PMI RMP Exam (page: 5)
PMI Risk Management Professional Exam
Updated on: 02-Jan-2026

Viewing Page 5 of 90

You are the project manager of the NHJ project for your company. This project has a budget at completion of $1,650,000 and you are 60 percent complete. According to the project plan, however, the project should be 65 percent complete. In this project you have spent $995,000 to reach this point of completion. There is a risk that this project may be late so you have taken some measures to recover the project schedule. Management would like to know, based on current performance, what the estimate at completion for this project will be.
What is the estimate at completion?

  1. $1,650,000
  2. $1,666,667
  3. $663,333
  4. -$8,333

Answer(s): B



Frank is the project manager of the NHQ project for his company. Frank is working with the project team, key stakeholders, and several subject matter experts on risks dealing with the new materials in the project. Frank wants to utilize a risk analysis method that will help the team to make decisions in the presence of the current uncertainty surrounding the new materials. Which risk analysis approach can Frank use to create an approach to make decisions in the presence of uncertainty?

  1. Monte Carlo Technique
  2. Qualitative risk analysis process
  3. Quantitative risk analysis process
  4. Delphi Technique

Answer(s): C



You are a risk auditor for your company. You are reviewing the contract types a project manager has used in her project. Of the following, which contract type has the most risk for the project manager as a buyer?

  1. Cost plus percentage of costs
  2. Time and material
  3. Cost plus incentive fee
  4. Fixed-price, incentive fee

Answer(s): A



Jane is the project manager of the GBB project for her company. In the current project a vendor has offered the project a ten percent discount based if they will order 100 units for the project. It is possible that the GBB Project may need the 100 units, but the cost of the units is not a top priority for the project. Jane documents the offer and tells the vendor that they will keep the offer in mind and continue with the project as planned. What risk response has been given in this project?

  1. Acceptance
  2. Enhance
  3. Exploiting
  4. Sharing

Answer(s): A



You are the project manager of the GHE Project. You have identified the following risks with the characteristics as shown in the following figure: How much capital should the project set aside for the risk contingency reserve?

  1. $142,000
  2. $41,750
  3. $23,750
  4. $232,000

Answer(s): C



Viewing Page 5 of 90



Share your comments for PMI RMP exam with other users:

Joseph J 7/11/2023 2:53:00 PM

i found the questions helpful
UNITED STATES


Meg 10/12/2023 8:02:00 AM

q 105 . ans is d
INDIA


Navaneeth S 7/14/2023 7:57:00 AM

i have interest to get a sybase iq dba certification
UNITED STATES


Aish 10/11/2023 5:27:00 AM

want to pass exm.
INDIA


Anonymous 6/12/2023 7:23:00 AM

are the answers correct?
INDIA


Kris 7/7/2023 9:43:00 AM

good morning, could you please upload this exam again, i need it to test my knowledge in sd-wan with version 7.0.
Anonymous


Meghraj mali 10/7/2023 1:47:00 PM

very nice question
CANADA


Noel 11/1/2022 9:14:00 PM

i have learning disability and this exam dumps allowed me to focus on the actual questions and not worry about notes and the those other study materials.
SOUTH AFRICA


Jas 10/25/2023 6:01:00 PM

165 should be apt
UNITED STATES


Neetu 6/22/2023 8:41:00 AM

please upload the dumps, real need of them
Anonymous


Mark 10/24/2023 1:34:00 AM

any recent feeedback?
UNITED STATES


Gopinadh 8/9/2023 4:05:00 AM

question number 2 is indicating you are giving proper questions. observe and change properly.
Anonymous


Santhi 1/1/2024 8:23:00 AM

passed today.40% questions were new.litwere case study,lots of new questions on afd,ratelimit,tm,lb,app gatway.got 2 set series of questions which are not present here.questions on azure cyclecloud, no.of vnet/vms required for implimentation,blueprints assignment/management group etc
INDIA


Raviraj Magadum 1/12/2024 11:39:00 AM

practice test
INDIA


sivaramakrishnan 7/27/2023 8:12:00 AM

want the dumps for emc content management server programming(cmsp)
Anonymous


Aderonke 10/23/2023 1:52:00 PM

brilliant and helpful
UNITED KINGDOM


Az 9/16/2023 2:43:00 PM

q75. azure files is pass
SWITZERLAND


ketty 11/9/2023 8:10:00 AM

very helpful
Anonymous


Sonail 5/2/2022 1:36:00 PM

thank you for these questions. it helped a lot.
UNITED STATES


Shariq 7/28/2023 8:00:00 AM

how do i get the h12-724 dumps
Anonymous


adi 10/30/2023 11:51:00 PM

nice data dumps
Anonymous


EDITH NCUBE 7/25/2023 7:28:00 AM

answers are correct
SOUTH AFRICA


Raja 6/20/2023 4:38:00 AM

good explanation
UNITED STATES


BigMouthDog 1/22/2022 8:17:00 PM

hi team just want to know if there is any update version of the exam 350-401
AUSTRALIA


francesco 10/30/2023 11:08:00 AM

helpful on 2017 scrum guide
EUROPEAN UNION


Amitabha Roy 10/5/2023 3:16:00 AM

planning to attempt for the exam.
Anonymous


Prem Yadav 7/29/2023 6:20:00 AM

pleaseee upload
INDIA


Ahmed Hashi 7/6/2023 5:40:00 PM

thanks ly so i have information cia
EUROPEAN UNION


mansi 5/31/2023 7:58:00 AM

hello team, i need sap qm dumps for practice
INDIA


Jamil aljamil 12/4/2023 4:47:00 AM

it’s good but not senatios based
UNITED KINGDOM


Cath 10/10/2023 10:19:00 AM

q.119 - the correct answer is b - they are not captured in an update set as theyre data.
VIET NAM


P 1/6/2024 11:22:00 AM

good matter
Anonymous


surya 7/30/2023 2:02:00 PM

please upload c_sacp_2308
CANADA


Sasuke 7/11/2023 10:30:00 PM

please upload the dump. thanks very much !!
Anonymous