PEOPLECERT PRINCE2-Agile-Practitioner Exam (page: 2)
PEOPLECERT PRINCE2 Agile Practitioner Project Management
Updated on: 25-Dec-2025

Which is a reason for 'blending and weaving' PRINCE2 with agile at all levels within a project?

  1. To adjust a 'command and control' culture for product delivery.
  2. Projects should be established with the intention of NOT delivering everything.
  3. To allow teams to self-organize whilst staying in control.
  4. PRINCE2 Agile is NOT a substitute for PRINCE2.

Answer(s): C

Explanation:

This approach enables teams to adopt Agile practices while maintaining the governance and structure provided by PRINCE2, promoting both flexibility and control in project delivery.



Project scenario - Get fit with football!

(
Note: The companies and people within the scenario are fictional)

Introduction

A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.

Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.

This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.

Scope

The initial scope of the project includes:

a marketing campaign to promote the event;

a celebrity to open the event;

a website to provide information about the event and handle applications;

an event village to support the 'family day out';

the training of LGA staff as volunteers to run and support the event;

back-office processes to handle the applications;

fundraising to cover the cost of the event.

The project has been set up with four work streams to deliver this work:

1. Marketing
2. Website
3. Event Village
4. Staff Training

Project Background

The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.

Timeline

An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.



Marketing - Additional information

The marketing campaign has two key areas to promote:

1. The event itself including the football tournament, event village and fundraising activities.
2. The LGA's long term aim to improve the fitness of children under the age of 16.

The Marketing Team has received some initial Scrum training but is unsure how it can be applied to their marketing work.

The Marketing Team is keen that the project manager provides them with a clear brief for the campaign before they spend too much time on it.

They have experience of working with a variety of marketing channels, although they are not sure which channel(s) will work most effectively to promote this type of event, and in particular to promote the LGA's longer term health aims.

The Marketing Team is not clear on the priority to assign to the two aims for the event.

The Marketing Team will publish advertisements and/or promotional material every week, with more information in each issue to keep the message up to date.

Nine releases are scheduled at the end of each of the nine week-long timeboxes.

The nine timeboxes within the marketing work stream are scheduled to include:

advertisements:

a radio interview;

production of a hand-out/flyer;

banners and signs to put up around the town and at the event;

the provision of a website and social media content;

promotional posters to be displayed by local businesses.

Using the Project Scenario and Marketing Additional information, answer the following question:

Which approach BEST outlines how to apply the 'continued business justification' principle during the initiation stage?

  1. Plan to publish a simple advertisement within a few days of timebox one to get feedback.
  2. Request that the Head of the LGA confirms that the funding is available.
  3. Plan a 'Design the Best Poster' competition in schools to encourage fitness awareness in children.
  4. Define a brief for the marketing campaign with costings for the use of each marketing approach.

Answer(s): B

Explanation:

Continued business justification ensures that the project remains viable throughout its life cycle. By confirming that funding is available, the project manager ensures that there are sufficient resources to support the project, aligning with the principle of maintaining justification for the project's continuation.



Project scenario - Get fit with football!

(
Note: The companies and people within the scenario are fictional)

Introduction

A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.

Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.

This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.

Scope

The initial scope of the project includes:

a marketing campaign to promote the event;

a celebrity to open the event;

a website to provide information about the event and handle applications;

an event village to support the 'family day out';

the training of LGA staff as volunteers to run and support the event;

back-office processes to handle the applications;

fundraising to cover the cost of the event.

The project has been set up with four work streams to deliver this work:

1. Marketing
2. Website
3. Event Village
4. Staff Training

Project Background

The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.

Timeline

An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.



Marketing - Additional information

The marketing campaign has two key areas to promote:

1. The event itself including the football tournament, event village and fundraising activities.
2. The LGA's long term aim to improve the fitness of children under the age of 16.

The Marketing Team has received some initial Scrum training but is unsure how it can be applied to their marketing work.

The Marketing Team is keen that the project manager provides them with a clear brief for the campaign before they spend too much time on it.

They have experience of working with a variety of marketing channels, although they are not sure which channel(s) will work most effectively to promote this type of event, and in particular to promote the LGA's longer term health aims.

The Marketing Team is not clear on the priority to assign to the two aims for the event.

The Marketing Team will publish advertisements and/or promotional material every week, with more information in each issue to keep the message up to date.

Nine releases are scheduled at the end of each of the nine week-long timeboxes.

The nine timeboxes within the marketing work stream are scheduled to include:

advertisements:

a radio interview;

production of a hand-out/flyer;

banners and signs to put up around the town and at the event;

the provision of a website and social media content;

promotional posters to be displayed by local businesses.

Using the Project Scenario and Marketing Additional information, answer the following question:

The project manager recommends that Stage 2 should be broken down further with more stage boundaries linked to the weekly publication of a newspaper advertisement.

