During Executing a Work package, specialist products are created and quality reviews are carried out - which management product captures the details of these reviews?

  1. Team Plan
  2. Checkpoint Report
  3. Quality Register
  4. Configuration Item Record

Answer(s): C



During a work package the Team manager needs to keep the project manager informed, which management product is used for this?

  1. Highlight report
  2. Checkpoint Report
  3. Issue Report
  4. End Stage Report

Answer(s): B



HOTSPOT
Column 1 is a list of entries from the Daily Log that occurred during stage 4 in the Controlling a Stage process. For each entry in Column 1, select the first management product from Column 2 that should have been updated, or created, as a result of the entry. Each selection from Column 2 can be used once, more than once or not at all.
Drop down the right answer from column 1 to column 2.
Hot Area:
Exhibit A:


Exhibit B:

  1. Please refer to Exhibit B for answer.

Answer(s): A



While producing the Team Plan to deliver the agreed Work Package, it became apparent that the user representatives assigned 10 check some of the products were unsuitable.
Which 2 actions should the Team Manager take in response to this situation?

  1. Consult the Senior Supplier to assign suitable reviewers.
  2. Discuss the situation with Project Assurance and agree the changes or additions to the reviewers. Advise the Project Manager of this risk.
  3. Ensure the Quality Register is updated with details of the agreed amendments to the reviewers.
  4. Notify the Project Manager by raising an Exception Report explaining that the original reviewers are unsuitable.

Answer(s): A,B



The chair of a quality review meeting advised the Team Manager that, because there were so many major issues, the product had been rejected. The presenter estimated that the corrections would take about two weeks. The re-assessment of the product will take a further week, resulting in a three-week delay. The Work Package only has one week tolerance.
Which 2 actions should the Team Manager take in response to this situation?

  1. Ask the reviewers to work overtime to prevent the delay.
  2. Ensure that the situation is included in the next Highlight Report.
  3. Raise an issue explaining that tolerances are forecast to be exceeded.
  4. Advise the Project Manager of the risk that there may be a two-week delay in the delivery of one of the products.
  5. Ensure that the Quality Register is updated with the quality review result.

Answer(s): C,E



Share your comments for PRINCE2 PRINCE2 Practitioner exam with other users:

D
Daryl
8/1/2022 11:33:00 PM

i really like the support team in this website. they are fast in communication and very helpful.

C
Curtis Nakawaki
6/29/2023 9:13:00 PM

a good contemporary exam review

X
x-men
5/23/2023 1:02:00 AM

q23, its an array, isnt it? starts with [ and end with ]. its an array of objects, not object.

A
abuti
7/21/2023 6:24:00 PM

cool very helpfull

K
Krishneel
3/17/2023 10:34:00 AM

i just passed. this exam dumps is the same one from prepaway and examcollection. it has all the real test questions.

R
Regor
12/4/2023 2:01:00 PM

is this a valid prince2 practitioner dumps?

A
asl
9/14/2023 3:59:00 PM

all are relatable questions

S
Siyya
1/19/2024 8:30:00 PM

might help me to prepare for the exam

T
Ted
6/21/2023 11:11:00 PM

just paid and downlaod the 2 exams using the 50% sale discount. so far i was able to download the pdf and the test engine. all looks good.

P
Paul K
11/27/2023 2:28:00 AM

i think it should be a,c. option d goes against the principle of building anything custom unless there are no work arounds available

P
ph
6/16/2023 12:41:00 AM

very legible

S
sephs2001
7/31/2023 10:42:00 PM

is this exam accurate or helpful?

A
ash
7/11/2023 3:00:00 AM

please upload dump, i have exam in 2 days

S
Sneha
8/17/2023 6:29:00 PM

this is useful

S
sachin
12/27/2023 2:45:00 PM

question 232 answer should be perimeter not netowrk layer. wrong answer selected

T
tomAws
7/18/2023 5:05:00 AM

nice questions

R
Rahul
6/11/2023 2:07:00 AM

hi team, could you please provide this dump ?

T
TeamOraTech
12/5/2023 9:49:00 AM

very helpful to clear the exam and understand the concept.

C
Curtis
7/12/2023 8:20:00 PM

i think it is great that you are helping people when they need it. thanks.

S
sam
7/17/2023 6:22:00 PM

cannot evaluate yet

N
nutz
7/20/2023 1:54:00 AM

a laptops wireless antenna is most likely located in the bezel of the lid

R
rajesh soni
1/17/2024 6:53:00 AM

good examplae to learn basic

T
Tanya
10/25/2023 7:07:00 AM

this is useful information

N
Nasir Mahmood
12/11/2023 7:32:00 AM

looks usefull

J
Jason
9/30/2023 1:07:00 PM

question 81 should be c.

T
TestPD1
8/10/2023 12:22:00 PM

question 18 : response isnt a ?

A
ally
8/19/2023 5:31:00 PM

plaese add questions

D
DIA
10/7/2023 5:59:00 AM

is dumps still valid ?

A
Annie
7/7/2023 8:33:00 AM

thanks for this

A
arnie
9/17/2023 6:38:00 AM

please upload questions

T
Tanuj Rana
7/22/2023 2:33:00 AM

please upload the question dump for professional machinelearning

F
Future practitioner
8/10/2023 1:26:00 PM

question 4 answer is c. this site shows the correct answer as b. "adopt a consumption model" is clearly a cost optimization design principle. looks like im done using this site to study!!!

A
Ace
8/3/2023 10:37:00 AM

number 52 answer is d

N
Nathan
12/17/2023 12:04:00 PM

just started preparing for my exam , and this site is so much help

AI Tutor 👋 I’m here to help!