The basis of identification for current or potential problems to support later claims or new procurements is provided by:
Answer(s): C
4.4.1.5 Work Performance InformationWork performance information is the performance data collected from various controlling processes, analyzed in context, and integrated based on relationships across areas. Thus work performance data has been transformed into work performance information. Data in itself cannot be used in the decision-making process as it has only out-of-context meaning. Work performance information, however, is correlated and contextualized, and provides a sound foundation for project decisions.Work performance information is circulated through communication processes. Examples of performance information are status of deliverables, implementation status for change requests, and forecasted estimates to complete.
Which Collect Requirements output links the product requirements to the deliverables that satisfy them?
Answer(s): B
5.2.3.2 Requirements Traceability MatrixThe requirements traceability matrix is a grid that links product requirements from their origin to the deliverables that satisfy them. The implementation of a requirements traceability matrix helps ensure that each requirement adds business value by linking it to the business and project objectives. It provides a means to track requirements throughout the project life cycle, helping to ensure that requirements approved in the requirements documentation are delivered at the end of the project. Finally, it provides a structure for managing changes to the product scope.Tracing includes, but is not limited to, tracing requirements for the following:Business needs, opportunities, goals, and objectives; Project objectives;Project scope/WBS deliverables; Product design;Product development;Test strategy and test scenarios; andHigh-level requirements to more detailed requirements.Attributes associated with each requirement can be recorded in the requirements traceability matrix. These attributes help to define key information about the requirement. Typical attributes used in the requirements traceability matrix may include: a unique identifier, a textual description of the requirement, the rationale for inclusion, owner, source, priority, version, current status (such as active, cancelled, deferred, added, approved, assigned, completed), and status date. Additional attributes to ensure that the requirement has met stakeholders’ satisfaction may include stability, complexity, and acceptance criteria.Process: 5.2 Collect RequirementsDefinition: The process of determining, documenting, and managing stakeholder needs and requirements to meet project objectives.Key Benefit: The key benefit of this process is that it provides the basis for defining and managing the project scope including product scope.Inputs1. Scope management plan 2. Requirements management plan3. Stakeholder management plan4. Project charter5. Stakeholder registerTools & Techniques1. Interviews2. Focus groups3. Facilitated workshops4. Group creativity techniques5. Group decision-making techniques6. Questionnaires and surveys7. Observations8. Prototypes9. Benchmarking10. Context diagrams11. Document analysisOutputs1. Requirements documentation2. Requirements traceability matrix
Units of measure, level of precision, level of accuracy, control thresholds, and rules of performance measurement are examples of items that are established in the:
Answer(s): A
Which type of dependency is established based on knowledge of best practices within a particular application area or some unusual aspect of the project in which a specific sequence is desired, even though there may be other acceptable sequences?
Answer(s): D
6.3.2.2 Dependency DeterminationDependencies may be characterized by the following attributes: mandatory or discretionary, internal or external, as described below. Dependency has four attributes, but two can be applicable at the same time in following ways: mandatory external dependencies, mandatory internal dependencies, discretionary external dependencies, or discretionary internal dependencies.Mandatory dependencies. Mandatory dependencies are those that are legally or contractually required or inherent in the nature of the work. Mandatory dependencies often involve physical limitations, such as on a construction project, where it is impossible to erect the superstructure until after the foundation has been built, or on an electronics project, where a prototype has to be built before it can be tested.Mandatory dependencies are also sometimes referred to as hard logic or hard dependencies. Technical dependencies may not be mandatory. The project team determines which dependencies are mandatory during the process of sequencing the activities. Mandatory dependencies should not be confused with assigning schedule constraints in the scheduling tool.Discretionary dependencies. Discretionary dependencies are sometimes referred to as preferred logic, preferential logic, or soft logic. Discretionary dependencies are established based on knowledge of best practices within a particular application area or some unusual aspect of the project where a specific sequence is desired, even though there may be other acceptable sequences. Discretionary dependencies should be fully documented since they can create arbitrary total float values and can limit later scheduling options. When fast tracking techniques are employed, these discretionary dependencies should be reviewed and considered for modification or removal. The project team determines which dependencies are discretionary during the process of sequencing the activities.External dependencies. External dependencies involve a relationship between project activities and non- project activities. These dependencies are usually outside the project team’s control. For example, the testing activity in a software project may be dependent on the delivery of hardware from an external source, or governmental environmental hearings may need to be held before site preparation can begin on a construction project. The project management team determines which dependencies are external during the process of sequencing the activities.Internal dependencies. Internal dependencies involve a precedence relationship between project activities and are generally inside the project team’s control. For example, if the team cannot test a machine until they assemble it, this is an internal mandatory dependency. The project management team determines which dependencies are internal during the process of sequencing the activities.
Sensitivity analysis is typically displayed as a/an:
11.4.2.2 Quantitative Risk Analysis and Modeling Techniques• Sensitivity analysis. Sensitivity analysis helps to determine which risks have the most potential impact on the project. It helps to understand how the variations in project’s objectives correlate with variations in different uncertainties. Conversely, it examines the extent to which the uncertainty of each project element affects the objective being studied when all other uncertain elements are held at their baseline values. One typical display of sensitivity analysis is the tornado diagram (Figure 11-15), which is useful for comparing relative importance and impact of variables that have a high degree of uncertainty to those that are more stable. The Tornado diagram is also helpful in analyzing risk-taking scenarios enabled on specific risks whose quantitative analysis highlights possible benefits greater than corresponding identified negative impacts. A tornado diagram is a special type of bar chart used in sensitivity analysis for comparing the relative importance of the variables. In a tornado diagram, the Y-axis contains each type of uncertainty at base values, and the X-axis contains the spread or correlation of the uncertainty to the studied output. In this fgure, each uncertainty contains a horizontal bar and is ordered vertically to show uncertainties with a decreasing spread from the base values.
Share your comments for PMI PMI-100 exam with other users:
question 13 tda - c01 answer : quick table calculation -> percentage of total , compute using table down
pls share teh dump
question 44 answer is user risk
please post the questions for preparation
thanks for the questions
please reopen it now ..its really urgent
these practice exam questions were exactly what i needed. the variety of questions and the realistic exam-like environment they created helped me assess my strengths and weaknesses. i felt more confident and well-prepared on exam day, and i owe it to this exam dumps!
thank u it very instructuf
its helpful?
is this dump still valid???
question 205 answer is b
question 39, should be answer b, directions stated is being sudneted from /21 to a /23. a /23 has 512 ips so 510 hosts. and can make 4 subnets out of the /21
beautiful test engine software and very helpful. questions are same as in the real exam. i passed my paper.
the questions are exactly the same in real exam. just make sure not to answer all them correct or else they suspect you are cheating.
question: 78 the right answer i think is d not a
very helpful
i am writing this exam tomorrow and have dumps
can i have the icdl excel exam
please upload it
hye when will post again the past year question for this h13-311_v3 part since i have to for my test tommorow…thank you very much
on question 22, option b-once per session is also valid.
this website is very helpful
its my first time exam
correct answers are device configuration-enable the automatic installation of webview2 runtime. & policy management- prevent users from submitting feedback.
is this dump still valid? today is 9-july-2023
i need this exam.. please upload these are really helpful
please upload the oracle 1z0-1059-22 dumps
very good questions
nice, first step to exams
is this valid for chfiv9 as well... as i am reker 3rd time...
great exam for people taking 220-1101
this is very helpfull for me
just started preparing for the exam
these are the type of questions i need.