A stakeholder has rejected a project’s deliverable because it does not meet the original business need. It is further determined that the deliverable does not meet the requirements identified in the baseline.

What is the best approach to resolve this issue?

  1. Provide the stakeholder with a copy of the approved requirements baseline and move forward without making a change.
  2. Meet with the customer can apologize for misunderstanding the business’s need.
  3. Require development resources to work overtime to modify the deliverable to satisfy the stakeholder.
  4. Suggest re-estimating the requirement and following the change control process.

Answer(s): D



A business analyst has been assigned to a project to implement a new phone system for a customer call center. The business analyst will need to create a business case.

Which of the following components will the business analyst use as input to the business case?

  1. Product scope
  2. Work breakdown structure
  3. Project timeline
  4. Project scope

Answer(s): D



Which technique allows the collection of the maximum number of ideas on a subject from a group without considering the validity or practicality of the ideas?

  1. Prototyping
  2. Surveying
  3. Brainstorming
  4. Interviewing

Answer(s): C



The business analyst receives multiple changes from different stakeholders during the requirements gathering phase of a project. How should the business analyst track the requirements throughout the lifecycle of the project to secure the delivery of the expected solution?

  1. Record all the requirements in a matrix, review it regularly, and get approval from stakeholders.
  2. Perform inspections through the lifecycle of the project to detect any gaps and adjust the requirements baseline.
  3. Plan regular meetings with stakeholders to review the requirements baseline update and to discuss changes.
  4. Establish a risk traceability matrix and designate someone to manage each risk with the appropriate response.

Answer(s): B



When a business analyst uses subject matter experts to define roles and identify influencers, which project artifact is created or updated?

  1. Stakeholder management plan
  2. RACI matrix
  3. Stakeholder register
  4. SWOT analysis

Answer(s): C


Reference:

https://cs.anu.edu.au/courses/comp3120/public_docs/BOKV1_6.pdf



Share your comments for PMI PMI-PBA exam with other users:

B
Blessious Phiri
8/15/2023 3:19:00 PM

oracle 19c is complex db

S
Sreenivas
10/24/2023 12:59:00 AM

helpful for practice

L
Liz
9/11/2022 11:27:00 PM

support team is fast and deeply knowledgeable. i appreciate that a lot.

N
Namrata
7/15/2023 2:22:00 AM

helpful questions

L
lipsa
11/8/2023 12:54:00 PM

thanks for question

E
Eli
6/18/2023 11:27:00 PM

the software is provided for free so this is a big change. all other sites are charging for that. also that fucking examtopic site that says free is not free at all. you are hit with a pay-wall.

O
open2exam
10/29/2023 1:14:00 PM

i need exam questions nca 6.5 any help please ?

G
Gerald
9/11/2023 12:22:00 PM

just took the comptia cybersecurity analyst (cysa+) - wished id seeing this before my exam

R
ryo
9/10/2023 2:27:00 PM

very helpful

J
Jamshed
6/20/2023 4:32:00 AM

i need this exam

R
Roberto Capra
6/14/2023 12:04:00 PM

nice questions... are these questions the same of the exam?

S
Synt
5/23/2023 9:33:00 PM

need to view

V
Vey
5/27/2023 12:06:00 AM

highly appreciate for your sharing.

T
Tshepang
8/18/2023 4:41:00 AM

kindly share this dump. thank you

J
Jay
9/26/2023 8:00:00 AM

link plz for download

L
Leo
10/30/2023 1:11:00 PM

data quality oecd

B
Blessious Phiri
8/13/2023 9:35:00 AM

rman is one good recovery technology

D
DiligentSam
9/30/2023 10:26:00 AM

need it thx

V
Vani
8/10/2023 8:11:00 PM

good questions

F
Fares
9/11/2023 5:00:00 AM

good one nice revision

L
Lingaraj
10/26/2023 1:27:00 AM

i love this thank you i need

M
Muhammad Rawish Siddiqui
12/5/2023 12:38:00 PM

question # 142: data governance is not one of the deliverables in the document and content management context diagram.

A
al
6/7/2023 10:25:00 AM

most answers not correct here

B
Bano
1/19/2024 2:29:00 AM

what % of questions do we get in the real exam?

O
Oliviajames
10/25/2023 5:31:00 AM

i just want to tell you. i took my microsoft az-104 exam and passed it. your program was awesome. i especially liked your detailed questions and answers and practice tests that made me well-prepared for the exam. thanks to this website!!!

D
Divya
8/27/2023 12:31:00 PM

all the best

K
KY
1/1/2024 11:01:00 PM

very usefull document

A
Arun
9/20/2023 4:52:00 PM

nice and helpful questions

J
Joseph J
7/11/2023 2:53:00 PM

i found the questions helpful

M
Meg
10/12/2023 8:02:00 AM

q 105 . ans is d

N
Navaneeth S
7/14/2023 7:57:00 AM

i have interest to get a sybase iq dba certification

A
Aish
10/11/2023 5:27:00 AM

want to pass exm.

A
Anonymous
6/12/2023 7:23:00 AM

are the answers correct?

K
Kris
7/7/2023 9:43:00 AM

good morning, could you please upload this exam again, i need it to test my knowledge in sd-wan with version 7.0.

AI Tutor 👋 I’m here to help!