ScenarioAssume you are working as a Test Manager in a startup organization. You are creating a system for carrying employee’s surveys for small to medium-sized companies. This application can be accessed online.The companies using this software will have to enroll first and create different buttons for each department of the organization. The company also defines different parameters for rating each department.After each survey, the system calculates the number of people who participated in the survey and also calculates the overall rating on the scale of 5 for each department. The software ranks the department in ascending order and the report is sent to the higher management or to the mail id exclusively specified in the software.The marketing team is making heavy efforts to sell the software and is also working on giving out discounts. According to them, the software will be high on performance and provide quick service.As of now, the requirement is finalized and development has begun. The companies who intend to use this software have 3 months’ time to enroll themselves.The organization decides to use cloud computing to host this service. There would not be any hardware other than normal office computers. Every developer, tester, and other people involved will be using simple desktops to use those services. All the standards will be adhered to by building the system.After doing a Risk Analysis, the below risk item was identified.“The customized company’s button is not redirecting to the correct organization”.You are using traceability metrics to track all the risk items. Which of the following positive test case is complete and enough to cover the above risk item?
Answer(s): C
Non-functional testing activities proper planning and control. Which of the below factor should be considered for planning the Nonfunctional activities? Select any 2.
Answer(s): B,C
Scenario:Assume you are working as a Test Manager in a startup organization. You are creating a system for carrying employee’s surveys for small to medium-sized companies. This application can be accessed online.The companies using this software will have to enroll first and create different buttons for each department of the organization. The company also defines different parameters for rating each department.After each survey, the system calculates the number of people who participated in the survey and also calculates the overall rating on the scale of 5 for each department. The software ranks the department in ascending order and the report is sent to the higher management or to the mail id exclusively specified in the software.The marketing team is making heavy efforts to sell the software and is also working on giving out discounts. According to them, the software will be high on performance and provide quick service.As of now, the requirement is finalized and development has begun. The companies who intend to use this software have 3 months’ time to enroll themselves.The organization decides to use cloud computing to host this service. There would not be any hardware other than normal office computers. Every developer, tester, and other people involved will be using simple desktops to use those services. All the standards will be adhered to by building the system.While following a Risk-Based testing strategy, the probability and the impact of the risk are both assessed on a scale of 5 (5 is low and 1 is high). Consider the below risk identified:“The customized company’s button is not redirecting to the correct organization”.The stakeholders have identified the possibility of this risk occurrence is at the medium level. Considering this situation, which of the statement is true?
Answer(s): B
Which of the two techniques are NOT a practical technique of Test Prioritization and Effort Estimation?
Answer(s): B,E
Which of the statements listed below about testing metrics is true?
Answer(s): D
Share your comments for ISTQB ATM exam with other users:
22. if you need to make sure that one computer in your hot-spot network can access the internet without hot-spot authentication, which menu allows you to do this? answer is ip binding and not wall garden. wall garden allows specified websites to be accessed with users authentication to the hotspot
is question 1 correct?
good content
manged to pass the exam with this exam dumps.
good questions
can we please have the latest exam questions?
please help with jn0-649 latest dumps
please i need this dump. thanks
i have to take the aws certified developer - associate dva-c02 in the next few weeks and i wanted to know if the questions on your website are the same as the official exam.
all questions are more important
ques 4 answer should be c ie automatically recover from failure
very very useful page
the exams are giving me an eye opener
3rd so far, need to cover more
aligns with the pecd notes
question 4: b securityadmin is the correct answer. https://docs.snowflake.com/en/user-guide/security-access-control-overview#access-control-framework
kindly please share dumps
it is very useful, thank you
need safe rte dumps
can you upload the cis - cpg dumps
q6 = 1. download odt application 2. create a configuration file (xml) 3. setup.exe /download to download the installation files 4. setup.exe /configure to deploy the application
great material
could you please upload sap c_arsor_2302 questions? it will be very much helpful.
vraag 20c: rsa veilig voor symmtrische cryptografie? antwoord c is toch fout. rsa is voor asymmetrische cryptogafie??
so far good
question 31 has obviously wrong answers. tls and ssl are used to encrypt data at transit, not at rest.
pls provide dump for 1z0-1080-23 planning exams
could you please upload the exam?
please upload this
good material
lets see if this is good stuff...
useful information
intéressant
thank you for making the interactive questions