Using the Timeline, which statement BEST evaluates this proposal in relation to the 'manage by stages' principle?

  1. It applies the principle well because short stage boundaries provide more opportunity for inter- team collaboration.
  2. It applies the principle well because short stage boundaries will enable the project to fail-fast and learn-fast.
  3. It applies the principle poorly because stage boundaries should be set at the beginning of each new timebox.
  4. It applies the principle poorly because the stage boundaries should typically be monthly on a three-month project.

Answer(s): B

Explanation:

The 'manage by stages' principle emphasizes breaking the project into manageable stages to assess progress and adapt as necessary. By creating shorter stage boundaries linked to the weekly publication of advertisements, the project can quickly identify issues and adjust strategies, fostering a learn-fast approach.



Project scenario - Get fit with football!

(
Note: The companies and people within the scenario are fictional)

Introduction

A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.

Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.

This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.

Scope

The initial scope of the project includes:

a marketing campaign to promote the event;

a celebrity to open the event;

a website to provide information about the event and handle applications;

an event village to support the 'family day out';

the training of LGA staff as volunteers to run and support the event;

back-office processes to handle the applications;

fundraising to cover the cost of the event.

The project has been set up with four work streams to deliver this work:

1. Marketing
2. Website
3. Event Village
4. Staff Training

Project Background

The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.

Timeline

An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.



Marketing - Additional information

The marketing campaign has two key areas to promote:

1. The event itself including the football tournament, event village and fundraising activities.
2. The LGA's long term aim to improve the fitness of children under the age of 16.

The Marketing Team has received some initial Scrum training but is unsure how it can be applied to their marketing work.

The Marketing Team is keen that the project manager provides them with a clear brief for the campaign before they spend too much time on it.

They have experience of working with a variety of marketing channels, although they are not sure which channel(s) will work most effectively to promote this type of event, and in particular to promote the LGA's longer term health aims.

The Marketing Team is not clear on the priority to assign to the two aims for the event.

The Marketing Team will publish advertisements and/or promotional material every week, with more information in each issue to keep the message up to date.

Nine releases are scheduled at the end of each of the nine week-long timeboxes.

The nine timeboxes within the marketing work stream are scheduled to include:

advertisements:

a radio interview;

production of a hand-out/flyer;

banners and signs to put up around the town and at the event;

the provision of a website and social media content;

promotional posters to be displayed by local businesses.

Using the Project Scenario and Marketing Additional information, answer the following question:

The senior user has specified a second charity to which any proceeds should be donated. All marketing material to be used from now onwards must promote the new charity. Banners promoting only the first charity have already been produced, delivered and approved in a previous timebox. The effort to add the new logo to the existing banners is low.

How should the Marketing Team respond to this change with respect to the banners already created?

  1. Handle it at the detailed level using the quality criteria in the product description for the banner.
  2. Treat it as an item NOT meeting the specification which the banner supplier should rectify.
  3. Escalate it to the project board as a request to change the detail of an existing product.
  4. Address it when planning and prioritizing the work in the current or next timebox.

Answer(s): D

Explanation:

Since the effort to add the new logo is low, it is efficient to incorporate this change during the planning and prioritization of tasks for the current or next timebox. This allows the team to adapt to the new requirement without needing to escalate or disrupt the project flow significantly.



Project scenario - Get fit with football!

(
Note: The companies and people within the scenario are fictional)

Introduction

A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.

Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.

This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.

Scope

The initial scope of the project includes:

a marketing campaign to promote the event;

a celebrity to open the event;

a website to provide information about the event and handle applications;

an event village to support the 'family day out';

the training of LGA staff as volunteers to run and support the event;

back-office processes to handle the applications;

fundraising to cover the cost of the event.

The project has been set up with four work streams to deliver this work:

1. Marketing
2. Website
3. Event Village
4. Staff Training

Project Background

The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.

Timeline

An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.



Marketing - Additional information

The marketing campaign has two key areas to promote:

1. The event itself including the football tournament, event village and fundraising activities.
2. The LGA's long term aim to improve the fitness of children under the age of 16.

The Marketing Team has received some initial Scrum training but is unsure how it can be applied to their marketing work.

The Marketing Team is keen that the project manager provides them with a clear brief for the campaign before they spend too much time on it.

They have experience of working with a variety of marketing channels, although they are not sure which channel(s) will work most effectively to promote this type of event, and in particular to promote the LGA's longer term health aims.

The Marketing Team is not clear on the priority to assign to the two aims for the event.

The Marketing Team will publish advertisements and/or promotional material every week, with more information in each issue to keep the message up to date.

Nine releases are scheduled at the end of each of the nine week-long timeboxes.

