A customer needs to analyze the capacity requirements of their network activities.
Which reports do you recommend?
Note: There are 2 correct answers to this question

  1. Resource reports
  2. Cost element reports
  3. Structure information system reports
  4. Hierarchical reports

Answer(s): A,D

Explanation:

Resource reports and hierarchical reports are some of the possible reports that you can use to analyze the capacity requirements of your network activities. Resource reports display capacity requirements and availability for work centers or resources over a period of time. Hierarchical reports display capacity requirements and availability for work centers or resources in a hierarchical structure, such as plant, MRP controller, or work center group.


Reference:

https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en- US/6a7a9f0a6e421014e10000000a174cb4.html



You are using WBS elements and activities are NOT assigned.
Which statements apply to the maintenance of the actual start and finish?
Note: There are 2 correct answers to this question

  1. You can only maintain the actual finish if all lower-level WBS elements have an actual finish date and the status of the WBS element is "Released"
  2. You can always maintain the actual start if the WBS element has the status "Released" or "Partially released"
  3. You can always maintain the actual start and finish date of a WBS element
  4. You can only maintain the actual start of a WBS element if the finish date is not maintained

Answer(s): B,C

Explanation:

If you are using WBS elements and activities are not assigned, you can always maintain the actual start and finish date of a WBS element manually or automatically. However, you can only maintain the actual start if the WBS element has the status "Released" or "Partially released", which means it is ready for processing or partially ready for processing. You can maintain the actual finish regardless of the status of the WBS element.


Reference:

https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-

US/6a7a9f0a6e421014e10000000a174cb4.html



What functions are available for period end closing in SAP Project System?
Note: There are 3 correct answers to this question

  1. Settlement
  2. Milestone trend analysis
  3. Confirmations
  4. Progress analysis
  5. Results analysis

Answer(s): A,D,E

Explanation:

Settlement, progress analysis, and results analysis are some of the functions available for period end closing in SAP Project System. Settlement is used to allocate the costs and revenues in projects or the results analysis data to one or more receivers, such as cost centers, profitability segments, or assets. Progress analysis is used to determine and compare the planned and actual project progress values, based on the overall planned costs and the work done. Results analysis is used to perform a periodic valuation of the project, based on the costs and revenues expected or incurred in the project.


Reference:

https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en- US/6a7a9f0a6e421014e10000000a174cb4.html



Where can you assign the use status profile for WBS elements?
Note: There are 3correct answers to this question

  1. In the project profile
  2. In the project version
  3. In the project type
  4. In the project definition of a standard WBS
  5. In the operative WBS element

Answer(s): A,C,E

Explanation:

User status profiles are used to define additional statuses for project objects that can control their business processes. You can assign user status profiles for WBS elements in the project profile, which is a template for creating projects with similar characteristics. You can also assign user status profiles for WBS elements in the project type, which is a classification of projects according to their objectives and characteristics. You can also assign user status profiles for WBS elements in the operative WBS element itself, which is a structural element of a project that represents a task or a partial task.


Reference:

https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en- US/6a7a9f0a6e421014e10000000a174cb4.html



Which organizational structures are required for network activities?
Note: There are 3 correct answers to this question

  1. Controlling area
  2. Plant
  3. Sales organization
  4. Company code
  5. Operating concern

Answer(s): A,B,D

Explanation:

Controlling area, plant, and company code are some of the organizational structures required for network activities. Controlling area is an organizational unit that represents a closed system for cost accounting purposes. Plant is an organizational unit that represents a location where materials are produced or services are provided. Company code is an organizational unit that represents an independent accounting entity with its own balance sheet and profit and loss statement.


Reference:

https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en- US/6a7a9f0a6e421014e10000000a174cb4.html



Viewing Page 3 of 23



Share your comments for SAP C_TS412_2021 exam with other users:

Sridhar 1/16/2024 9:19:00 PM

good questions
Anonymous


Summer 10/4/2023 9:57:00 PM

looking forward to the real exam
Anonymous


vv 12/2/2023 2:45:00 PM

good ones for exam preparation
UNITED STATES


Danny Zas 9/15/2023 4:45:00 AM

this is a good experience
UNITED STATES


SM 1211 10/12/2023 10:06:00 PM

hi everyone
UNITED STATES


A 10/2/2023 6:08:00 PM

waiting for the dump. please upload.
UNITED STATES


Anonymous 7/16/2023 11:05:00 AM

upload cks exam questions
Anonymous


Johan 12/13/2023 8:16:00 AM

awesome training material
NETHERLANDS


PC 7/28/2023 3:49:00 PM

where is dump
Anonymous


YoloStar Yoloing 10/22/2023 9:58:00 PM

q. 289 - the correct answer should be b not d, since the question asks for the most secure way to provide access to a s3 bucket (a single one), and by principle of the least privilege you should not be giving access to all buckets.
Anonymous


Zelalem Nega 5/14/2023 12:45:00 PM

please i need if possible h12-831,
UNITED KINGDOM


unknown-R 11/23/2023 7:36:00 AM

good collection of questions and solution for pl500 certification
UNITED STATES


Swaminathan 5/11/2023 9:59:00 AM

i would like to appear the exam.
Anonymous


Veenu 10/24/2023 6:26:00 AM

i am very happy as i cleared my comptia a+ 220-1101 exam. i studied from as it has all exam dumps and mock tests available. i got 91% on the test.
Anonymous


Karan 5/17/2023 4:26:00 AM

need this dump
Anonymous


Ramesh Kutumbaka 12/30/2023 11:17:00 PM

its really good to eventuate knowledge before appearing for the actual exam.
Anonymous


anonymous 7/20/2023 10:31:00 PM

this is great
CANADA


Xenofon 6/26/2023 9:35:00 AM

please i want the questions to pass the exam
UNITED STATES


Diego 1/21/2024 8:21:00 PM

i need to pass exam
Anonymous


Vichhai 12/25/2023 3:25:00 AM

great, i appreciate it.
AUSTRALIA


P Simon 8/25/2023 2:39:00 AM

please could you upload (isc)2 certified in cybersecurity (cc) exam questions
SOUTH AFRICA


Karim 10/8/2023 8:34:00 PM

good questions, wrong answers
Anonymous


Itumeleng 1/6/2024 12:53:00 PM

im preparing for exams
Anonymous


MS 1/19/2024 2:56:00 PM

question no: 42 isnt azure vm an iaas solution? so, shouldnt the answer be "no"?
Anonymous


keylly 11/28/2023 10:10:00 AM

im study azure
Anonymous


dorcas 9/22/2023 8:08:00 AM

i need this now
Anonymous


treyf 11/9/2023 5:13:00 AM

i took the aws saa-c03 test and scored 935/1000. it has all the exam dumps and important info.
UNITED STATES


anonymous 1/11/2024 4:50:00 AM

good questions
Anonymous


Anjum 9/23/2023 6:22:00 PM

well explained
Anonymous


Thakor 6/7/2023 11:52:00 PM

i got the full version and it helped me pass the exam. pdf version is very good.
INDIA


sartaj 7/18/2023 11:36:00 AM

provide the download link, please
INDIA


loso 7/25/2023 5:18:00 AM

please upload thank.
THAILAND


Paul 6/23/2023 7:12:00 AM

please can you share 1z0-1055-22 dump pls
UNITED STATES


exampei 10/7/2023 8:14:00 AM

i will wait impatiently. thank youu
Anonymous