A project team meets to estimate user stories for a sprint. While an important non-functional requirement must be delivered in the sprint, the estimate exceeds sprint capacity.What should the team do?
Answer(s): C
A development team and product owner disagrees on a user story in the product backlog.What should the agile practitioner do?
During a planning session, four out of five team members vote to include eight story points in a particular story, while the fifth member votes for five story points.How should this be handled?
A project is starting and the type of work is complex and suitable for agile. In assessing the team members, it appears that co-location would be a challenge.What should the agile practitioner do?
Answer(s): A
Team A is working on the second sprint of a product release. Team B, which is an interdependent team located on the same floor, requires exclusive and frequent information to complete its sprint goal.What should the agile team do?
Answer(s): B
Share your comments for PMI PMI-ACP exam with other users:
i think the answer to question 42 is b not c
thanks for the dump
fantastic assessments
i find the xengine test engine simulator to be more fun than reading from pdf.
nice document
thank you for making the questions and answers intractive and selectable.
answers are correct?
can i belive this dump
great site to practice for sitecore exam
good for students
nice practice dumps
nokia 4a0-114 dumps
great content and wonderful to have the answers with explanation
for question #118, the answer is option c. the screen shot is showing the drop down, but the answer is marked incorrectly please update . thanks for sharing such nice questions.
the correct answer for the question 29 is d.
question no 22: correct answers: bc, 1 per session 1 per page 1 per component always
these are pretty useful
awesome
yes please upload
great job whoever put this together, for the greater good! thanks!
just started to view all questions for the exam
helpful material
hope for the best
will post exam has finished
really correct and good analyze!
excellent thanks a lot
will post once pass the cka exam
good content
q:32 answer has to be option c
nice questions
i really like the support team in this website. they are fast in communication and very helpful.
a good contemporary exam review
q23, its an array, isnt it? starts with [ and end with ]. its an array of objects, not object.
cool very helpfull
Keeping this site free takes real effort. We constantly battle automated scraping and unauthorized content copying. A quick account helps us protect the community and keep the site free.
To continue studying for your PMI-ACP, please sign in or create a free account.