Which sets of dates can be used to schedule networks?
Note: There are 2 correct answers to this question

  1. Basic dates
  2. Forecast dates
  3. Baseline dates
  4. Planned dates

Answer(s): A,D

Explanation:

Basic dates and planned dates are some of the sets of dates that can be used to schedule networks. Basic dates are the earliest possible start and finish dates of an activity or a network, based on its dependencies and constraints. Planned dates are the scheduled start and finish dates of an activity or a network, based on its basic dates and available capacities.


Reference:

https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en- US/6a7a9f0a6e421014e10000000a174cb4.html



Which sales documents can update planned revenues on WBS elements?
Note: There are 2 correct answers to this question

  1. Sales order
  2. Billing
  3. Quotation
  4. Inquiry

Answer(s): A,B

Explanation:

Sales order and billing are some of the sales documents that can update planned revenues on WBS elements. Sales order is a document that records a customer's request for goods or services from a sales organization. Billing is a document that records the delivery of goods or services to a customer and requests payment for them. Both sales order and billing can update planned revenues on WBS elements if they are assigned to them directly or indirectly via network activities.


Reference:

https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en- US/6a7a9f0a6e421014e10000000a174cb4.html



You want to determine the planned costs for an internally processed activity.
Which data do you need
Note: There are 2 correct answers to this question

  1. Duration
  2. Activity type
  3. Work
  4. Profit center

Answer(s): A,B

Explanation:

To determine the planned costs for an internally processed activity, you need the duration and activity type data. The duration is the time required to complete the activity. The activity type is a classification of activities according to their functions or characteristics. The system calculates the planned costs for an internally processed activity based on the formula for costing in the work center, the activity output price for the activity type and cost center assigned to the work center, and the duration of the activity.


Reference:

https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en- US/6a7a9f0a6e421014e10000000a174cb4.html



What are some of the advantages of using project simul-ations?
Note: There are 3 correct answers to this question

  1. Project simulations allow posting of actual data
  2. Project simulations can be created without using an operational project as a template
  3. Project simulations can be used to plan structures and costs
  4. Project simulations can create purchase requisitions
  5. Multiple project simulations can be used simultaneously

Answer(s): B,C,E

Explanation:

Project simulations are some of the advantages of using project simulations in SAP Project System. Project simulations are copies of projects that allow you to plan and simulate different scenarios without affecting operational projects. Project simulations can be created without using an operational project as a template, which means you can start from scratch or use a standard structure. Project simulations can be used to plan structures and costs, which means you can create and change WBS elements, networks, activities, and cost elements. Multiple project simulations can be used simultaneously, which means you can compare different alternatives and choose the best one.


Reference:

https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en- US/6a7a9f0a6e421014e10000000a174cb4.html



Which statements describe planned and actual revenue for WBS elements?
Note: There are 2 correct answers to this question

  1. Planned revenue requires a sales order assigned to a WBS element
  2. Planned revenue can be transferred from a sales quotation
  3. Actual revenue is posted via a billing plan assigned to a WBS element
  4. Actual revenue is posted via a billing document created from a sales order

Answer(s): A,D

Explanation:

Planned revenue and actual revenue are two types of revenue for WBS elements in SAP Project System. Planned revenue requires a sales order assigned to a WBS element, which means that the sales order item contains the data for revenue planning, such as quantity, price, and billing plan. Actual revenue is posted via a billing document created from a sales order, which means that the billing document records the delivery of goods or services to a customer and requests payment for them.


Reference:

https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en- US/6a7a9f0a6e421014e10000000a174cb4.html



Viewing Page 4 of 23



Share your comments for SAP C_TS412_2021 exam with other users:

Vavz 11/2/2023 6:51:00 AM

questions are accurate
Anonymous


Su 11/23/2023 4:34:00 AM

i need questions/dumps for this exam.
Anonymous


LuvSN 7/16/2023 11:19:00 AM

i need this exam, when will it be uploaded
ROMANIA


Mihai 7/19/2023 12:03:00 PM

i need the dumps !
Anonymous


Wafa 11/13/2023 3:06:00 AM

very helpful
Anonymous


Alokit 7/3/2023 2:13:00 PM

good source
Anonymous


Show-Stopper 7/27/2022 11:19:00 PM

my 3rd test and passed on first try. hats off to this brain dumps site.
UNITED STATES


Michelle 6/23/2023 4:06:00 AM

please upload it
Anonymous


Lele 11/20/2023 11:55:00 AM

does anybody know if are these real exam questions?
EUROPEAN UNION


Girish Jain 10/9/2023 12:01:00 PM

are these questions similar to actual questions in the exam? because they seem to be too easy
Anonymous


Phil 12/8/2022 11:16:00 PM

i have a lot of experience but what comes in the exam is totally different from the practical day to day tasks. so i thought i would rather rely on these brain dumps rather failing the exam.
GERMANY


BV 6/8/2023 4:35:00 AM

good questions
NETHERLANDS


krishna 12/19/2023 2:05:00 AM

valied exam dumps. they were very helpful and i got a pretty good score. i am very grateful for this service and exam questions
Anonymous


Pie 9/3/2023 4:56:00 AM

will it help?
INDIA


Lucio 10/6/2023 1:45:00 PM

very useful to verify knowledge before exam
POLAND


Ajay 5/17/2023 4:54:00 AM

good stuffs
Anonymous


TestPD1 8/10/2023 12:19:00 PM

question 17 : responses arent b and c ?
EUROPEAN UNION


Nhlanhla 12/13/2023 5:26:00 AM

just passed the exam on my first try using these dumps.
Anonymous


Rizwan 1/6/2024 2:18:00 AM

very helpful
INDIA


Yady 5/24/2023 10:40:00 PM

these questions look good.
SINGAPORE


Kettie 10/12/2023 1:18:00 AM

this is very helpful content
Anonymous


SB 7/21/2023 3:18:00 AM

please provide the dumps
UNITED STATES


David 8/2/2023 8:20:00 AM

it is amazing
Anonymous


User 8/3/2023 3:32:00 AM

quesion 178 about "a banking system that predicts whether a loan will be repaid is an example of the" the answer is classification. not regresion, you should fix it.
EUROPEAN UNION


quen 7/26/2023 10:39:00 AM

please upload apache spark dumps
Anonymous


Erineo 11/2/2023 5:34:00 PM

q14 is b&c to reduce you will switch off mail for every single alert and you will switch on daily digest to get a mail once per day, you might even skip the empty digest mail but i see this as a part of the daily digest adjustment
Anonymous


Paul 10/21/2023 8:25:00 AM

i think it is good question
Anonymous


Unknown 8/15/2023 5:09:00 AM

good for students who wish to give certification.
INDIA


Ch 11/20/2023 10:56:00 PM

is there a google drive link to the images? the links in questions are not working.
AUSTRALIA


Joey 5/16/2023 5:25:00 AM

very promising, looks great, so much wow!
Anonymous


alaska 10/24/2023 5:48:00 AM

i scored 87% on the az-204 exam. thanks! i always trust
GERMANY


nnn 7/9/2023 11:09:00 PM

good need more
Anonymous


User-sfdc 12/29/2023 7:21:00 AM

sample questions seems good
Anonymous


Tamer dam 8/4/2023 10:21:00 AM

huawei is ok
UNITED STATES