During Executing a Work package, specialist products are created and quality reviews are carried out - which management product captures the details of these reviews?

  1. Team Plan
  2. Checkpoint Report
  3. Quality Register
  4. Configuration Item Record

Answer(s): C



During a work package the Team manager needs to keep the project manager informed, which management product is used for this?

  1. Highlight report
  2. Checkpoint Report
  3. Issue Report
  4. End Stage Report

Answer(s): B



HOTSPOT
Column 1 is a list of entries from the Daily Log that occurred during stage 4 in the Controlling a Stage process. For each entry in Column 1, select the first management product from Column 2 that should have been updated, or created, as a result of the entry. Each selection from Column 2 can be used once, more than once or not at all.
Drop down the right answer from column 1 to column 2.
Hot Area:
Exhibit A:


Exhibit B:

  1. Please refer to Exhibit B for answer.

Answer(s): A



While producing the Team Plan to deliver the agreed Work Package, it became apparent that the user representatives assigned 10 check some of the products were unsuitable.
Which 2 actions should the Team Manager take in response to this situation?

  1. Consult the Senior Supplier to assign suitable reviewers.
  2. Discuss the situation with Project Assurance and agree the changes or additions to the reviewers. Advise the Project Manager of this risk.
  3. Ensure the Quality Register is updated with details of the agreed amendments to the reviewers.
  4. Notify the Project Manager by raising an Exception Report explaining that the original reviewers are unsuitable.

Answer(s): A,B



The chair of a quality review meeting advised the Team Manager that, because there were so many major issues, the product had been rejected. The presenter estimated that the corrections would take about two weeks. The re-assessment of the product will take a further week, resulting in a three-week delay. The Work Package only has one week tolerance.
Which 2 actions should the Team Manager take in response to this situation?

  1. Ask the reviewers to work overtime to prevent the delay.
  2. Ensure that the situation is included in the next Highlight Report.
  3. Raise an issue explaining that tolerances are forecast to be exceeded.
  4. Advise the Project Manager of the risk that there may be a two-week delay in the delivery of one of the products.
  5. Ensure that the Quality Register is updated with the quality review result.

Answer(s): C,E



Viewing Page 11 of 58



Share your comments for PRINCE2 PRINCE2 Practitioner exam with other users:

SkepticReader 8/1/2023 8:51:00 AM

question 35 has an answer for a different question. i believe the answer is "a" because it shut off the firewall. "0" in registry data means that its false (aka off).
UNITED STATES


Nabin 10/16/2023 4:58:00 AM

helpful content
MALAYSIA


Blessious Phiri 8/15/2023 3:19:00 PM

oracle 19c is complex db
Anonymous


Sreenivas 10/24/2023 12:59:00 AM

helpful for practice
Anonymous


Liz 9/11/2022 11:27:00 PM

support team is fast and deeply knowledgeable. i appreciate that a lot.
UNITED STATES


Namrata 7/15/2023 2:22:00 AM

helpful questions
Anonymous


lipsa 11/8/2023 12:54:00 PM

thanks for question
Anonymous


Eli 6/18/2023 11:27:00 PM

the software is provided for free so this is a big change. all other sites are charging for that. also that fucking examtopic site that says free is not free at all. you are hit with a pay-wall.
EUROPEAN UNION


open2exam 10/29/2023 1:14:00 PM

i need exam questions nca 6.5 any help please ?
Anonymous


Gerald 9/11/2023 12:22:00 PM

just took the comptia cybersecurity analyst (cysa+) - wished id seeing this before my exam
UNITED STATES


ryo 9/10/2023 2:27:00 PM

very helpful
MEXICO


Jamshed 6/20/2023 4:32:00 AM

i need this exam
PAKISTAN


Roberto Capra 6/14/2023 12:04:00 PM

nice questions... are these questions the same of the exam?
Anonymous


Synt 5/23/2023 9:33:00 PM

need to view
UNITED STATES


Vey 5/27/2023 12:06:00 AM

highly appreciate for your sharing.
CAMBODIA


Tshepang 8/18/2023 4:41:00 AM

kindly share this dump. thank you
Anonymous


Jay 9/26/2023 8:00:00 AM

link plz for download
UNITED STATES


Leo 10/30/2023 1:11:00 PM

data quality oecd
Anonymous


Blessious Phiri 8/13/2023 9:35:00 AM

rman is one good recovery technology
Anonymous


DiligentSam 9/30/2023 10:26:00 AM

need it thx
Anonymous


Vani 8/10/2023 8:11:00 PM

good questions
NEW ZEALAND


Fares 9/11/2023 5:00:00 AM

good one nice revision
Anonymous


Lingaraj 10/26/2023 1:27:00 AM

i love this thank you i need
Anonymous


Muhammad Rawish Siddiqui 12/5/2023 12:38:00 PM

question # 142: data governance is not one of the deliverables in the document and content management context diagram.
SAUDI ARABIA


al 6/7/2023 10:25:00 AM

most answers not correct here
Anonymous


Bano 1/19/2024 2:29:00 AM

what % of questions do we get in the real exam?
UNITED STATES


Oliviajames 10/25/2023 5:31:00 AM

i just want to tell you. i took my microsoft az-104 exam and passed it. your program was awesome. i especially liked your detailed questions and answers and practice tests that made me well-prepared for the exam. thanks to this website!!!
UNITED STATES


Divya 8/27/2023 12:31:00 PM

all the best
UNITED STATES


KY 1/1/2024 11:01:00 PM

very usefull document
Anonymous


Arun 9/20/2023 4:52:00 PM

nice and helpful questions
INDIA


Joseph J 7/11/2023 2:53:00 PM

i found the questions helpful
UNITED STATES


Meg 10/12/2023 8:02:00 AM

q 105 . ans is d
INDIA


Navaneeth S 7/14/2023 7:57:00 AM

i have interest to get a sybase iq dba certification
UNITED STATES


Aish 10/11/2023 5:27:00 AM

want to pass exm.
INDIA