The formula to calculate the Point of Total Assumption (PTA) is:

  1. PTA = (Floor price ­ Target price / seller share ratio) + Target cost
  2. PTA = (Target price ­ Ceiling price / Buyer share ratio) + Target cost
  3. PTA = (Target price ­ Ceiling price / seller share ratio) + Target cost
  4. PTA = (Ceiling price ­ Target price / Buyer share ratio) + Target cost

Answer(s): D



Liquidated damages are a negative incentive (penalty) for:

  1. Over budget
  2. Late delivery
  3. Do not achieve requirements
  4. Requirements gap

Answer(s): B



A critical aspect in the success of performance-based incentive contracting is called:

  1. Creativity
  2. Timeliness
  3. Achievement
  4. Standardization

Answer(s): A



An agreement on a set of criteria and procedures to be applied by the buyer in determining how well the seller has performed and how much fee the seller has earned is called:

  1. Inducement plans
  2. Awarded-plans
  3. Award-free plans
  4. Contract incentive plans

Answer(s): C



A fixed fee that the seller will earn no matter how its performance is evaluated in known as:

  1. incurred fee
  2. award fee
  3. period fee
  4. base fee

Answer(s): D



Which contracts allow overrun or under-run sharing of cost through a predetermined formula for fee adjustments that apply to incentives for cost category contracts?

  1. fixed price incentive
  2. cost-plus-incentive fee
  3. special incentive fee
  4. pros and cons of award fee

Answer(s): B



Which of the following is Correct?

  1. cost-plus-award fee contracts include subjective incentives, in which the profit the seller earns depends on how well the seller satisfies a buyer's subjective desires.
  2. cost-plus-incentive fee contracts include subjective incentives, in which the profit the seller earns depends on how well the seller satisfies a buyer's objective desires.
  3. cost-plus-award fee contracts include objective incentives, in which the profit the buyer earns depends on how well the seller satisfies a buyer's objective desires.
  4. cost-plus-incentive fee contracts include objective incentives, in which the profit the buyer earns depends on how well the buyer satisfies a seller's subjective desires.

Answer(s): A



Time and Material contracts typically involve higher levels of risks for sellers.

  1. True
  2. False

Answer(s): B



Share your comments for NCMA CPCM exam with other users:

M
Muhammad Rawish Siddiqui
12/5/2023 12:38:00 PM

question # 142: data governance is not one of the deliverables in the document and content management context diagram.

A
al
6/7/2023 10:25:00 AM

most answers not correct here

B
Bano
1/19/2024 2:29:00 AM

what % of questions do we get in the real exam?

O
Oliviajames
10/25/2023 5:31:00 AM

i just want to tell you. i took my microsoft az-104 exam and passed it. your program was awesome. i especially liked your detailed questions and answers and practice tests that made me well-prepared for the exam. thanks to this website!!!

D
Divya
8/27/2023 12:31:00 PM

all the best

K
KY
1/1/2024 11:01:00 PM

very usefull document

A
Arun
9/20/2023 4:52:00 PM

nice and helpful questions

J
Joseph J
7/11/2023 2:53:00 PM

i found the questions helpful

M
Meg
10/12/2023 8:02:00 AM

q 105 . ans is d

N
Navaneeth S
7/14/2023 7:57:00 AM

i have interest to get a sybase iq dba certification

A
Aish
10/11/2023 5:27:00 AM

want to pass exm.

A
Anonymous
6/12/2023 7:23:00 AM

are the answers correct?

K
Kris
7/7/2023 9:43:00 AM

good morning, could you please upload this exam again, i need it to test my knowledge in sd-wan with version 7.0.

M
Meghraj mali
10/7/2023 1:47:00 PM

very nice question

N
Noel
11/1/2022 9:14:00 PM

i have learning disability and this exam dumps allowed me to focus on the actual questions and not worry about notes and the those other study materials.

J
Jas
10/25/2023 6:01:00 PM

165 should be apt

N
Neetu
6/22/2023 8:41:00 AM

please upload the dumps, real need of them

M
Mark
10/24/2023 1:34:00 AM

any recent feeedback?

G
Gopinadh
8/9/2023 4:05:00 AM

question number 2 is indicating you are giving proper questions. observe and change properly.

S
Santhi
1/1/2024 8:23:00 AM

passed today.40% questions were new.litwere case study,lots of new questions on afd,ratelimit,tm,lb,app gatway.got 2 set series of questions which are not present here.questions on azure cyclecloud, no.of vnet/vms required for implimentation,blueprints assignment/management group etc

R
Raviraj Magadum
1/12/2024 11:39:00 AM

practice test

S
sivaramakrishnan
7/27/2023 8:12:00 AM

want the dumps for emc content management server programming(cmsp)

A
Aderonke
10/23/2023 1:52:00 PM

brilliant and helpful

A
Az
9/16/2023 2:43:00 PM

q75. azure files is pass

K
ketty
11/9/2023 8:10:00 AM

very helpful

S
Sonail
5/2/2022 1:36:00 PM

thank you for these questions. it helped a lot.

S
Shariq
7/28/2023 8:00:00 AM

how do i get the h12-724 dumps

A
adi
10/30/2023 11:51:00 PM

nice data dumps

E
EDITH NCUBE
7/25/2023 7:28:00 AM

answers are correct

R
Raja
6/20/2023 4:38:00 AM

good explanation

B
BigMouthDog
1/22/2022 8:17:00 PM

hi team just want to know if there is any update version of the exam 350-401

F
francesco
10/30/2023 11:08:00 AM

helpful on 2017 scrum guide

A
Amitabha Roy
10/5/2023 3:16:00 AM

planning to attempt for the exam.

P
Prem Yadav
7/29/2023 6:20:00 AM

pleaseee upload

AI Tutor 👋 I’m here to help!