The purpose of a Sprint is to produce a done Increment of product.

  1. True
  2. False

Answer(s): A


Reference:

https://www.knowledgehut.com/tutorials/scrum-tutorial/product-increment



Who creates the definition of “Done”?

  1. The Scrum Master as he/she is responsible for the Development Team’s productivity.
  2. The Scrum Team, in a collaborative effort where the result is the common denominator of all members’ definition.
  3. The Product Owner as he/she is responsible for the product’s success.
  4. The development organization (or Development Team if none is available from the development organization).

Answer(s): D



Five new Scrum Teams have been created to build one product. A few of the developers on one of the Development Teams ask the Scrum Master how to coordinate their work with the order teams.
What should the Scrum Master do?

  1. Teach the Product Owner to work with the lead developers on ordering Product Backlog in a way to avoid too much technical and development overlap during a Sprint.
  2. Teach them that it is their responsibility to work with the other teams to create an integrated Increment.
  3. Collect the Sprint tasks from the teams at the end of their Sprint Planning and merge that into a consolidated plan for the entire Sprint.
  4. Visit the five teams each day to inspect that their Sprint Backlogs are aligned.

Answer(s): C



Which two things should the Development Team do during the first Sprint? (Choose two.)

  1. Make up a plan for the rest of the project.
  2. Analyze, describe, and document the requirements for the subsequent Sprints.
  3. Develop at least one piece of functionality.
  4. Analyze, design, and describe the complete architecture and infrastructure.
  5. Create an increment of potentially releasable software.

Answer(s): C,E



What are three ways Scrum promotes self-organization? (Choose three.)

  1. By not allowing documentation.
  2. By the Development Team deciding what work to do in a Sprint.
  3. By preventing stakeholders from entering the development room.
  4. By removing titles for Development Team members.
  5. By being a lightweight framework.

Answer(s): B,D,E



Viewing Page 4 of 48



Share your comments for Scrum PSM I exam with other users:

Umashankar Sharma 10/22/2023 9:39:00 AM

planning to take psm test
Anonymous


Aderonke 10/23/2023 2:13:00 PM

helpful assessment
UNITED KINGDOM


Aderonke 10/31/2023 12:51:00 AM

fantastic assessments
Anonymous


Krishneel 3/17/2023 10:34:00 AM

i just passed. this exam dumps is the same one from prepaway and examcollection. it has all the real test questions.
INDIA


Rajender 10/18/2023 3:54:00 AM

i would like to take psm1 exam.
Anonymous


Aderonke 10/23/2023 12:53:00 PM

fantastic assessment on psm 1
UNITED KINGDOM


Aderonke 10/23/2023 1:07:00 PM

very helpful assessments
UNITED KINGDOM


Roberto Capra 6/14/2023 12:04:00 PM

nice questions... are these questions the same of the exam?
Anonymous


Aderonke 10/23/2023 1:52:00 PM

brilliant and helpful
UNITED KINGDOM


francesco 10/30/2023 11:08:00 AM

helpful on 2017 scrum guide
EUROPEAN UNION


vinay 9/4/2023 10:23:00 AM

really nice
Anonymous


Ashwini 8/22/2023 5:13:00 AM

it really helped
Anonymous


Jude 8/29/2023 1:56:00 PM

why is the answer to "which of the following is required by scrum?" all of the following stated below since most of them are not mandatory? sprint retrospective. members must be stand up at the daily scrum. sprint burndown chart. release planning.
UNITED STATES