Who should make sure everyone on the Development Team does his or her tasks for the Sprint?

  1. The Project Manager.
  2. The Product Owner.
  3. The Scrum Master.
  4. The Development Team.
  5. All of the above.

Answer(s): D


Reference:

https://backlog.com/blog/quick-guide-scrum-roles-responsibilities/



When is it most appropriate for a Development Team to change the definition of “Done”?

  1. During Spring Planning.
  2. Prior to starting a new Sprint.
  3. During the Sprint Retrospective.
  4. Prior to starting a new project.

Answer(s): C



The Daily Scrum is an event that happens every day.
What would be three key concerns if the frequency were to be lowered to every two or three days? (Choose three.)

  1. Opportunities to inspect and adapt the Sprint Backlog are lost.
  2. Impediments are raised and resolved more slowly.
  3. The Product Owner cannot accurately report progress to the stakeholders.
  4. Too much work is spent updating the Scrum board before the meeting.
  5. The Scrum Master loses the ability to update the Gantt chart properly.
  6. The Sprint plan may become inaccurate.

Answer(s): A,B,F



Which statement best describes Scrum?

  1. A defined and predictive process that conforms to the principles of Scientific Management.
  2. A complete methodology that defines how to develop software.
  3. A cookbook that defines best practices for software development.
  4. A framework within which complex products in complex environments are developed.

Answer(s): D


Reference:

https://medium.com/pm101/get-the-scrum-certification-studying-on-your-own-cba68459fe1#:~:text=Scrum%20is%20a%20framework%20for,to%20Scrum's%20success%20and%20usage



Which Scrum Values are exhibited by not building Product Backlog items that have low business value? (Choose three.)

  1. Economic Value Added.
  2. Respect.
  3. Focus.
  4. Earned Value.
  5. Courage.

Answer(s): B,C,E



Viewing Page 8 of 48



Share your comments for Scrum PSM I exam with other users:

Umashankar Sharma 10/22/2023 9:39:00 AM

planning to take psm test
Anonymous


Aderonke 10/23/2023 2:13:00 PM

helpful assessment
UNITED KINGDOM


Aderonke 10/31/2023 12:51:00 AM

fantastic assessments
Anonymous


Krishneel 3/17/2023 10:34:00 AM

i just passed. this exam dumps is the same one from prepaway and examcollection. it has all the real test questions.
INDIA


Rajender 10/18/2023 3:54:00 AM

i would like to take psm1 exam.
Anonymous


Aderonke 10/23/2023 12:53:00 PM

fantastic assessment on psm 1
UNITED KINGDOM


Aderonke 10/23/2023 1:07:00 PM

very helpful assessments
UNITED KINGDOM


Roberto Capra 6/14/2023 12:04:00 PM

nice questions... are these questions the same of the exam?
Anonymous


Aderonke 10/23/2023 1:52:00 PM

brilliant and helpful
UNITED KINGDOM


francesco 10/30/2023 11:08:00 AM

helpful on 2017 scrum guide
EUROPEAN UNION


vinay 9/4/2023 10:23:00 AM

really nice
Anonymous


Ashwini 8/22/2023 5:13:00 AM

it really helped
Anonymous


Jude 8/29/2023 1:56:00 PM

why is the answer to "which of the following is required by scrum?" all of the following stated below since most of them are not mandatory? sprint retrospective. members must be stand up at the daily scrum. sprint burndown chart. release planning.
UNITED STATES