During Executing a Work package, specialist products are created and quality reviews are carried out - which management product captures the details of these reviews?

  1. Team Plan
  2. Checkpoint Report
  3. Quality Register
  4. Configuration Item Record

Answer(s): C



During a work package the Team manager needs to keep the project manager informed, which management product is used for this?

  1. Highlight report
  2. Checkpoint Report
  3. Issue Report
  4. End Stage Report

Answer(s): B



HOTSPOT
Column 1 is a list of entries from the Daily Log that occurred during stage 4 in the Controlling a Stage process. For each entry in Column 1, select the first management product from Column 2 that should have been updated, or created, as a result of the entry. Each selection from Column 2 can be used once, more than once or not at all.
Drop down the right answer from column 1 to column 2.
Hot Area:
Exhibit A:


Exhibit B:

  1. Please refer to Exhibit B for answer.

Answer(s): A



While producing the Team Plan to deliver the agreed Work Package, it became apparent that the user representatives assigned 10 check some of the products were unsuitable.
Which 2 actions should the Team Manager take in response to this situation?

  1. Consult the Senior Supplier to assign suitable reviewers.
  2. Discuss the situation with Project Assurance and agree the changes or additions to the reviewers. Advise the Project Manager of this risk.
  3. Ensure the Quality Register is updated with details of the agreed amendments to the reviewers.
  4. Notify the Project Manager by raising an Exception Report explaining that the original reviewers are unsuitable.

Answer(s): A,B



The chair of a quality review meeting advised the Team Manager that, because there were so many major issues, the product had been rejected. The presenter estimated that the corrections would take about two weeks. The re-assessment of the product will take a further week, resulting in a three-week delay. The Work Package only has one week tolerance.
Which 2 actions should the Team Manager take in response to this situation?

  1. Ask the reviewers to work overtime to prevent the delay.
  2. Ensure that the situation is included in the next Highlight Report.
  3. Raise an issue explaining that tolerances are forecast to be exceeded.
  4. Advise the Project Manager of the risk that there may be a two-week delay in the delivery of one of the products.
  5. Ensure that the Quality Register is updated with the quality review result.

Answer(s): C,E



Share your comments for PRINCE2 PRINCE2 Practitioner exam with other users:

H
H.T.M. D
6/25/2023 2:55:00 PM

kindly please share dumps

S
Satish
11/6/2023 4:27:00 AM

it is very useful, thank you

C
Chinna
7/30/2023 8:37:00 AM

need safe rte dumps

1
1234
6/30/2023 3:40:00 AM

can you upload the cis - cpg dumps

D
Did
1/12/2024 3:01:00 AM

q6 = 1. download odt application 2. create a configuration file (xml) 3. setup.exe /download to download the installation files 4. setup.exe /configure to deploy the application

J
John
10/12/2023 12:30:00 PM

great material

D
Dinesh
8/1/2023 2:26:00 PM

could you please upload sap c_arsor_2302 questions? it will be very much helpful.

L
LBert
6/19/2023 10:23:00 AM

vraag 20c: rsa veilig voor symmtrische cryptografie? antwoord c is toch fout. rsa is voor asymmetrische cryptogafie??

G
g
12/22/2023 1:51:00 PM

so far good

M
Milos
8/4/2023 9:33:00 AM

question 31 has obviously wrong answers. tls and ssl are used to encrypt data at transit, not at rest.

D
Diksha
9/25/2023 2:32:00 AM

pls provide dump for 1z0-1080-23 planning exams

H
H
7/17/2023 4:28:00 AM

could you please upload the exam?

A
Anonymous
9/14/2023 4:47:00 AM

please upload this

N
Naveena
1/13/2024 9:55:00 AM

good material

W
WildWilly
1/19/2024 10:43:00 AM

lets see if this is good stuff...

L
Lavanya
11/2/2023 1:53:00 AM

useful information

M
Moussa
12/12/2023 5:52:00 AM

intéressant

M
Madan
6/22/2023 9:22:00 AM

thank you for making the interactive questions

V
Vavz
11/2/2023 6:51:00 AM

questions are accurate

S
Su
11/23/2023 4:34:00 AM

i need questions/dumps for this exam.

L
LuvSN
7/16/2023 11:19:00 AM

i need this exam, when will it be uploaded

M
Mihai
7/19/2023 12:03:00 PM

i need the dumps !

W
Wafa
11/13/2023 3:06:00 AM

very helpful

A
Alokit
7/3/2023 2:13:00 PM

good source

S
Show-Stopper
7/27/2022 11:19:00 PM

my 3rd test and passed on first try. hats off to this brain dumps site.

M
Michelle
6/23/2023 4:06:00 AM

please upload it

L
Lele
11/20/2023 11:55:00 AM

does anybody know if are these real exam questions?

G
Girish Jain
10/9/2023 12:01:00 PM

are these questions similar to actual questions in the exam? because they seem to be too easy

P
Phil
12/8/2022 11:16:00 PM

i have a lot of experience but what comes in the exam is totally different from the practical day to day tasks. so i thought i would rather rely on these brain dumps rather failing the exam.

B
BV
6/8/2023 4:35:00 AM

good questions

K
krishna
12/19/2023 2:05:00 AM

valied exam dumps. they were very helpful and i got a pretty good score. i am very grateful for this service and exam questions

P
Pie
9/3/2023 4:56:00 AM

will it help?

L
Lucio
10/6/2023 1:45:00 PM

very useful to verify knowledge before exam

A
Ajay
5/17/2023 4:54:00 AM

good stuffs

AI Tutor 👋 I’m here to help!