The basis of identification for current or potential problems to support later claims or new procurements is provided by:
Answer(s): C
4.4.1.5 Work Performance InformationWork performance information is the performance data collected from various controlling processes, analyzed in context, and integrated based on relationships across areas. Thus work performance data has been transformed into work performance information. Data in itself cannot be used in the decision-making process as it has only out-of-context meaning. Work performance information, however, is correlated and contextualized, and provides a sound foundation for project decisions.Work performance information is circulated through communication processes. Examples of performance information are status of deliverables, implementation status for change requests, and forecasted estimates to complete.
Which Collect Requirements output links the product requirements to the deliverables that satisfy them?
Answer(s): B
5.2.3.2 Requirements Traceability MatrixThe requirements traceability matrix is a grid that links product requirements from their origin to the deliverables that satisfy them. The implementation of a requirements traceability matrix helps ensure that each requirement adds business value by linking it to the business and project objectives. It provides a means to track requirements throughout the project life cycle, helping to ensure that requirements approved in the requirements documentation are delivered at the end of the project. Finally, it provides a structure for managing changes to the product scope.Tracing includes, but is not limited to, tracing requirements for the following:Business needs, opportunities, goals, and objectives; Project objectives;Project scope/WBS deliverables; Product design;Product development;Test strategy and test scenarios; andHigh-level requirements to more detailed requirements.Attributes associated with each requirement can be recorded in the requirements traceability matrix. These attributes help to define key information about the requirement. Typical attributes used in the requirements traceability matrix may include: a unique identifier, a textual description of the requirement, the rationale for inclusion, owner, source, priority, version, current status (such as active, cancelled, deferred, added, approved, assigned, completed), and status date. Additional attributes to ensure that the requirement has met stakeholders’ satisfaction may include stability, complexity, and acceptance criteria.Process: 5.2 Collect RequirementsDefinition: The process of determining, documenting, and managing stakeholder needs and requirements to meet project objectives.Key Benefit: The key benefit of this process is that it provides the basis for defining and managing the project scope including product scope.Inputs1. Scope management plan 2. Requirements management plan3. Stakeholder management plan4. Project charter5. Stakeholder registerTools & Techniques1. Interviews2. Focus groups3. Facilitated workshops4. Group creativity techniques5. Group decision-making techniques6. Questionnaires and surveys7. Observations8. Prototypes9. Benchmarking10. Context diagrams11. Document analysisOutputs1. Requirements documentation2. Requirements traceability matrix
Units of measure, level of precision, level of accuracy, control thresholds, and rules of performance measurement are examples of items that are established in the:
Answer(s): A
Which type of dependency is established based on knowledge of best practices within a particular application area or some unusual aspect of the project in which a specific sequence is desired, even though there may be other acceptable sequences?
Answer(s): D
6.3.2.2 Dependency DeterminationDependencies may be characterized by the following attributes: mandatory or discretionary, internal or external, as described below. Dependency has four attributes, but two can be applicable at the same time in following ways: mandatory external dependencies, mandatory internal dependencies, discretionary external dependencies, or discretionary internal dependencies.Mandatory dependencies. Mandatory dependencies are those that are legally or contractually required or inherent in the nature of the work. Mandatory dependencies often involve physical limitations, such as on a construction project, where it is impossible to erect the superstructure until after the foundation has been built, or on an electronics project, where a prototype has to be built before it can be tested.Mandatory dependencies are also sometimes referred to as hard logic or hard dependencies. Technical dependencies may not be mandatory. The project team determines which dependencies are mandatory during the process of sequencing the activities. Mandatory dependencies should not be confused with assigning schedule constraints in the scheduling tool.Discretionary dependencies. Discretionary dependencies are sometimes referred to as preferred logic, preferential logic, or soft logic. Discretionary dependencies are established based on knowledge of best practices within a particular application area or some unusual aspect of the project where a specific sequence is desired, even though there may be other acceptable sequences. Discretionary dependencies should be fully documented since they can create arbitrary total float values and can limit later scheduling options. When fast tracking techniques are employed, these discretionary dependencies should be reviewed and considered for modification or removal. The project team determines which dependencies are discretionary during the process of sequencing the activities.External dependencies. External dependencies involve a relationship between project activities and non- project activities. These dependencies are usually outside the project team’s control. For example, the testing activity in a software project may be dependent on the delivery of hardware from an external source, or governmental environmental hearings may need to be held before site preparation can begin on a construction project. The project management team determines which dependencies are external during the process of sequencing the activities.Internal dependencies. Internal dependencies involve a precedence relationship between project activities and are generally inside the project team’s control. For example, if the team cannot test a machine until they assemble it, this is an internal mandatory dependency. The project management team determines which dependencies are internal during the process of sequencing the activities.
Sensitivity analysis is typically displayed as a/an:
11.4.2.2 Quantitative Risk Analysis and Modeling Techniques• Sensitivity analysis. Sensitivity analysis helps to determine which risks have the most potential impact on the project. It helps to understand how the variations in project’s objectives correlate with variations in different uncertainties. Conversely, it examines the extent to which the uncertainty of each project element affects the objective being studied when all other uncertain elements are held at their baseline values. One typical display of sensitivity analysis is the tornado diagram (Figure 11-15), which is useful for comparing relative importance and impact of variables that have a high degree of uncertainty to those that are more stable. The Tornado diagram is also helpful in analyzing risk-taking scenarios enabled on specific risks whose quantitative analysis highlights possible benefits greater than corresponding identified negative impacts. A tornado diagram is a special type of bar chart used in sensitivity analysis for comparing the relative importance of the variables. In a tornado diagram, the Y-axis contains each type of uncertainty at base values, and the X-axis contains the spread or correlation of the uncertainty to the studied output. In this fgure, each uncertainty contains a horizontal bar and is ordered vertically to show uncertainties with a decreasing spread from the base values.
Share your comments for PMI PMI-100 exam with other users:
next time i will write a full review
first time using this site
please sent me oracle 1z0-1105-22 pdf
very helpful
good info about oml
very useful to practice
this website is very helpful.
good content
so challenging
17 should be d ,for morequery its scale out
nice question
yes.
good mateial
good practice exam
impressivre qustion
questions seem helpful
question 21 answer is alerts
am preparing for exam
good one thanks
only got thru 5 questions, need more to evaluate
q26 should be b
the aaa triad in information security is authentication, accounting and authorisation so the answer should be d 1, 3 and 5.
need to attend this
these are free brain dumps i understand, how can one get free pdf
provide access
good morning
please upload the ncp-mci 6.5 dumps, really need to practice this one. thanks guys
question 16: https://help.salesforce.com/s/articleview?id=sf.care_console_overview.htm&type=5
yes i m prepared exam
my experience was great with this site as i studied for the ms-900 from here and got 900/1000 on the test. my main focus was on the tutorials which were provided and practice questions. thanks!
great course
very good question
question: 93 which statement is true regarding the result? sales contain 6 columns and values contain 7 columns so c is not right answer.