The nine timeboxes within the marketing work stream are scheduled to include:

advertisements:

a radio interview;

production of a hand-out/flyer;

banners and signs to put up around the town and at the event;

the provision of a website and social media content;

promotional posters to be displayed by local businesses.

Using the Project Scenario and Marketing Additional Information, answer the following question:

For which marketing product would a quality method of automated test-driven development be MOST suited?

  1. The newspaper advertisements.
  2. The banners for the Event Village.
  3. The text and links for the website.
  4. The radio interview.

Answer(s): C

Explanation:

Automated test-driven development (TDD) is particularly well-suited for digital products like website content, where code and links can be continuously tested for functionality and correctness. This approach allows for rapid iterations and ensures that updates do not introduce errors, making it ideal for maintaining the quality of web content.



Viewing Page 2 of 11



Share your comments for PEOPLECERT PRINCE2-Agile-Practitioner exam with other users:

Nizam 6/16/2023 7:29:00 AM

I have to say this is really close to real exam. Passed my exam with this.
EUROPEAN UNION


poran 11/20/2023 4:43:00 AM

good analytics question
Anonymous


Antony 11/23/2023 11:36:00 AM

this looks accurate
INDIA


Ethan 8/23/2023 12:52:00 AM

question 46, the answer should be data "virtualization" (not visualization).
Anonymous


nSiva 9/22/2023 5:58:00 AM

its useful.
UNITED STATES


Ranveer 7/26/2023 7:26:00 PM

Pass this exam 3 days ago. The PDF version and the Xengine App is quite useful.
SOUTH AFRICA


Sanjay 8/15/2023 10:22:00 AM

informative for me.
UNITED STATES


Tom 12/12/2023 8:53:00 PM

question 134s answer shoule be "dlp"
JAPAN


Alex 11/7/2023 11:02:00 AM

in 72 the answer must be [sys_user_has_role] table.
Anonymous


Finn 5/4/2023 10:21:00 PM

i appreciated the mix of multiple-choice and short answer questions. i passed my exam this morning.
IRLAND


AJ 7/13/2023 8:33:00 AM

great to find this website, thanks
UNITED ARAB EMIRATES


Curtis Nakawaki 6/29/2023 9:11:00 PM

examination questions seem to be relevant.
UNITED STATES


Umashankar Sharma 10/22/2023 9:39:00 AM

planning to take psm test
Anonymous


ED SHAW 7/31/2023 10:34:00 AM

please allow to download
UNITED STATES


AD 7/22/2023 11:29:00 AM

please provide dumps
UNITED STATES


Ayyjayy 11/6/2023 7:29:00 AM

is the answer to question 15 correct ? i feel like the answer should be b
BAHRAIN


Blessious Phiri 8/12/2023 11:56:00 AM

its getting more technical
Anonymous


Jeanine J 7/11/2023 3:04:00 PM

i think these questions are what i need.
UNITED STATES


Aderonke 10/23/2023 2:13:00 PM

helpful assessment
UNITED KINGDOM


Tom 1/5/2024 2:32:00 AM

i am confused about the answers to the questions. do you know if the answers are correct?
KOREA REPUBLIC OF


Vinit N. 8/28/2023 2:33:00 AM

hi, please make the dumps available for my upcoming examination.
UNITED STATES


Sanyog Deshpande 9/14/2023 7:05:00 AM

good practice
UNITED STATES


Tyron 9/8/2023 12:12:00 AM

so far it is really informative
Anonymous


beast 7/30/2023 2:22:00 PM

hi i want it please please upload it
Anonymous


Mirex 5/26/2023 3:45:00 AM

am preparing for exam ,just nice questions
Anonymous


exampei 8/7/2023 8:05:00 AM

please upload c_tadm_23 exam
TURKEY


Anonymous 9/12/2023 12:50:00 PM

can we get tdvan4 vantage data engineering pdf?
UNITED STATES


Aish 10/11/2023 5:51:00 AM

want to clear the exam.
INDIA


Smaranika 6/22/2023 8:42:00 AM

could you please upload the dumps of sap c_sac_2302
INDIA


Blessious Phiri 8/15/2023 1:56:00 PM

asm management configuration is about storage
Anonymous


Lewis 7/6/2023 8:49:00 PM

kool thumb up
UNITED STATES


Moreece 5/15/2023 8:44:00 AM

just passed the az-500 exam this last friday. most of the questions in this exam dumps are in the exam. i bought the full version and noticed some of the questions which were answered wrong in the free version are all corrected in the full version. this site is good but i wish the had it in an interactive version like a test engine simulator.
Anonymous


Terry 5/24/2023 4:41:00 PM

i can practice for exam
Anonymous


Emerys 7/29/2023 6:55:00 AM

please i need this exam.
Anonymous