Project Stakeholder Management focuses on:
Answer(s): C
PROJECT STAKEHOLDER MANAGEMENTProject Stakeholder Management includes the processes required to identify the people, groups, or organizations that could impact or be impacted by the project, to analyze stakeholder expectations and their impact on the project, and to develop appropriate management strategies for effectively engaging stakeholders in project decisions and execution. Stakeholder management also focuses on continuous communication with stakeholders to understand their needs and expectations, addressing issues as they occur, managing conflicting interests and fostering appropriate stakeholder engagement in project decisions and activities. Stakeholder satisfaction should be managed as a key project objective
A risk that arises as a direct result of implementing a risk response is called a:
Answer(s): D
11.5.2 Plan Risk Responses: Tools and TechniquesSeveral risk response strategies are available. The strategy or mix of strategies most likely to be effective should be selected for each risk. Risk analysis tools, such as decision tree analysis (Section 11.4.2.2), can be used to choose the most appropriate responses. Specific actions are developed to implement that strategy, including primary and backup strategies, as necessary. A fallback plan can be developed for implementation if the selected strategy turns out not to be fully effective or if an accepted risk occurs. Secondary risks should also be reviewed. Secondary risks are risks that arise as a direct result of implementing a risk response. A contingency reserve is often allocated for time or cost. If developed, it may include identification of the conditions that trigger its use.
The purpose of developing a project scope management plan is to:
Answer(s): B
A tool and technique used in the Develop Project Charter process is:
4.1.2.1 Expert JudgmentExpert judgment is often used to assess the inputs used to develop the project charter. Expert judgment is applied to all technical and management details during this process. Such expertise is provided by any group or individual with specialized knowledge or training and is available from many sources, including:Other units within the organization, Consultants,Stakeholders, including customers or sponsors, Professional and technical associations, Industry groups,Subject matter experts (SME), and Project management office (PMO).4.1.3.1 Project CharterThe project charter is the document issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities. It documents the business needs, assumptions, constraints, the understanding of the customer’s needs and high-level requirements, and the new product, service, or result that it is intended to satisfy, such as:Project purpose or justification,Measurable project objectives and related success criteria, High-level requirements,Assumptions and constraints,High-level project description and boundaries, High-level risks,Summary milestone schedule, Summary budget, Stakeholder list,Project approval requirements (i.e., what constitutes project success, who decides the project is successful, and who signs off on the project),Assigned project manager, responsibility, and authority level, andName and authority of the sponsor or other person(s) authorizing the project charter.Process: 4.1. Develop Project CharterDefinition: The process of developing a document that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.Key Benefit: The key benefit of this process is a well-defined project start and project boundaries, creation of a formal record of the project, and a direct way for senior management to formally accept and commit to the project.Inputs1. Project statement of work2. Business case3. Agreements4. Enterprise environmental factors5. Organizational process assetsTools & Techniques 1. Expert judgment2. Facilitation techniquesOutputs1. Project charter
The following chart contains information about the tasks in a project.Based on the chart, what is the cost performance index (CPI) for Task 2?
Share your comments for PMI PMI-100 exam with other users:
helpful material
hope for the best
will post exam has finished
really correct and good analyze!
excellent thanks a lot
will post once pass the cka exam
good content
q:32 answer has to be option c
nice questions
i really like the support team in this website. they are fast in communication and very helpful.
a good contemporary exam review
q23, its an array, isnt it? starts with [ and end with ]. its an array of objects, not object.
cool very helpfull
i just passed. this exam dumps is the same one from prepaway and examcollection. it has all the real test questions.
is this a valid prince2 practitioner dumps?
all are relatable questions
might help me to prepare for the exam
just paid and downlaod the 2 exams using the 50% sale discount. so far i was able to download the pdf and the test engine. all looks good.
i think it should be a,c. option d goes against the principle of building anything custom unless there are no work arounds available
very legible
is this exam accurate or helpful?
please upload dump, i have exam in 2 days
this is useful
question 232 answer should be perimeter not netowrk layer. wrong answer selected
hi team, could you please provide this dump ?
very helpful to clear the exam and understand the concept.
i think it is great that you are helping people when they need it. thanks.
cannot evaluate yet
a laptops wireless antenna is most likely located in the bezel of the lid
good examplae to learn basic
this is useful information
looks usefull
question 81 should be c.