Which does NOT reflect the PRINCE2 principle of continued business justification?
Answer(s): C
The principle of continued business justification in PRINCE2 means that a project must remain justified throughout its life cycle. The key factor is the project's ongoing justification, not solely its ability to deliver financial benefits. Projects may continue for reasons other than financial gain, such as strategic importance, compliance, or public safety. Therefore, stopping a project based only on financial criteria does not reflect this principle accurately.
PRINCE2 Foundation manual, PRINCE2 official resources
Which characteristic distinguishes a project from regular business operations?
Answer(s): B
A characteristic that distinguishes a project from regular business operations is that it introduces business change. Projects are temporary endeavors undertaken to create a unique product, service, or result, and they often drive significant changes within an organization, unlike regular operations, which are repetitive and ongoing.
Which characteristic of a project reflects that there are different perspectives and motivations for customers and suppliers?
The characteristic of a project that reflects different perspectives and motivations for customers and suppliers is its "Unique" nature. Projects typically bring together diverse groups, each with distinct objectives and expectations. The uniqueness of a project involves these varied stakeholder inputs and requirements, which often need to be balanced and managed.
Which PRINCE2 principle is supported by the setting of tolerances for the three levels of plan?
The PRINCE2 principle supported by the setting of tolerances for the three levels of plan (Project, Stage, and Team Plans) is "Manage by exception." This principle allows management to set predefined tolerances for project objectives, and only escalate issues to higher management if these tolerances are exceeded, thereby facilitating efficient use of management time and focus.
Which role is responsible for creating Checkpoint Reports?
In PRINCE2®, the Team Manager is responsible for creating Checkpoint Reports. These reports provide the Project Manager with a summary of the progress within a Work Package, detailing performance against plan, and highlighting any issues that might affect the work.
PRINCE2® Foundation official study materials.
Share your comments for PRINCE2 PRINCE2-7-Foundation exam with other users:
so far so good
i am really liking it
thanks good stuff
need dump c_tadm_23
next time i will write a full review
first time using this site
please sent me oracle 1z0-1105-22 pdf
very helpful
good info about oml
very useful to practice
this website is very helpful.
good content
so challenging
17 should be d ,for morequery its scale out
nice question
yes.
good mateial
good practice exam
impressivre qustion
questions seem helpful
question 21 answer is alerts
am preparing for exam
good one thanks
only got thru 5 questions, need more to evaluate
q26 should be b
the aaa triad in information security is authentication, accounting and authorisation so the answer should be d 1, 3 and 5.
need to attend this
these are free brain dumps i understand, how can one get free pdf
provide access
good morning
please upload the ncp-mci 6.5 dumps, really need to practice this one. thanks guys
question 16: https://help.salesforce.com/s/articleview?id=sf.care_console_overview.htm&type=5
yes i m prepared exam