The component of the human resource management plan that includes ways in which team members can obtain certifications that support their ability to benefit the project is known as:

  1. recognition and rewards
  2. compliance
  3. staff acquisition
  4. training needs

Answer(s): D



Stakeholders can be identified in later stages of the project because the Identify Stakeholders process should be:

  1. Continuous
  2. Discrete
  3. Regulated
  4. Arbitrary

Answer(s): A

Explanation:

Process: 13.1 Identify Stakeholders
Definition: The process of identifying the people, groups, or organizations that could impact or be impacted by a decision, activity, or outcome of the project; and analyzing and documenting relevant information regarding their interests, involvement, interdependencies, influence, and potential impact on project success.
Key Benefit: The key benefit of this process is that it allows the project manager to identify the appropriate focus for each stakeholder or group of stakeholders.

Inputs
1. Project charter
2. Procurement documents
3. Enterprise environmental factors
4. Organizational process assets

Tools & Techniques
1. Stakeholder analysis
2. Expert judgment
3. Meetings

Outputs
1. Stakeholder register



A graphic display of project team members and their reporting relationships is known as a:

  1. Resource calendar.
  2. Project organization chart.
  3. Resource breakdown structure (RBS).
  4. Responsibility assignment matrix (RAM).

Answer(s): B

Explanation:

Project organization charts. A project organization chart is a graphic display of project team members and their reporting relationships. It can be formal or informal, highly detailed or broadly framed, based on the needs of the project. For example, the project organization chart for a 3,000-person disaster response team will have greater detail than a project organization chart for an internal, twenty-person project.



Which item is a cost of conformance?

  1. Training
  2. Liabilities
  3. Lost business
  4. Scrap

Answer(s): A



Which key interpersonal skill of a project manager is defined as the strategy of sharing power and relying on interpersonal skills to convince others to cooperate toward common goals?

  1. Collaboration
  2. Negotiation
  3. Decision making
  4. Influencing

Answer(s): D