An input to Close Project or Phase is:
Answer(s): A
Process: 4.6. Close Project or PhaseDefinition: The process of finalizing all activities across all of the Project Management Process Groups to formally complete the phase or project.Key Benefit: The key benefit of this process is that it provides lessons learned, the formal ending of project work, and the release of organization resources to pursue new endeavors.Inputs1. Project management plan2. Accepted deliverables3. Organizational process assetsTools & Techniques1. Expert judgment2. Analytical techniques3. MeetingsOutputs1. Final product, service, or result transition2. Organizational process assets updates
An output of the Direct and Manage Project Work process is:
Process: 4.3. Direct and Manage Project WorkDefinition: The process of leading and performing the work defined in the project management plan and implementing approved changes to achieve the project’s objectives.Key Benefit: The key benefit of this process is that it provides overall management of the project work.Inputs1. Project management plan2. Approved change requests3. Enterprise environmental factors4. Organizational process assets Tools & Techniques1. Expert judgment2. Project management information system3. MeetingsOutputs1. Deliverables2. Work performance data3. Change requests4. Project management plan updates5. Project documents updates
External organizations that have a special relationship with the enterprise and provide specialized expertise are called:
Answer(s): B
Which process involves subdividing project deliverables and project work into smaller, more manageable portions?
Process: 5.4 Create WBSDefinition: WBS is the process of subdividing project deliverables and project work into smaller, more manageable components.Key Benefit: The key benefit of this process is that it provides a structured vision of what has to be delivered.Inputs1. Scope management plan2. Project scope statement3. Requirements documentation4. Enterprise environmental factors5. Organizational process assetsTools & Techniques1. Decomposition2. Expert judgment Outputs1. Scope baseline2. Project documents updates
In a project, total float measures the: