During Executing a Work package, specialist products are created and quality reviews are carried out - which management product captures the details of these reviews?

  1. Team Plan
  2. Checkpoint Report
  3. Quality Register
  4. Configuration Item Record

Answer(s): C



During a work package the Team manager needs to keep the project manager informed, which management product is used for this?

  1. Highlight report
  2. Checkpoint Report
  3. Issue Report
  4. End Stage Report

Answer(s): B



HOTSPOT
Column 1 is a list of entries from the Daily Log that occurred during stage 4 in the Controlling a Stage process. For each entry in Column 1, select the first management product from Column 2 that should have been updated, or created, as a result of the entry. Each selection from Column 2 can be used once, more than once or not at all.
Drop down the right answer from column 1 to column 2.
Hot Area:
Exhibit A:


Exhibit B:

  1. Please refer to Exhibit B for answer.

Answer(s): A



While producing the Team Plan to deliver the agreed Work Package, it became apparent that the user representatives assigned 10 check some of the products were unsuitable.
Which 2 actions should the Team Manager take in response to this situation?

  1. Consult the Senior Supplier to assign suitable reviewers.
  2. Discuss the situation with Project Assurance and agree the changes or additions to the reviewers. Advise the Project Manager of this risk.
  3. Ensure the Quality Register is updated with details of the agreed amendments to the reviewers.
  4. Notify the Project Manager by raising an Exception Report explaining that the original reviewers are unsuitable.

Answer(s): A,B



The chair of a quality review meeting advised the Team Manager that, because there were so many major issues, the product had been rejected. The presenter estimated that the corrections would take about two weeks. The re-assessment of the product will take a further week, resulting in a three-week delay. The Work Package only has one week tolerance.
Which 2 actions should the Team Manager take in response to this situation?

  1. Ask the reviewers to work overtime to prevent the delay.
  2. Ensure that the situation is included in the next Highlight Report.
  3. Raise an issue explaining that tolerances are forecast to be exceeded.
  4. Advise the Project Manager of the risk that there may be a two-week delay in the delivery of one of the products.
  5. Ensure that the Quality Register is updated with the quality review result.

Answer(s): C,E



Share your comments for PRINCE2 PRINCE2 Practitioner exam with other users:

L
Lavanya
11/2/2023 1:53:00 AM

useful information

M
Moussa
12/12/2023 5:52:00 AM

intéressant

M
Madan
6/22/2023 9:22:00 AM

thank you for making the interactive questions

V
Vavz
11/2/2023 6:51:00 AM

questions are accurate

S
Su
11/23/2023 4:34:00 AM

i need questions/dumps for this exam.

L
LuvSN
7/16/2023 11:19:00 AM

i need this exam, when will it be uploaded

M
Mihai
7/19/2023 12:03:00 PM

i need the dumps !

W
Wafa
11/13/2023 3:06:00 AM

very helpful

A
Alokit
7/3/2023 2:13:00 PM

good source

S
Show-Stopper
7/27/2022 11:19:00 PM

my 3rd test and passed on first try. hats off to this brain dumps site.

M
Michelle
6/23/2023 4:06:00 AM

please upload it

L
Lele
11/20/2023 11:55:00 AM

does anybody know if are these real exam questions?

G
Girish Jain
10/9/2023 12:01:00 PM

are these questions similar to actual questions in the exam? because they seem to be too easy

P
Phil
12/8/2022 11:16:00 PM

i have a lot of experience but what comes in the exam is totally different from the practical day to day tasks. so i thought i would rather rely on these brain dumps rather failing the exam.

B
BV
6/8/2023 4:35:00 AM

good questions

K
krishna
12/19/2023 2:05:00 AM

valied exam dumps. they were very helpful and i got a pretty good score. i am very grateful for this service and exam questions

P
Pie
9/3/2023 4:56:00 AM

will it help?

L
Lucio
10/6/2023 1:45:00 PM

very useful to verify knowledge before exam

A
Ajay
5/17/2023 4:54:00 AM

good stuffs

T
TestPD1
8/10/2023 12:19:00 PM

question 17 : responses arent b and c ?

N
Nhlanhla
12/13/2023 5:26:00 AM

just passed the exam on my first try using these dumps.

R
Rizwan
1/6/2024 2:18:00 AM

very helpful

Y
Yady
5/24/2023 10:40:00 PM

these questions look good.

K
Kettie
10/12/2023 1:18:00 AM

this is very helpful content

S
SB
7/21/2023 3:18:00 AM

please provide the dumps

D
David
8/2/2023 8:20:00 AM

it is amazing

U
User
8/3/2023 3:32:00 AM

quesion 178 about "a banking system that predicts whether a loan will be repaid is an example of the" the answer is classification. not regresion, you should fix it.

Q
quen
7/26/2023 10:39:00 AM

please upload apache spark dumps

E
Erineo
11/2/2023 5:34:00 PM

q14 is b&c to reduce you will switch off mail for every single alert and you will switch on daily digest to get a mail once per day, you might even skip the empty digest mail but i see this as a part of the daily digest adjustment

P
Paul
10/21/2023 8:25:00 AM

i think it is good question

U
Unknown
8/15/2023 5:09:00 AM

good for students who wish to give certification.

C
Ch
11/20/2023 10:56:00 PM

is there a google drive link to the images? the links in questions are not working.

J
Joey
5/16/2023 5:25:00 AM

very promising, looks great, so much wow!

A
alaska
10/24/2023 5:48:00 AM

i scored 87% on the az-204 exam. thanks! i always trust

AI Tutor 👋 I’m here to help!