What is the architecture owner responsible for?

  1. Mitigating key technical risks
  2. Working cross-functionally to deliver the solution
  3. Removing impediments
  4. Determining the priorities for the solution

Answer(s): A

Explanation:

In Disciplined Agile, the Architecture Owner is responsible for mitigating key technical risks. This role focuses on overseeing the architectural integrity of the solution being developed, ensuring that the team makes sound technical decisions that align with the desired architecture and quality attributes of the project. The Architecture Owner helps in identifying and addressing potential technical risks early in the project life cycle, collaborating with the team to adapt the architecture as necessary to mitigate these risks.
This individual works closely with the team to guide architectural considerations, ensures compliance with the chosen architectural strategies, and maintains the overall technical direction of the project. Although they are involved in other cross-functional activities, their primary responsibility is to foresee and address technical challenges that could jeopardize the success of the project.


Reference:

PMI, "Choose Your WoW! A Disciplined Agile Delivery Handbook for Optimizing Your Way of Working (WoW)," which details the responsibilities of the Architecture Owner, including mitigating technical risks.

PMI Disciplined Agile (DA) Toolkit, which provides an overview of the roles and responsibilities within DA, particularly the Architecture Owner's role in managing technical risks.



Why is the coordination meeting important for a project team?

  1. It provides a demo of the product to keep everyone up to date.
  2. It provides an opportunity for the team to help itself stay m sync.
  3. It allows the stakeholders to see how well the team is working together.
  4. If allows the team to reassess the backlog to meet their needs.

Answer(s): B

Explanation:

The coordination meeting (often referred to as the daily stand-up or daily coordination meeting in Agile practices) is crucial for a project team because it provides an opportunity for the team to help itself stay in sync. This meeting is typically held daily and allows team members to communicate their progress, discuss any challenges or impediments, and align their activities with the project's goals.
In Disciplined Agile, such meetings are vital for fostering collaboration and ensuring that everyone on the team is aware of what others are doing, which helps avoid misunderstandings, duplicate work, and potential blockers. The purpose is not to report to a manager but for the team to coordinate, plan, and adjust their work dynamically to ensure continuous alignment and effective progress towards the team's objectives.


Reference:

PMI Disciplined Agile Toolkit, which emphasizes the importance of coordination meetings (or daily stand-ups) in maintaining team alignment and promoting self-organization. PMI, "Choose Your WoW! A Disciplined Agile Delivery Handbook for Optimizing Your Way of Working (WoW)," which describes the value of regular team coordination to ensure synchronicity and continuous alignment within agile teams.



What arc the three categories of process blades, according to Disciplined Agile (DA)? (Choose three)

  1. Disciplined DevOps
  2. Disciplined Protect Management Office (PMO)
  3. Disciplined Agile IT
  4. Disciplined Kanban
  5. Disciplined Agile Delivery (DAD)

Answer(s): A,B,E

Explanation:

In PMI's Disciplined Agile (DA) framework, process blades refer to modular, process decision-making tools that help organizations optimize their way of working (WoW). They are categorized into three primary areas:
Disciplined DevOps (A) - This blade focuses on streamlining and integrating development and operations activities, with a focus on continuous delivery and automation practices. It encompasses activities such as IT operations, quality assurance, data management, and release management to improve flow and operational efficiency.
Disciplined Project Management Office (PMO) (B) - The Disciplined Agile PMO is designed to oversee and provide governance to an organization's project and product delivery processes. It facilitates strategic alignment and value delivery across teams, ensuring that agile principles are applied at a broader organizational level, and that governance and funding models are adaptable. Disciplined Agile Delivery (DAD) (E) - Disciplined Agile Delivery is a hybrid agile approach focused on the delivery of software-based solutions. It combines strategies from Agile, Lean, Scrum, and other methodologies to create a flexible and scalable approach to delivery. DAD provides guidance across all stages of solution delivery, from concept to deployment. These three categories help organizations leverage Disciplined Agile principles by enabling flexible, scalable solutions that can be customized based on their specific context and needs.



What arc Disciplined Agile milestones based on?

  1. Continuous integration
  2. Documentation
  3. Lean governance
  4. Lifecycle

Answer(s): C

Explanation:

Disciplined Agile (DA) milestones are based on the concept of Lean governance, which is focused on ensuring that agile practices are aligned with the organization's overall objectives while minimizing bureaucracy. In the DA framework, milestones provide lightweight checkpoints throughout the lifecycle to ensure that the team is on track to meet its objectives and deliver value. These milestones are not about documentation or merely following a predefined lifecycle but are instead focused on achieving business value in a lean and efficient manner. A . Continuous integration is a practice rather than a basis for milestones. B . Documentation is not a central focus of DA milestones.

D . Lifecycle refers to the various phases in the DA process, but milestones are specific checkpoints within these phases guided by lean governance principles. Thus, C. Lean governance is the correct answer, as it embodies the principles upon which Disciplined Agile milestones are established.



Why is the retrospective an important agile ceremony?

  1. It allows the team time to focus on hew they can better work together moving forward.
  2. It allows the team to organize the product backlog into categories which are meaningful to them.
  3. It prohibits stakeholders who attended the demo from giving additional requests to the team.
  4. If provides the product owner with the opportunity to see how well the team works together.

