In which product are acceptance criteria documented?

  1. Project Product Description
  2. Product Description
  3. Quality Register
  4. Quality Management Strategy

Answer(s): A



According to PRINCE2, which of the following is a statement about the quality which the customer requires from the project product?

  1. Customer's quality expectations
  2. Quality criteria
  3. Acceptance criteria
  4. Quality Management Strategy

Answer(s): A



Which product contains the customer's quality expectations?

  1. Quality Register
  2. Quality Management Strategy
  3. Project Product Description
  4. Business Case

Answer(s): C



Which of the following documents the quality techniques, standards and procedures to be applied during the project?

  1. Quality Register
  2. Quality Management Strategy
  3. Project Product Description
  4. Quality assurance

Answer(s): B



Identify the missing word in the following sentence... The purpose of the [ ? ] theme is to define and implement the means by which the project will create and verify products that are fit for purpose.

  1. Plans
  2. Change
  3. Organization
  4. Quality

Answer(s): D



What is the purpose of a change budget?

  1. To correct any errors found in products produced by suppliers
  2. To pay for any increase in scope
  3. To implement risk actions, such as fallback plans
  4. To supplement any cost tolerance being exceeded

Answer(s): B



Which of the following is FALSE regarding the Change theme?

  1. Change control should be used to prevent changes being made to baselined products
  2. Issues can affect the project's performance targets of time, cost, quality, scope, benefits and risk
  3. A pre-requisite of effective issue and change control would be an appropriate configuration management system
  4. Without issue and change control being applied, a project will become unresponsive to its stakeholders

Answer(s): A



Who are allowed to raise an issue?

  1. Only the Project Manager and Team Manager
  2. Anyone with an interest in the project or its outcome
  3. Only the Change Authority
  4. Only members of the project management team

Answer(s): B