In your plant MRP is activated.

Which options do you have to exclude a material from the MRP run?
Note: There are 2 correct answers to this question.

  1. Use a specific MRP list.
  2. Use a specific material status.
  3. Use a specific material group.
  4. Use a specific MRP type.

Answer(s): B,D



In documentation for MRP in Advanced Planning you read that new orders are created through infinite planning.
What does this mean for the capacity requirements of a new order?

  1. MRP assigns the capacity requirements automatically after the last scheduled operation for each work center.
  2. MRP creates the capacity requirements without considering existing load on the work centers.
  3. MRP creates the capacity requirements at the earliest possible time.
  4. MRP assigns the capacity requirements automatically to work centers with the earliest available capacity.

Answer(s): A



Which master data fields can have an impact on whether MRP creates planned orders or purchase requisitions for a material?
Note: There are 2 correct answers to this question.

  1. Procurement type
  2. Material type
  3. MRP type
  4. MRP group

Answer(s): A,B



You have a scheduling agreement with a vendor. You want classic MRP to automatically create schedule lines in case of material shortage.
What must you do?

Note: There are 2 correct answers to this question.

  1. Set the creation indicator for purchase requisitions on the initial screen of the MRP run.
  2. Add the agreement to the source list mark it for MRP relevance.
  3. Set the creation indicator for delivery schedule lines on the initial screen of the MRP run.
  4. Add the agreement to the quota arrangement mark it for MRP relevance.

Answer(s): B,C



How are dependent requirements for assemblies created?
Note: There are 2 correct answers to this question.

  1. They are created together with the independent requirement for the finished product.
  2. They are created on assembly level during the planning run.
  3. They are created with exact times in Advanced Planning.
  4. They are only created for multilevel bill of material (BOM) structures.

Answer(s): B,C



Which time elements does MRP consider in backward scheduling to determine the basic dates for components from depender
Note: There are 2 correct answers to this question.

  1. Planned delivery time
  2. Total replenishment lead time
  3. Operation duration
  4. Inhouse production time

Answer(s): A,D



What determines whether the planned independent requirements in dem management are consumed by other requirements?
Note: There are 2 correct answers to this question.

  1. Order type
  2. Requirements profile
  3. Requirements type
  4. Planning strategy

Answer(s): C,D



What does forecasting in the dem planning cycle include?
Note: There are 3 correct answers to this question.

  1. Oneoff events
  2. Past production planning quantities
  3. Past quotation quantities
  4. Market intelligence
  5. Past sales order quantities

Answer(s): A,D,E



Viewing Page 2 of 12



Share your comments for SAP C_TS422_2504 exam with other users:

Merry 7/30/2023 6:57:00 AM

good questions
Anonymous


VoiceofMidnight 12/17/2023 4:07:00 PM

Delayed the exam until December 29th.
UNITED STATES


Umar Ali 8/29/2023 2:59:00 PM

A and D are True
Anonymous


vel 8/28/2023 9:17:09 AM

good one with explanation
Anonymous


Gurdeep 1/18/2024 4:00:15 PM

This is one of the most useful study guides I have ever used.
CANADA