Major changes to a software process should start with

  1. conducting a formal assessment
  2. obtaining management commitment
  3. developing a project plan
  4. establishing firm requirements

Answer(s): B



In which phase of a project's development life cycle does the lack of requirements control prove most costly?

  1. Requirements
  2. Design
  3. Test
  4. Maintenance

Answer(s): D



Which of the following is a benefit of using the goal-question-metric paradigm when software metrics are selected?

  1. Only well-defined metrics are selected.
  2. Metrics are selected on the basis of organizational objectives.
  3. Buy-in from the project personnel is achieved for the selected metrics.
  4. Metric models are simplified to include only the most important elements.

Answer(s): B



Equivalence class partitioning is a testing technique best defined as the organization of each

  1. element of the specification into workable pieces
  2. combination of states into two or more groups
  3. program function by intuition and experience
  4. input domain into two or more groups

Answer(s): D



Which of the following statements is true about software requirements baselines?

  1. They are the basis for software change control.
  2. They are established during the planning phase.
  3. They are not used until the testing phase.
  4. They are placed under version control and not changed until the next release.

Answer(s): A



Share your comments for Quality Assurance CSQE exam with other users:

V
VoiceofMidnight
12/17/2023 4:07:00 PM

Delayed the exam until December 29th.

U
Umar Ali
8/29/2023 2:59:00 PM

A and D are True

V
vel
8/28/2023 9:17:09 AM

good one with explanation