During Executing a Work package, specialist products are created and quality reviews are carried out - which management product captures the details of these reviews?

  1. Team Plan
  2. Checkpoint Report
  3. Quality Register
  4. Configuration Item Record

Answer(s): C



During a work package the Team manager needs to keep the project manager informed, which management product is used for this?

  1. Highlight report
  2. Checkpoint Report
  3. Issue Report
  4. End Stage Report

Answer(s): B



HOTSPOT
Column 1 is a list of entries from the Daily Log that occurred during stage 4 in the Controlling a Stage process. For each entry in Column 1, select the first management product from Column 2 that should have been updated, or created, as a result of the entry. Each selection from Column 2 can be used once, more than once or not at all.
Drop down the right answer from column 1 to column 2.
Hot Area:
Exhibit A:


Exhibit B:

  1. Please refer to Exhibit B for answer.

Answer(s): A



While producing the Team Plan to deliver the agreed Work Package, it became apparent that the user representatives assigned 10 check some of the products were unsuitable.
Which 2 actions should the Team Manager take in response to this situation?

  1. Consult the Senior Supplier to assign suitable reviewers.
  2. Discuss the situation with Project Assurance and agree the changes or additions to the reviewers. Advise the Project Manager of this risk.
  3. Ensure the Quality Register is updated with details of the agreed amendments to the reviewers.
  4. Notify the Project Manager by raising an Exception Report explaining that the original reviewers are unsuitable.

Answer(s): A,B



The chair of a quality review meeting advised the Team Manager that, because there were so many major issues, the product had been rejected. The presenter estimated that the corrections would take about two weeks. The re-assessment of the product will take a further week, resulting in a three-week delay. The Work Package only has one week tolerance.
Which 2 actions should the Team Manager take in response to this situation?

  1. Ask the reviewers to work overtime to prevent the delay.
  2. Ensure that the situation is included in the next Highlight Report.
  3. Raise an issue explaining that tolerances are forecast to be exceeded.
  4. Advise the Project Manager of the risk that there may be a two-week delay in the delivery of one of the products.
  5. Ensure that the Quality Register is updated with the quality review result.

Answer(s): C,E



Share your comments for PRINCE2 PRINCE2 Practitioner exam with other users:

B
Blessious Phiri
8/13/2023 3:10:00 PM

control file is the heart of rman backup

S
Senthil
9/19/2023 5:47:00 AM

hi could you please upload the ibm c2090-543 dumps

H
Harry
6/27/2023 7:20:00 AM

appriciate if you could upload this again

A
Anonymous
7/10/2023 4:10:00 AM

please upload the dump

R
Raja
6/20/2023 5:30:00 AM

i found some questions answers mismatch with explanation answers. please properly update

D
Doora
11/30/2023 4:20:00 AM

nothing to mention

D
deally
1/19/2024 3:41:00 PM

knowable questions

S
Sonia
7/23/2023 4:03:00 PM

very helpfull

B
binEY
10/6/2023 5:15:00 AM

good questions

N
Neha
9/28/2023 1:58:00 PM

its helpful

D
Desmond
1/5/2023 9:11:00 PM

i just took my oracle exam and let me tell you, this exam dumps was a lifesaver! without them, iam not sure i would have passed. the questions were tricky and the answers were obscure, but the exam dumps had everything i needed. i would recommend to anyone looking to pass their oracle exams with flying colors (and a little bit of cheating) lol.

D
Davidson OZ
9/9/2023 6:37:00 PM

22. if you need to make sure that one computer in your hot-spot network can access the internet without hot-spot authentication, which menu allows you to do this? answer is ip binding and not wall garden. wall garden allows specified websites to be accessed with users authentication to the hotspot

3
381
9/2/2023 4:31:00 PM

is question 1 correct?

L
Laurent
10/6/2023 5:09:00 PM

good content

S
Sniper69
5/9/2022 11:04:00 PM

manged to pass the exam with this exam dumps.

D
Deepak
12/27/2023 2:37:00 AM

good questions

D
dba
9/23/2023 3:10:00 AM

can we please have the latest exam questions?

P
Prasad
9/29/2023 7:27:00 AM

please help with jn0-649 latest dumps

G
GTI9982
7/31/2023 10:15:00 PM

please i need this dump. thanks

E
Elton Riva
12/12/2023 8:20:00 PM

i have to take the aws certified developer - associate dva-c02 in the next few weeks and i wanted to know if the questions on your website are the same as the official exam.

B
Berihun Desalegn Wonde
7/13/2023 11:00:00 AM

all questions are more important

G
gr
7/2/2023 7:03:00 AM

ques 4 answer should be c ie automatically recover from failure

R
RS
7/27/2023 7:17:00 AM

very very useful page

B
Blessious Phiri
8/12/2023 11:47:00 AM

the exams are giving me an eye opener

A
AD
10/22/2023 9:08:00 AM

3rd so far, need to cover more

M
Matt
11/18/2023 2:32:00 AM

aligns with the pecd notes

S
Sri
10/15/2023 4:38:00 PM

question 4: b securityadmin is the correct answer. https://docs.snowflake.com/en/user-guide/security-access-control-overview#access-control-framework

H
H.T.M. D
6/25/2023 2:55:00 PM

kindly please share dumps

S
Satish
11/6/2023 4:27:00 AM

it is very useful, thank you

C
Chinna
7/30/2023 8:37:00 AM

need safe rte dumps

1
1234
6/30/2023 3:40:00 AM

can you upload the cis - cpg dumps

D
Did
1/12/2024 3:01:00 AM

q6 = 1. download odt application 2. create a configuration file (xml) 3. setup.exe /download to download the installation files 4. setup.exe /configure to deploy the application

J
John
10/12/2023 12:30:00 PM

great material

D
Dinesh
8/1/2023 2:26:00 PM

could you please upload sap c_arsor_2302 questions? it will be very much helpful.

AI Tutor 👋 I’m here to help!