Which time elements are considered during backwards scheduling for planned orders?
Note: There are 3 correct answers to this question.

  1. Goods receipt processing time
  2. Opening period
  3. Quality inspection time
  4. Goods issue processing time
  5. In-house production time

Answer(s): A,B,E



A goods receipt is posted for a production order.
What are the results?
Note: There are 3 correct answers to this question.

  1. Actual costs are credited to the production order.
  2. A EWM inbound delivery order could be created.
  3. The production order is deleted in the stock/requirements list.
  4. The stock account is credited.
  5. Internal labor costs are posted.

Answer(s): A,B,C



What documents can be generated during an MRP Live Run for external procured materials?
Note:
There are 2 correct answers to this question.

  1. Purchase Order
  2. Purchase Requisition
  3. Schedule Line
  4. Planned Order

Answer(s): B,D



During the period-end closing, what steps can be run with background processing?
Note: There are 3 correct answers to this question.

  1. Order release
  2. Order confirmation
  3. WIP determination
  4. Variance Calculation
  5. Order settlement

Answer(s): C,D,E



Which areas are covered in SAP Integrated Business Planning?
Note: There are 3 correct answers to this question.

  1. Cost Center Planning
  2. Demand-driven replenishment
  3. Supplier Lifecycle Management
  4. Inventory
  5. Supply Chain Control Tower

Answer(s): B,D,E



When running MRP, what setting in the material master determines whether a material will be procured or produced?

  1. MRP type
  2. Procurement type
  3. Purchasing group
  4. Processing key

Answer(s): B



What does a work center control?
Note: There are 2 correct answers to this question.

  1. Calculation of costs of work performed
  2. Release of production orders
  3. Availability of capacity
  4. Valuation of bill of material components

Answer(s): A,C



Which values need to be settled to Financial Accounting and Margin Analysis during settlement of a production order?
Note: There are 3 correct answers to this question.

  1. Work in Progress
  2. Variance Categories
  3. Confirmation of Time
  4. Goods issue postings of materials
  5. Price Differences

Answer(s): A,B,E



Share your comments for SAP C_IEE2E_2404 exam with other users:

V
vel
8/28/2023 9:17:09 AM

good one with explanation

G
Gurdeep
1/18/2024 4:00:15 PM

This is one of the most useful study guides I have ever used.

AI Tutor 👋 I’m here to help!