

good questions

P
Praveen P
11/8/2023 5:18:00 AM

good content

A
Anastasiia
12/28/2023 9:06:00 AM

totally not correct answers. 21. you have one gcp account running in your default region and zone and another account running in a non-default region and zone. you want to start a new compute engine instance in these two google cloud platform accounts using the command line interface. what should you do? correct: create two configurations using gcloud config configurations create [name]. run gcloud config configurations activate [name] to switch between accounts when running the commands to start the compute engine instances.

P
Priyanka
7/24/2023 2:26:00 AM

kindly upload the dumps

N
Nabeel
7/25/2023 4:11:00 PM

still learning

G
gure
7/26/2023 5:10:00 PM

excellent way to learn

C
ciken
8/24/2023 2:55:00 PM

help so much

B
Biswa
11/20/2023 9:28:00 AM

understand sql col.

S
Saint Pierre
10/24/2023 6:21:00 AM

i would give 5 stars to this website as i studied for az-800 exam from here. it has all the relevant material available for preparation. i got 890/1000 on the test.

R
Rose
7/24/2023 2:16:00 PM

this is nice.

A
anon
10/15/2023 12:21:00 PM

q55- the ridac workflow can be modified using flow designer, correct answer is d not a

N
NanoTek3
6/13/2022 10:44:00 PM

by far this is the most accurate exam dumps i have ever purchased. all questions are in the exam. i saw almost 90% of the questions word by word.

E
eriy
11/9/2023 5:12:00 AM

i cleared the az-104 exam by scoring 930/1000 on the exam. it was all possible due to this platform as it provides premium quality service. thank you!

M
Muhammad Rawish Siddiqui
12/8/2023 8:12:00 PM

question # 232: accessibility, privacy, and innovation are not data quality dimensions.

V
Venkat
12/27/2023 9:04:00 AM

looks wrong answer for 443 question, please check and update

V
Varun
10/29/2023 9:11:00 PM

great question

D
Doc
10/29/2023 9:36:00 PM

question: a user wants to start a recruiting posting job posting. what must occur before the posting process can begin? 3 ans: comment- option e is incorrect reason: as part of enablement steps, sap recommends that to be able to post jobs to a job board, a user need to have the correct permission and secondly, be associated with one posting profile at minimum

I
It‘s not A
9/17/2023 5:31:00 PM

answer to question 72 is d [sys_user_role]

I
indira m
8/14/2023 12:15:00 PM

please provide the pdf

R
ribrahim
8/1/2023 6:05:00 AM

hey guys, just to let you all know that i cleared my 312-38 today within 1 hr with 100 questions and passed. thank you so much brain-dumps.net all the questions that ive studied in this dump came out exactly the same word for word "verbatim". you rock brain-dumps.net!!! section name total score gained score network perimeter protection 16 11 incident response 10 8 enterprise virtual, cloud, and wireless network protection 12 8 application and data protection 13 10 network défense management 10 9 endpoint protection 15 12 incident d

A
Andrew
8/23/2023 6:02:00 PM

very helpful

L
latha
9/7/2023 8:14:00 AM

useful questions

I
ibrahim
11/9/2023 7:57:00 AM

page :20 https://exam-dumps.com/snowflake/free-cof-c02-braindumps.html?p=20#collapse_453 q 74: true or false: pipes can be suspended and resumed. true. desc.: pausing or resuming pipes in addition to the pipe owner, a role that has the following minimum permissions can pause or resume the pipe https://docs.snowflake.com/en/user-guide/data-load-snowpipe-intro

F
Franklin Allagoa
7/5/2023 5:16:00 AM

i want hcia exam dumps

S
SSA
12/24/2023 1:18:00 PM

good training

B
BK
8/11/2023 12:23:00 PM

very useful

D
Deepika Narayanan
7/13/2023 11:05:00 PM

yes need this exam dumps

B
Blessious Phiri
8/15/2023 3:31:00 PM

these questions are a great eye opener

AI Tutor 👋 I’m here to help!