When should the Project Board refer to corporate or programme management for a decision?

  1. The stage requires resources
  2. It is forecast that project level tolerance will be exceeded
  3. The Senior Supplier or Senior User needs to be changed
  4. Any request for change needs to be approved

Answer(s): B

Explanation:

The Project Board should refer to corporate or programme management for decisions when it is forecast that the project level tolerance will be exceeded. This scenario typically triggers an exception process as the predefined tolerances are fundamental limits within which the Project Board allows the Project Manager to manage the project.


Reference:

PRINCE2® Foundation official study guide and materials.



Identify the missing words in the following sentence. At the end of a stage, the [ ? ] should be used to check whether there is a requirement to send copies of the End Stage Report to external interested parties.

  1. Stage Plan
  2. Communication Management Strategy
  3. Follow-on action recommendations
  4. Quality Management Strategy

Answer(s): B

Explanation:

The Communication Management Strategy should be referred to at the end of a stage to check whether there is a requirement to send copies of the End Stage Report to external interested parties. This document outlines how, when, and by whom information will be disseminated throughout the project, including communication with external stakeholders.


Reference:

PRINCE2® Foundation official study guide and materials.



Which is NOT a purpose of the Organization theme?

  1. Define a project management team structure
  2. Define the level of tolerance for each level of the project management team
  3. Define the Project Board's responsibility for directing the project
  4. Define which role is accountable for the project's success

Answer(s): B

Explanation:

The Organization theme does not include defining the level of tolerance for each level of the project management team. Tolerance levels are typically set within the Plans theme, which deals with how the project is structured in terms of stages and the delegation of authority within those tolerances. The Organization theme primarily focuses on defining roles and responsibilities.


Reference:

PRINCE2® Foundation official study guide and materials.



Which is NOT represented by one of the three primary categories of stakeholder identified in PRINCE2?

  1. Those with a financial interest in the project
  2. Those who will manage the project on a day-to-day basis
  3. Those who will specify the desired outputs of the project
  4. Those who will create the project's outputs

Answer(s): A

Explanation:

PRINCE2® identifies three primary categories of stakeholders: 1) those who will specify the desired outputs (customers/users), 2) those who will manage the project on a day-to-day basis (suppliers), and 3) those who use the project's outputs. Those with a financial interest in the project are not explicitly categorized as one of the primary stakeholder types in PRINCE2®.


Reference:

PRINCE2® Foundation official study guide and materials.



Which does the Executive need to ensure is in place before the project is initiated?

  1. All Work Packages are authorized
  2. An understanding of how the project will contribute to corporate objectives
  3. The Project Plan has been approved
  4. The Project Initiation Documentation is complete

Answer(s): B

Explanation:

Before initiating a project, the Executive in PRINCE2 needs to ensure there is a clear understanding of how the project will contribute to the corporate objectives. This alignment is crucial for justifying the project's existence and ensuring it has a clear business purpose and expected benefits that support the organization's strategic goals.


Reference:

PRINCE2 Foundation manual, PRINCE2 official resources



Share your comments for PRINCE2 PRINCE2 Foundation 7 Edition exam with other users:

M
Massam
6/11/2022 5:55:00 PM

90% of questions was there but i failed the exam, i marked the answers as per the guide but looks like they are not accurate , if not i would have passed the exam given that i saw about 45 of 50 questions from dump

A
Anonymous
12/27/2023 12:47:00 AM

answer to this question "what administrative safeguards should be implemented to protect the collected data while in use by manasa and her product management team? " it should be (c) for the following reasons: this administrative safeguard involves controlling access to collected data by ensuring that only individuals who need the data for their job responsibilities have access to it. this helps minimize the risk of unauthorized access and potential misuse of sensitive information. while other options such as (a) documenting data flows and (b) conducting a privacy impact assessment (pia) are important steps in data protection, implementing a "need to know" access policy directly addresses the issue of protecting data while in use by limiting access to those who require it for legitimate purposes. (d) is not directly related to safeguarding data during use; it focuses on data transfers and location.

J
Japles
5/23/2023 9:46:00 PM

password lockout being the correct answer for question 37 does not make sense. it should be geofencing.

F
Faritha
8/10/2023 6:00:00 PM

for question 4, the righr answer is :recover automatically from failures

A
Anonymous
9/14/2023 4:27:00 AM

question number 4s answer is 3, option c. i

P
p das
12/7/2023 11:41:00 PM

very good questions

A
Anna
1/5/2024 1:12:00 AM

i am confused about the answers to the questions. are the answers correct?

B
Bhavya
9/13/2023 10:15:00 AM

very usefull

R
Rahul Kumar
8/31/2023 12:30:00 PM

need certification.

D
Diran Ole
9/17/2023 5:15:00 PM

great exam prep

V
Venkata Subbarao Bandaru
6/24/2023 8:45:00 AM

i require dump

D
D
7/15/2023 1:38:00 AM

good morning, could you please upload this exam again,

A
Ann
9/15/2023 5:39:00 PM

hi can you please upload the dumps for sap contingent module. thanks

S
Sridhar
1/16/2024 9:19:00 PM

good questions

S
Summer
10/4/2023 9:57:00 PM

looking forward to the real exam

V
vv
12/2/2023 2:45:00 PM

good ones for exam preparation

D
Danny Zas
9/15/2023 4:45:00 AM

this is a good experience

S
SM 1211
10/12/2023 10:06:00 PM

hi everyone

A
A
10/2/2023 6:08:00 PM

waiting for the dump. please upload.

A
Anonymous
7/16/2023 11:05:00 AM

upload cks exam questions

J
Johan
12/13/2023 8:16:00 AM

awesome training material

P
PC
7/28/2023 3:49:00 PM

where is dump

Y
YoloStar Yoloing
10/22/2023 9:58:00 PM

q. 289 - the correct answer should be b not d, since the question asks for the most secure way to provide access to a s3 bucket (a single one), and by principle of the least privilege you should not be giving access to all buckets.

Z
Zelalem Nega
5/14/2023 12:45:00 PM

please i need if possible h12-831,

U
unknown-R
11/23/2023 7:36:00 AM

good collection of questions and solution for pl500 certification

S
Swaminathan
5/11/2023 9:59:00 AM

i would like to appear the exam.

V
Veenu
10/24/2023 6:26:00 AM

i am very happy as i cleared my comptia a+ 220-1101 exam. i studied from as it has all exam dumps and mock tests available. i got 91% on the test.

K
Karan
5/17/2023 4:26:00 AM

need this dump

R
Ramesh Kutumbaka
12/30/2023 11:17:00 PM

its really good to eventuate knowledge before appearing for the actual exam.

A
anonymous
7/20/2023 10:31:00 PM

this is great

X
Xenofon
6/26/2023 9:35:00 AM

please i want the questions to pass the exam

D
Diego
1/21/2024 8:21:00 PM

i need to pass exam

V
Vichhai
12/25/2023 3:25:00 AM

great, i appreciate it.

P
P Simon
8/25/2023 2:39:00 AM

please could you upload (isc)2 certified in cybersecurity (cc) exam questions

AI Tutor 👋 I’m here to help!