PMI Risk Management Professional Exam RMP Exam Questions in PDF

Free PMI RMP Dumps Questions (page: 10)

Bill is the project manager of the JKH Project. He and the project team have identified a risk event in the project with a high probability of occurrence and the risk event has a high cost impact on the project. Bill discusses the risk event with Virginia, the primary project customer, and she decides that the requirements surrounding the risk event should be removed from the project. The removal of the requirements does affect the project scope, but it can release the project from the high risk exposure. What risk response has been enacted in this project?

  1. Mitigation
  2. Transference
  3. Acceptance
  4. Avoidance

Answer(s): D



Your project team has identified a project risk that must be responded to. The risk has been recorded in the risk register and the project team has been discussing potential risk responses for the risk event. The event is not likely to happen for several months but the probability of the event is high. Which one of the following is a valid response to the identified risk event?

  1. Corrective action
  2. Risk audit
  3. Technical performance measurement
  4. Earned value management

Answer(s): A



Beth is the project manager of the BFG Project for her company. In this project Beth has decided to create a contingency response based on the performance of the project schedule. If the project schedule variance is greater than $10,000 the contingency plan will be implemented. What is the formula for the schedule variance?

  1. SV=EV/PV
  2. SV=PV-EV
  3. SV=EV/AC
  4. SV=EV-PV

Answer(s): D



During which of the following processes, probability and impact matrix is prepared?

  1. Perform Qualitative Risk Analysis
  2. Monitoring and Control Risks
  3. Plan Risk Responses
  4. Perform Quantitative Risk Analysis

Answer(s): A



Holly is the project manager of the GHH Project. During risk identification and the subsequent risk analysis process she has identified a risk with a high probability and high impact for her project. She and the stakeholder agree that the project management plan should be changed to eliminate the risk threat entirely. What risk response has Holly used in this instance?

  1. This is the risk mitigation response.
  2. This is the avoidance risk response.
  3. This is the transference risk response.
  4. This is a scope change and not a risk response.

Answer(s): B



Share your comments for PMI RMP exam with other users:

S
Stephen
8/4/2023 9:08:00 PM

please upload cima e2 managing performance dumps

H
hp
6/16/2023 12:44:00 AM

wonderful questions

P
Priyo
11/14/2023 2:23:00 AM

i used this site since 2000, still great to support my career

J
Jude
8/29/2023 1:56:00 PM

why is the answer to "which of the following is required by scrum?" all of the following stated below since most of them are not mandatory? sprint retrospective. members must be stand up at the daily scrum. sprint burndown chart. release planning.

M
Marc blue
9/15/2023 4:11:00 AM

great job. hope this helps out.

A
Anne
9/13/2023 2:33:00 AM

upload please. many thanks!

P
pepe el toro
9/12/2023 7:55:00 PM

this is so interesting

A
Antony
11/28/2023 12:13:00 AM

great material thanks

T
Thembelani
5/30/2023 2:22:00 AM

anyone who wrote this exam recently

P
P
9/16/2023 1:27:00 AM

ok they re good

J
Jorn
7/13/2023 5:05:00 AM

relevant questions

A
AM
6/20/2023 7:54:00 PM

please post

N
Nagendra Pedipina
7/13/2023 2:22:00 AM

q:42 there has to be a image in the question to choose what does it mean from the options

B
BrainDumpee
11/18/2023 1:36:00 PM

looking for cphq dumps, where can i find these for free? please and thank you.

S
sheik
10/14/2023 11:37:00 AM

@aarun , thanks for the information. it would be great help if you share your email

R
Random user
12/11/2023 1:34:00 AM

1z0-1078-23 need this dumps

L
labuschanka
11/16/2023 6:06:00 PM

i gave the microsoft azure az-500 tests and prepared from this site as it has latest mock tests available which helped me evaluate my performance and score 919/1000

M
Marianne
10/22/2023 11:57:00 PM

i cannot see the button to go to the questions

S
sushant
6/28/2023 4:52:00 AM

good questions

A
A\MAM
6/27/2023 5:17:00 PM

q-6 ans-b correct. https://docs.paloaltonetworks.com/pan-os/9-1/pan-os-cli-quick-start/use-the-cli/commit-configuration-changes

U
unanimous
12/15/2023 6:38:00 AM

very nice very nice

A
akminocha
9/28/2023 10:36:00 AM

please help us with 1z0-1107-2 dumps

J
Jefi
9/4/2023 8:15:00 AM

please upload the practice questions

T
Thembelani
5/30/2023 2:45:00 AM

need this dumps

A
Abduraimov
4/19/2023 12:43:00 AM

preparing for this exam is overwhelming. you cannot pass without the help of these exam dumps.

P
Puneeth
10/5/2023 2:06:00 AM

new to this site but i feel it is good

A
Ashok Kumar
1/2/2024 6:53:00 AM

the correct answer to q8 is b. explanation since the mule app has a dependency, it is necessary to include project modules and dependencies to make sure the app will run successfully on the runtime on any other machine. source code of the component that the mule app is dependent of does not need to be included in the exported jar file, because the source code is not being used while executing an app. compiled code is being used instead.

M
Merry
7/30/2023 6:57:00 AM

good questions

V
VoiceofMidnight
12/17/2023 4:07:00 PM

Delayed the exam until December 29th.

U
Umar Ali
8/29/2023 2:59:00 PM

A and D are True

V
vel
8/28/2023 9:17:09 AM

good one with explanation

G
Gurdeep
1/18/2024 4:00:15 PM

This is one of the most useful study guides I have ever used.

AI Tutor 👋 I’m here to help!