Which project management team member represents the interest of those who will operate the project's products to realize the benefits after the project is complete?

  1. Executive
  2. Senior User
  3. Senior Supplier
  4. Project Manager

Answer(s): B

Explanation:

The Senior User within the PRINCE2 project management team represents the interests of those who will use the project's products and benefit from their operation after the project is complete. This role is responsible for specifying the needs of users, ensuring the solution meets these needs, and is capable of delivering the anticipated benefits.


Reference:

PRINCE2 Foundation manual, PRINCE2 official resources



What product is used to maintain a record of those who have an interest in the project and their information requirements?

  1. Project Plan
  2. Communication Management Strategy
  3. Project Brief
  4. Project Product Description

Answer(s): B

Explanation:

The Communication Management Strategy is used in PRINCE2 to maintain a record of stakeholders who have an interest in the project and their information requirements. This document outlines how and when stakeholders will be kept informed about the project's progress and any issues that may arise.


Reference:

PRINCE2 Foundation manual, PRINCE2 official resources



Identify the missing word in the following sentence. A member of the Project Board is responsible for [ ? ] assurance.

  1. quality
  2. supplier
  3. risk
  4. product

Answer(s): A

Explanation:

A member of the Project Board is responsible for quality assurance in PRINCE2. Quality assurance is concerned with ensuring that the project's products meet the quality requirements set out in the project and that the project adheres to the appropriate corporate, programme management, or customer quality standards.


Reference:

PRINCE2 Foundation manual, PRINCE2 official resources



How many roles make up the Project Board?

  1. One
  2. Two
  3. Three
  4. Four

Answer(s): C

Explanation:

The Project Board within the PRINCE2® framework is made up of three key roles: the Executive, the Senior User, and the Senior Supplier. These roles represent the business, user, and supplier interests respectively, ensuring that the project's decision-making is balanced across these three perspectives.


Reference:

PRINCE2® Foundation official documentation and study materials.



Which of the following statements about stakeholders are true?

1. Someone who thinks they will be affected by a project is a stakeholder on that project.
2. Stakeholders may be internal or external to the corporate organization.

  1. Only 1 is true
  2. Only 2 is true
  3. Both 1 and 2 are true
  4. Neither 1 or 2 are true

Answer(s): C

Explanation:

Both statements about stakeholders are true in the context of PRINCE2®. A stakeholder in a project includes anyone who thinks they will be affected by the project, which can include both supporters and those who may oppose the project. Additionally, stakeholders can be both internal and external to the organization that is undertaking the project.


Reference:

PRINCE2® Foundation official documentation and study materials.



Share your comments for PRINCE2 PRINCE2 Foundation 7 Edition exam with other users:

T
trying
7/28/2023 12:37:00 PM

thanks good stuff

E
exampei
10/4/2023 2:40:00 PM

need dump c_tadm_23

E
Eman Sawalha
6/10/2023 6:18:00 AM

next time i will write a full review

J
johnpaul
11/15/2023 7:55:00 AM

first time using this site

O
omiornil@gmail.com
7/25/2023 9:36:00 AM

please sent me oracle 1z0-1105-22 pdf

J
John
8/29/2023 8:59:00 PM

very helpful

K
Kvana
9/28/2023 12:08:00 PM

good info about oml

C
Checo Lee
7/3/2023 5:45:00 PM

very useful to practice

D
dixitdnoh@gmail.com
8/27/2023 2:58:00 PM

this website is very helpful.

S
Sanjay
8/14/2023 8:07:00 AM

good content

B
Blessious Phiri
8/12/2023 2:19:00 PM

so challenging

P
PAYAL
10/17/2023 7:14:00 AM

17 should be d ,for morequery its scale out

K
Karthik
10/12/2023 10:51:00 AM

nice question

G
Godmode
5/7/2023 10:52:00 AM

yes.

B
Bhuddhiman
7/30/2023 1:18:00 AM

good mateial

K
KJ
11/17/2023 3:50:00 PM

good practice exam

S
sowm
10/29/2023 2:44:00 PM

impressivre qustion

C
CW
7/6/2023 7:06:00 PM

questions seem helpful

L
luke
9/26/2023 10:52:00 AM

good content

Z
zazza
6/16/2023 9:08:00 AM

question 21 answer is alerts

A
Abwoch Peter
7/4/2023 3:08:00 AM

am preparing for exam

M
mohamed
9/12/2023 5:26:00 AM

good one thanks

M
Mfc
10/23/2023 3:35:00 PM

only got thru 5 questions, need more to evaluate

W
Whizzle
7/24/2023 6:19:00 AM

q26 should be b

S
sarra
1/17/2024 3:44:00 AM

the aaa triad in information security is authentication, accounting and authorisation so the answer should be d 1, 3 and 5.

D
DBS
5/14/2023 12:56:00 PM

need to attend this

D
Da_costa
8/1/2023 5:28:00 PM

these are free brain dumps i understand, how can one get free pdf

V
vikas
10/28/2023 6:57:00 AM

provide access

A
Abdullah
9/29/2023 2:06:00 AM

good morning

R
Raj
6/26/2023 3:12:00 PM

please upload the ncp-mci 6.5 dumps, really need to practice this one. thanks guys

M
Miguel
10/5/2023 12:21:00 PM

question 16: https://help.salesforce.com/s/articleview?id=sf.care_console_overview.htm&type=5

H
Hiren Ladva
7/8/2023 10:34:00 PM

yes i m prepared exam

O
oliverjames
10/24/2023 5:37:00 AM

my experience was great with this site as i studied for the ms-900 from here and got 900/1000 on the test. my main focus was on the tutorials which were provided and practice questions. thanks!

B
Bhuddhiman
7/20/2023 11:52:00 AM

great course

AI Tutor 👋 I’m here to help!