Which of the following checks to see if the assessable record exists for the demand and creates an assessable record if none exists?

  1. Validate Assessment Metrics for Demand
  2. Auto Business Rule for Assessments
  3. Update Demand State
  4. Create OnDemand Assessment

Answer(s): D



Projects and which other artifact can be linked to either a program, a portfolio, both, or neither.

  1. Demands
  2. Test Cases
  3. Resources
  4. Stories

Answer(s): A



If Scenario Planning for PPM is installed, a portfolio manager can access the Portfolio Planning Workbench by navigating to which of the following? (Choose two.)

  1. Project module
  2. Program Workbench
  3. Portfolio Planning related link
  4. Portfolio Planning Workbench module

Answer(s): C,D



When creating a resource plan within a demand, how are the default dates on a resource plan determined?

  1. From demand start date and due date
  2. Resource plan(s) cannot be created from demand
  3. Using demand created date
  4. From portfolio date

Answer(s): A



A customer requires five (5) teamspaces to support different departments. What should you do?

  1. Enable the teamspace property.
  2. Contact the Account Representative to activate the teamspaces.
  3. Activate via each teamspace plugin.
  4. Use UI Policies and Business Rules to enable teamspaces.

Answer(s): C



Viewing Page 1 of 23



Share your comments for ServiceNow® CIS-PPM exam with other users:

anon 10/15/2023 12:21:00 PM

q55- the ridac workflow can be modified using flow designer, correct answer is d not a
UNITED STATES