In which Phase of the ADM does the business scenario technique figure most prominently?

  1. Preliminary
  2. Architecture Vision
  3. Business Architecture
  4. Information Systems Architectures
  5. Technology Architecture

Answer(s): B



Which one of the following best describes the Architecture Vision document?

  1. An agreement between development partners and the sponsor on architecture deliverables
  2. A description of how the new capability will address stakeholder concerns
  3. A description of the scope and approach for completion of the architecture project
  4. A set of quantitative statements outlining requirements on the implementation
  5. A set of rules and guidelines to support fulfilling the mission of the organization

Answer(s): B



Which of the following best describes TOGAF?

  1. An abstract framework for the development of standards and processes for a business architecture
  2. A collection of components organized to accomplish a specific set of functions
  3. A process model, best practices and assets to aid production, use and maintenance of enterprise architectures
  4. A reference model containing taxonomy defining terminology for an enterprise architecture, together with an associated graphic
  5. A system development lifecycle method for software engineering

Answer(s): C



Which ADM phase establishes the connection between the architecture organization and the implementation organization through the Architecture Contract?

  1. Phase E
  2. Phase F
  3. Phase G
  4. Phase H
  5. Requirements Management

Answer(s): C



Which one of the following statements about the Requirements Management phase is true?

  1. All requirements fed into the phase are prioritized, and those of low priority are deferred until the next iteration of the ADM cycle
  2. The phase generates the requirements for a given ADM cycle using the Business Scenario technique
  3. The phase manages the flow of requirements, storing them, and feeding them in and out of the relevant ADM phases
  4. The phase operates like a waiting room, and all requirements fed in to the phase must be resolved by the end of the current ADM cycle
  5. The phase resolves the requirements that are fed into it from the other ADM phases

Answer(s): C



Viewing Page 11 of 73



Share your comments for The Open Group OG0-093 exam with other users:

Nagendra Pedipina 7/13/2023 2:12:00 AM

q:32 answer has to be option c
INDIA


Nagendra Pedipina 7/12/2023 9:10:00 AM

q:37 c is correct
INDIA


Madan 6/22/2023 9:22:00 AM

thank you for making the interactive questions
Anonymous


Nagendra Pedipina 7/13/2023 2:22:00 AM

q:42 there has to be a image in the question to choose what does it mean from the options
INDIA