You are the project manager for a construction project. The project involves casting of a column in a very narrow space. Because of lack of space, casting it is highly dangerous. High technical skill will be required for casting that column. You decide to hire a local expert team for casting that column. Which of the following types of risk response are you following?

  1. Acceptance
  2. Avoidance
  3. Mitigation
  4. Transference

Answer(s): D



There are seven risks responses that a project manager can choose from. Which risk response is appropriate for both positive and negative risk events?

  1. Acceptance
  2. Sharing
  3. Transference
  4. Mitigation

Answer(s): A



You are the project manager of the NGQQ Project for your company. To help you communicate project status to your stakeholders, you are going to create a stakeholder register. All of the following information should be included in the stakeholder register except for which one?

  1. Assessment information of the stakeholders' major requirements, expectations, and potential influence
  2. Stakeholder classification of their role in the project
  3. Identification information for each stakeholder
  4. Stakeholder management strategy

Answer(s): D



You are the project manager of the GGK project for your company. The GGK project has a budget of
$1,265,100 and is currently 40 percent complete. In this project, you elected to add labor to the project to increase the likelihood of completing the project early as the project was only scheduled to be 35 percent complete at this time. This positive risk response, while keeping the project ahead of schedule, has added significant costs to the project. You have already spent $575,000 to reach this point in the project.
Management would like to know what your cost performance index and the schedule performance index is for this project. What are these values?

  1. The CPI is -$68,960 and the SPI is $63,255.
  2. The CPI is .88 and the SPI is zero.
  3. The CPI is .88 and the SPI is 1.14.
  4. The CPI is 1.14 and the SPI is .88.

Answer(s): C



You are the project manager of the AMD project for your organization. In this project, you are currently performing quantitative risk analysis. The tool and technique you are using is simulation where the project model is computed many times with the input values chosen at random for each iteration. The goal is to create a probability distribution from the iterations for the project schedule. What technique will you use with this simulation?

  1. Pareto modeling
  2. Expected Monetary Value
  3. Analogous modeling
  4. Monte Carlo Technique

Answer(s): D



Share your comments for PMI RMP exam with other users:

C
Chengchaone
9/11/2023 10:22:00 AM

can you please upload please?

M
Mouli
9/2/2023 7:02:00 AM

question 75: option c is correct answer

J
JugHead
9/27/2023 2:40:00 PM

please add this exam

S
sushant
6/28/2023 4:38:00 AM

please upoad

J
John
8/7/2023 12:09:00 AM

has anyone recently attended safe 6.0 certification? is it the samq question from here.

B
Blessious Phiri
8/14/2023 3:49:00 PM

expository experience

C
concerned citizen
12/29/2023 11:31:00 AM

52 should be b&c. controller failure has nothing to do with this type of issue. degraded state tells us its a raid issue, and if the os is missing then the bootable device isnt found. the only other consideration could be data loss but thats somewhat broad whereas b&c show understanding of the specific issues the question is asking about.

D
deedee
12/23/2023 5:10:00 PM

great help!!!

S
Samir
8/1/2023 3:07:00 PM

very useful tools

S
Saeed
11/7/2023 3:14:00 AM

looks a good platform to prepare az-104

M
Matiullah
6/24/2023 7:37:00 AM

want to pass the exam

S
SN
9/5/2023 2:25:00 PM

good resource

Z
Zoubeyr
9/8/2023 5:56:00 AM

question 11 : d

U
User
8/29/2023 3:24:00 AM

only the free dumps will be enough for pass, or have to purchase the premium one. please suggest.

C
CW
7/6/2023 7:37:00 PM

good questions. thanks.

F
Farooqi
11/21/2023 1:37:00 AM

good for practice.

I
Isaac
10/28/2023 2:30:00 PM

great case study

M
Malviya
2/3/2023 9:10:00 AM

the questions in this exam dumps is valid. i passed my test last monday. i only whish they had their pricing in inr instead of usd. but it is still worth it.

R
rsmyth
5/18/2023 12:44:00 PM

q40 the answer is not d, why are you giving incorrect answers? snapshot consolidation is used to merge the snapshot delta disk files to the vm base disk

K
Keny
6/23/2023 9:00:00 PM

thanks, very relevant

M
Muhammad Rawish Siddiqui
11/29/2023 12:14:00 PM

wrong answer. it is true not false.

J
Josh
7/10/2023 1:54:00 PM

please i need the mo-100 questions

V
VINNY
6/2/2023 11:59:00 AM

very good use full

A
Andy
12/6/2023 5:56:00 AM

very valid questions

M
Mamo
8/12/2023 7:46:00 AM

will these question help me to clear pl-300 exam?

M
Marial Manyang
7/26/2023 10:13:00 AM

please provide me with these dumps questions. thanks

A
Amel Mhamdi
12/16/2022 10:10:00 AM

in the pdf downloaded is write google cloud database engineer i think that it isnt the correct exam

A
Angel
8/30/2023 10:58:00 PM

i think you have the answers wrong regarding question: "what are three core principles of web content accessibility guidelines (wcag)? answer: robust, operable, understandable

S
SH
5/16/2023 1:43:00 PM

these questions are not valid , they dont come for the exam now

S
sudhagar
9/6/2023 3:02:00 PM

question looks valid

V
Van
11/24/2023 4:02:00 AM

good for practice

D
Divya
8/2/2023 6:54:00 AM

need more q&a to go ahead

R
Rakesh
10/6/2023 3:06:00 AM

question 59 - a newly-created role is not assigned to any user, nor granted to any other role. answer is b https://docs.snowflake.com/en/user-guide/security-access-control-overview

N
Nik
11/10/2023 4:57:00 AM

just passed my exam today. i saw all of these questions in my text today. so i can confirm this is a valid dump.

AI Tutor 👋 I’m here to help!