During Executing a Work package, specialist products are created and quality reviews are carried out - which management product captures the details of these reviews?

  1. Team Plan
  2. Checkpoint Report
  3. Quality Register
  4. Configuration Item Record

Answer(s): C



During a work package the Team manager needs to keep the project manager informed, which management product is used for this?

  1. Highlight report
  2. Checkpoint Report
  3. Issue Report
  4. End Stage Report

Answer(s): B



HOTSPOT
Column 1 is a list of entries from the Daily Log that occurred during stage 4 in the Controlling a Stage process. For each entry in Column 1, select the first management product from Column 2 that should have been updated, or created, as a result of the entry. Each selection from Column 2 can be used once, more than once or not at all.
Drop down the right answer from column 1 to column 2.
Hot Area:
Exhibit A:


Exhibit B:

  1. Please refer to Exhibit B for answer.

Answer(s): A



While producing the Team Plan to deliver the agreed Work Package, it became apparent that the user representatives assigned 10 check some of the products were unsuitable.
Which 2 actions should the Team Manager take in response to this situation?

  1. Consult the Senior Supplier to assign suitable reviewers.
  2. Discuss the situation with Project Assurance and agree the changes or additions to the reviewers. Advise the Project Manager of this risk.
  3. Ensure the Quality Register is updated with details of the agreed amendments to the reviewers.
  4. Notify the Project Manager by raising an Exception Report explaining that the original reviewers are unsuitable.

Answer(s): A,B



The chair of a quality review meeting advised the Team Manager that, because there were so many major issues, the product had been rejected. The presenter estimated that the corrections would take about two weeks. The re-assessment of the product will take a further week, resulting in a three-week delay. The Work Package only has one week tolerance.
Which 2 actions should the Team Manager take in response to this situation?

  1. Ask the reviewers to work overtime to prevent the delay.
  2. Ensure that the situation is included in the next Highlight Report.
  3. Raise an issue explaining that tolerances are forecast to be exceeded.
  4. Advise the Project Manager of the risk that there may be a two-week delay in the delivery of one of the products.
  5. Ensure that the Quality Register is updated with the quality review result.

Answer(s): C,E



Share your comments for PRINCE2 PRINCE2 Practitioner exam with other users:

M
Manju
10/19/2023 1:19:00 PM

is it really helpful to pass the exam

L
LeAnne Hair
8/24/2023 12:47:00 PM

#229 in incorrect - all the customers require an annual review

A
Abdul SK
9/28/2023 11:42:00 PM

kindy upload

A
Aderonke
10/23/2023 12:53:00 PM

fantastic assessment on psm 1

S
SAJI
7/20/2023 2:51:00 AM

56 question correct answer a,b

R
Raj Kumar
10/23/2023 8:52:00 PM

thank you for providing the q bank

P
piyush keshari
7/7/2023 9:46:00 PM

true quesstions

B
B.A.J
11/6/2023 7:01:00 AM

i can´t believe ms asks things like this, seems to be only marketing material.

G
Guss
5/23/2023 12:28:00 PM

hi, could you please add the last update of ns0-527

R
Rond65
8/22/2023 4:39:00 PM

question #3 refers to vnet4 and vnet5. however, there is no vnet5 listed in the case study (testlet 2).

C
Cheers
12/13/2023 9:55:00 AM

sometimes it may be good some times it may be

S
Sumita Bose
7/21/2023 1:01:00 AM

qs 4 answer seems wrong- please check

A
Amit
9/7/2023 12:53:00 AM

very detailed explanation !

F
FisherGirl
5/16/2022 10:36:00 PM

the interactive nature of the test engine application makes the preparation process less boring.

C
Chiranthaka
9/20/2023 11:15:00 AM

very useful.

S
SK
7/15/2023 3:51:00 AM

complete question dump should be made available for practice.

G
Gamerrr420
5/25/2022 9:38:00 PM

i just passed my first exam. i got 2 exam dumps as part of the 50% sale. my second exam is under work. once i write that exam i report my result. but so far i am confident.

K
Kudu hgeur
9/21/2023 5:58:00 PM

nice create dewey stefen

A
Anorag
9/6/2023 9:24:00 AM

i just wrote this exam and it is still valid. the questions are exactly the same but there are about 4 or 5 questions that are answered incorrectly. so watch out for those. best of luck with your exam.

N
Nathan
1/10/2023 3:54:00 PM

passed my exam today. this is a good start to 2023.

1
1
10/28/2023 7:32:00 AM

great sharing

A
Anand
1/20/2024 10:36:00 AM

very helpful

K
Kumar
6/23/2023 1:07:00 PM

thanks.. very helpful

U
User random
11/15/2023 3:01:00 AM

i registered for 1z0-1047-23 but dumps qre available for 1z0-1047-22. help me with this...

K
kk
1/17/2024 3:00:00 PM

very helpful

R
Raj
7/24/2023 10:20:00 AM

please upload oracle 1z0-1110-22 exam pdf

B
Blessious Phiri
8/13/2023 11:58:00 AM

becoming interesting on the logical part of the cdbs and pdbs

L
LOL what a joke
9/10/2023 9:09:00 AM

some of the answers are incorrect, i would be wary of using this until an admin goes back and reviews all the answers

M
Muhammad Rawish Siddiqui
12/9/2023 7:40:00 AM

question # 267: federated operating model is also correct.

M
Mayar
9/22/2023 4:58:00 AM

its helpful alot.

S
Sandeep
7/25/2022 11:58:00 PM

the questiosn from this braindumps are same as in the real exam. my passing mark was 84%.

E
Eman Sawalha
6/10/2023 6:09:00 AM

it is an exam that measures your understanding of cloud computing resources provided by aws. these resources are aligned under 6 categories: storage, compute, database, infrastructure, pricing and network. with all of the services and typees of services under each category

M
Mars
11/16/2023 1:53:00 AM

good and very useful

R
ronaldo7
10/24/2023 5:34:00 AM

i cleared the az-104 exam by scoring 930/1000 on the exam. it was all possible due to this platform as it provides premium quality service. thank you!

AI Tutor 👋 I’m here to help!