Answer(s): A

Explanation:

In Agile, and specifically within the Disciplined Agile framework, the retrospective is a crucial ceremony where the team reflects on their past iteration to identify areas of improvement. The main purpose is to foster continuous improvement by focusing on how the team can better work together moving forward. It encourages open communication, self-reflection, and team accountability, aligning with the agile principles of continuous learning and adaptation.
The other options are incorrect because:
B . Organizing the product backlog is typically done during backlog refinement sessions, not retrospectives.
C . Prohibiting stakeholders from making requests is not the purpose of a retrospective; stakeholder feedback is valuable and is usually gathered during review sessions. D . Providing the product owner with insights into team dynamics may occur, but it is not the primary goal of the retrospective.
Therefore, the correct answer is A. It allows the team time to focus on how they can better work together moving forward, as it aligns with the continuous improvement objective central to Agile and Disciplined Agile practices.



Viewing Page 2 of 11



Share your comments for PMI DASM exam with other users:

francesco 10/30/2023 11:08:00 AM

helpful on 2017 scrum guide
EUROPEAN UNION


Amitabha Roy 10/5/2023 3:16:00 AM

planning to attempt for the exam.
Anonymous


Prem Yadav 7/29/2023 6:20:00 AM

pleaseee upload
INDIA


Ahmed Hashi 7/6/2023 5:40:00 PM

thanks ly so i have information cia
EUROPEAN UNION


mansi 5/31/2023 7:58:00 AM

hello team, i need sap qm dumps for practice
INDIA


Jamil aljamil 12/4/2023 4:47:00 AM

it’s good but not senatios based
UNITED KINGDOM


Cath 10/10/2023 10:19:00 AM

q.119 - the correct answer is b - they are not captured in an update set as theyre data.
VIET NAM


P 1/6/2024 11:22:00 AM

good matter
Anonymous


surya 7/30/2023 2:02:00 PM

please upload c_sacp_2308
CANADA


Sasuke 7/11/2023 10:30:00 PM

please upload the dump. thanks very much !!
Anonymous


V 7/4/2023 8:57:00 AM

good questions
UNITED STATES


TTB 8/22/2023 5:30:00 AM

hi, could you please update the latest dump version
Anonymous


T 7/28/2023 9:06:00 PM

this question is keep repeat : you are developing a sales application that will contain several azure cloud services and handle different components of a transaction. different cloud services will process customer orders, billing, payment, inventory, and shipping. you need to recommend a solution to enable the cloud services to asynchronously communicate transaction information by using xml messages. what should you include in the recommendation?
NEW ZEALAND


Gurgaon 9/28/2023 4:35:00 AM

great questions
UNITED STATES


wasif 10/11/2023 2:22:00 AM

its realy good
UNITED ARAB EMIRATES


Shubhra Rathi 8/26/2023 1:12:00 PM

oracle 1z0-1059-22 dumps
Anonymous


Leo 7/29/2023 8:48:00 AM

please share me the pdf..
INDIA


AbedRabbou Alaqabna 12/18/2023 3:10:00 AM

q50: which two functions can be used by an end user when pivoting an interactive report? the correct answer is a, c because we do not have rank in the function pivoting you can check in the apex app
GREECE


Rohan Limaye 12/30/2023 8:52:00 AM

best to practice
Anonymous


Aparajeeta 10/13/2023 2:42:00 PM

so far it is good
Anonymous


Vgf 7/20/2023 3:59:00 PM

please provide me the dump
Anonymous


Deno 10/25/2023 1:14:00 AM

i failed the cisa exam today. but i have found all the questions that were on the exam to be on this site.
Anonymous


CiscoStudent 11/15/2023 5:29:00 AM

in question 272 the right answer states that an autonomous acces point is "configured and managed by the wlc" but this is not what i have learned in my ccna course. is this a mistake? i understand that lightweight aps are managed by wlc while autonomous work as standalones on the wlan.
Anonymous


pankaj 9/28/2023 4:36:00 AM

it was helpful
Anonymous


User123 10/8/2023 9:59:00 AM

good question
UNITED STATES


vinay 9/4/2023 10:23:00 AM

really nice
Anonymous


Usman 8/28/2023 10:07:00 AM

please i need dumps for isc2 cybersecuity
Anonymous


Q44 7/30/2023 11:50:00 AM

ans is coldline i think
UNITED STATES


Anuj 12/21/2023 1:30:00 PM

very helpful
Anonymous


Giri 9/13/2023 10:31:00 PM

can you please provide dumps so that it helps me more
UNITED STATES


Aaron 2/8/2023 12:10:00 AM

thank you for providing me with the updated question and answers. this version has all the questions from the exam. i just saw them in my exam this morning. i passed my exam today.
SOUTH AFRICA


Sarwar 12/21/2023 4:54:00 PM

how i can see exam questions?
CANADA


Chengchaone 9/11/2023 10:22:00 AM

can you please upload please?
Anonymous


Mouli 9/2/2023 7:02:00 AM

question 75: option c is correct answer
Anonymous