PMI Risk Management Professional PMI-RMP Dumps in PDF

Free PMI PMI-RMP Real Questions (page: 24)

While creating the appropriate risk strategy, the project manager discovers that the project team lacks the necessary expertise to define the risk management plan.
What additional resources should be utilized?

  1. Consultants, organizational process assets, subject matter experts, and stakeholder tolerance analysis
  2. Consultants, industry group, and subject matter experts
  3. Consultants, professional and technical associations, subject matter experts, and industry groups
  4. Consultants, professional and technical associations, and subject matter experts

Answer(s): B



A project manager is creating a risk management plan, but participants in a group meeting are hesitant to express their concerns.
What will encourage participants to offer their opinions?

  1. Brainstorming
  2. Monte Carlo simulation
  3. Interviews
  4. Nominal group technique

Answer(s): C



Which of the following is a key element of neuro-linguistic programming?

  1. Re-coding based on agile methodology
  2. Flex-scheduling
  3. Cross-training
  4. Building rapport with others

Answer(s): D



When monitoring the execution quality of risk-related plans and processes, which of the following would be a useful metric to track and record?

  1. The number of risks in the project risk register
  2. The degree of variation from the baseline
  3. The number of levels in the risk breakdown structure
  4. The degree of variation from the risk response strategy

Answer(s): B



A project manager identifies a risk in a multifunctional project and decides to take no action.
What should the risk manager do if the risk occurs?

  1. Implement a workaround.
  2. Create a change request.
  3. Implement a contingency or fallback plan.
  4. Review the project management plan.

Answer(s): A



The project manager must evaluate two separate contractors for a project with an absolute finish date of 15 December. After performing a Monte Carlo assessment on the submitted schedules, the following information is found:



Which contractor should be chosen, because of having the highest statistical output?

  1. Contractor A should be chosen based on confidence level.
  2. Contractor B should be chosen based on probability.
  3. Contractor A should be chosen based on probability and confidence level.
  4. Contractor B should be chosen based on probability and confidence level.

Answer(s): A



When analyzing the reward system in a company, there is evidence that "fire-fighter behavior" is the highest rewarded behavior. It suggests that people are dealing with major problems primarily in an emergency mode, and deploying quickly. Secondly, those who work efficiently are getting the most attention and recognition for their efforts.

What impact does this observation potentially have on the risk management process?

  1. Nothing, since the reward system does not have any impact on the risk management process.
  2. It means that this company's culture does not reward all people, and it gives little attention to proactive behavior such as risk management.
  3. It does not matter as each project has its own rewards system with no relationship to the company's rewards.
  4. This is a positive situation for risk management, since it encourages quick deployment of solutions and workarounds when necessary.

Answer(s): B



What would be the next step after determining the agreed-upon risk response for a specific risk?

  1. Add the risk response to the project management plan and document the predicted exposure.
  2. Evaluate the project related implications and update the risk response to the project management plan if needed.
  3. Document the predicted exposure.
  4. Communicate to stakeholders.

Answer(s): D



Share your comments for PMI PMI-RMP exam with other users:

N
Noushin
11/28/2023 4:52:00 PM

i think the answer to question 42 is b not c

S
susan sandivore
8/28/2023 1:00:00 AM

thanks for the dump

A
Aderonke
10/31/2023 12:51:00 AM

fantastic assessments

P
Priscila
7/22/2022 9:59:00 AM

i find the xengine test engine simulator to be more fun than reading from pdf.

S
suresh
12/16/2023 10:54:00 PM

nice document

W
Wali
6/4/2023 10:07:00 PM

thank you for making the questions and answers intractive and selectable.

N
Nawaz
7/18/2023 1:10:00 AM

answers are correct?

D
das
6/23/2023 7:57:00 AM

can i belive this dump

S
Sanjay
10/15/2023 1:34:00 PM

great site to practice for sitecore exam

J
jaya
12/17/2023 8:36:00 AM

good for students

B
Bsmaind
8/20/2023 9:23:00 AM

nice practice dumps

K
kumar
11/15/2023 11:24:00 AM

nokia 4a0-114 dumps

V
Vetri
10/3/2023 12:59:00 AM

great content and wonderful to have the answers with explanation

R
Ranjith
8/21/2023 3:39:00 PM

for question #118, the answer is option c. the screen shot is showing the drop down, but the answer is marked incorrectly please update . thanks for sharing such nice questions.

E
Eduardo Ramírez
12/11/2023 9:55:00 PM

the correct answer for the question 29 is d.

D
Dass
11/2/2023 7:43:00 AM

question no 22: correct answers: bc, 1 per session 1 per page 1 per component always

R
Reddy
12/14/2023 2:42:00 AM

these are pretty useful

D
Daisy Delgado
1/9/2023 1:05:00 PM

awesome

A
Atif
6/13/2023 4:09:00 AM

yes please upload

X
Xunil
6/12/2023 3:04:00 PM

great job whoever put this together, for the greater good! thanks!

L
Lakshmi
10/2/2023 5:26:00 AM

just started to view all questions for the exam

R
rani
1/19/2024 11:52:00 AM

helpful material

G
Greg
11/16/2023 6:59:00 AM

hope for the best

H
hi
10/5/2023 4:00:00 AM

will post exam has finished

V
Vmotu
8/24/2023 11:14:00 AM

really correct and good analyze!

H
hicham
5/30/2023 8:57:00 AM

excellent thanks a lot

S
Suman C
7/7/2023 8:13:00 AM

will post once pass the cka exam

R
Ram
11/3/2023 5:10:00 AM

good content

N
Nagendra Pedipina
7/13/2023 2:12:00 AM

q:32 answer has to be option c

T
Tamer Barakat
12/7/2023 5:17:00 PM

nice questions

D
Daryl
8/1/2022 11:33:00 PM

i really like the support team in this website. they are fast in communication and very helpful.

C
Curtis Nakawaki
6/29/2023 9:13:00 PM

a good contemporary exam review

X
x-men
5/23/2023 1:02:00 AM

q23, its an array, isnt it? starts with [ and end with ]. its an array of objects, not object.

A
abuti
7/21/2023 6:24:00 PM

cool very helpfull

AI Tutor 👋 I’m here to help!